HomeMy WebLinkAboutCorrespondence - 940 JOHNSON STREET 10/24/2011 DelleChiaie, Pamela
From: Sawyer, Susan
Sent: Monday, October 24, 2011 11:51 AM
To: DelleChiaie, Pamela
Cc: 'Marianne Peters'
Subject: RE: Soil Testing for 940 Johnson scheduled for Mon/Nov 7th @ 9:30
1 Suspect this means we will have a plan in here by Nov 2"'1 and then we'll be the bad guys. I had also had a good
conversation with the son of the deceased 2 weeks ago and told him they should focus on selling with an approved plan,
as the end of the season is near. So as not to push everyone. We will not Push for a review just to get an installation
permit pulled by the Nov. 1.5"' deadline. if they have to come to the Nov, 17t" meeting for out of season installation, so
be it. Or even December.
`T'hx
S
From: DelleChiaie, Pamela
Sent: Monday, October 24, 2011 11:29 AM
To: 'Marianne Peters'
Cc: Sawyer, Susan
Subject: RE: Soil Testing for 940 Johnson scheduled for Mon/Nov 7th @ 9:30
Thank you!!! (
&a Rwwa,
Pamela DelleCbiaiie
From: Marianne Peters IMa ILQLol
-pe ,L t o
qCaLr3iLillrive
�--rCQ1L!MU1-JnQ2mMJ
Sent: Monday, October 24, 2011 11:27 AM
To: DelleChiaie, Pamela; Sawyer, Susan; Grant, Michele
Cc: WMLdu L Qs
_Lie0d comcast.net
'Randy Burley'
Subject: RE: Soil Testing for 940 Johnson scheduled for Mon/Nov 7th @ 9:30
Rescheduled for October 31,1, same time; all moved up!
-----Original Appointment-----
From: DelleChiaie, Pamela LM:ciLI(C),Ijdel.t C_b c toWLiofoio�thandover.com
Sent: Monday, October 24, 2011 10:13 AM
To: 'Daniel Ottenheimer'; 'Isaac Rowe'; 'Peters, Marianne'; 'Randy Burley'; Sawyer, Susan
Subject: Soil Testing for 940 Johnson scheduled for Mon/Nov 7th @ 9:30
When: Monday, November 07, 20119:30 AM-12:30 PM (GMT-05:00) Eastern Time (US &Canada).
Where: 940 Johnson Street, North Andover, MA 01845
Monday—October 24,2011-10:12 a.m.
Hello Mill River,
I received a call from- 603-315-3864—David Taylor—Trustee for 940 Johnson Street—who called to request
that this soil testing be scheduled ASAP, and not wait until Nov.T1. Is there anyway in your schedule that this
could happen? Bill Dufresne told Mr.Taylor that it had to do with Mill River's availability. Please let me know
if any sooner scheduling is possible. Thank you.
Pamela
NAHD
------------
From: Marianne Peters fmpeters@millriverconsulting.com]
Sent: Friday,October 21,20111:41 PM
To: DelleChiaie, Pamela;Sawyer,Susan;Grant, Michele
Cc: 'Randy Burley';'Isaac Rowe'
Subject: Soil Testing for 940 Johnson scheduled for Mon/Nov 7th @ 9:30
Soil testing for 940 Johnson w/Bill Dufresne scheduled for Monday, November 71, @ 9:30 with Randy.
Marianne Peters
Office Manager
6 Sargent Street
Gloucester, MA 01930-2719
Phone: 978-282-0014
Fax: 978-282-1318
www..-rn il I rive rcons,g1tbg...go al
,LoRettL
�@.rttiliCiy!g�r(on�iult,i _ .com
qq__
Please note the MaSS,1GhL1SettS Secretary of State's office has determined that rnost ernails to and from municipal offices and officials are Public records,
For more information please refer to: htjr.L.,t wvu,sec s at� q �j rn.
t P�qj /Lreid��h
Please consider the environment before printing this email,
<< Message:Soil Testing for 940 Johnson scheduled for Mon/Nov 7th @ 9:30(23.0 KB)>>
2
t`
•
North Andover Health Department
(ommunity Developinent Division
December 12, 2011
Vladimir Nemchenok
c/o: Bill Dufresne
Merrimack Engineering Services
66 Park Street
Andover, MA 01810
Re: Subsurface Sewage Disposal System Plan for 940 Johnson Street, Mai) 107A, Lot 91
Dear Mr. Nemchenok:
The proposed wastewater system design plan for the above site dated November 13, 2011 has
been reviewed. Unfortunately, the plan cannot be approved until the following items are
corrected. The specific section in Title 5: 310 CMR 15.000, or North Andover regulation that is
not met by this design follows each item where applicable.
1, A Local Upgrade Approval for only having one test pit in the soil absorption system area
must be requested. Please submit the Form 9A Local Upgrade Approval request or revise
the design plan(3 10 CMR 15,405(1)(k)).
2. A local variance will be required to be requested to have the tank(s) less than 75' to the
wetland resource area NA Table 1. Please submit request to be on the next BOH meeting.
List all variance and LUA's requested.
3. Please note all LUA and local variance requests on plan NA 3.2
4. The notation in the "Deep Test Results" calls for the C material in T-1 to be GR. SL. The
soil logs call for a GR. LS. Please clarify
5. Please illustrate the distance from the pool to the tank (10'min. or LUA)
6. Please provide a pump curve 15.220(4)(r)
Page 1 of 2
North Andover health Department, 1600 ()sgood Street, Building 20, Suite 2-36,
North Andover, MA 01845 phone: 978.688,9540 'ax: 978.688.8476
7. The soil log and "Deep Test Results" call for the ground elevation of T-1 to be 98.8, but
there appears to be a spot grade of 99x9 right next to the test pit on the site plan. Also,
scaling between the contours it appears the 99.9 is more accurate of a grade than 98.8.
Please re-evaluate design parameters.
8. In the "Design Calculations"the perc rate is referenced to be, "3 M.P.I. *SEE SIEVE
ANALYSIS BY TERRA FILTER". The sieve analysis reference appears to be have been
inadvertently copied from another plan, Please clarify.
Please note the reviewer has observed a repeated problem in the field, and has the following
recommendation, though not required by the code. Depict a gas baffle 15,227(4); while Title 5
says for an effluent filter or gas baffle, the preference is for both, for the reason that if the
effluent filter is removed and not reinstalled, the gas baffle feature is also lost. This is not a
deficiency only an observation.
Please feel free to contact the office with any questions you may have. We look forward to
working with you to obtain a wastewater treatment and dispersal system which will be in
compliance with all regulations and assure protection of public health and the environment of
North Andover.
Sincerely,
S/u/tY. Sawyer, HS/RV,/,",
is Health Director
cc: File
Homeowners—CARROLL H & MARY A TAYLOR TRUSTEE, TAYLOR FAMILY
TRUST
Attach: Page 6 of the local septic regulations
Page 2 of 2
North Andover Health Department, 1600 Osgood Street, Building 20, Suite 2-36,
Noilli Andover, MA 01845 Phone: 978.688.9540 Fax: 978.688.8476
3A Design plans for a tight tank shall require approval of the Board of Health at a public
hearing,
3,5 All drilled or dug wells shall meet all setbacks and be considered potable water supply
wells.
3,6 Wetlands resource area setbacks as described in these regulations and in Title 5 are to be
measured from the resource as may be jurisdictional under federal, state or North Andover
requirements,
3.7 No well shall be constructed or placed within the distance specified In Table 1
from the component of an existing onsite wastewater system.
3.8 If a variance to the North Andover Board of Health regulations,Title 5 Local Upgrade
Approval and/or Title 5 variance can be met with the incorporation of a Massachusetts
Department of Enviromnental Protection(DEP)-approved device which reduces wastewater to
levels below 30 mg/L 130D and 30 rng/L TSS, then the design plan can be approved by the
Health Department and does not require a bearing before the Board of Health unless otherwise
required.
3.9 Per the current fee schedule,the fee for the onsite wastewater system plan review shall be
paid upon initial submission and will cover the first revision if applicable, Each subsequent
revision will require a separate fee.
TABLE 1 -SETBACK DISTANCE TABLE.
Resource Build Septic Tanks, Prnnp Tanks, Soil
ing Treatttiont Units,Tight Absorption
Sewer Tanks,Grease Traps(feet) System (feet)
Deck on footin s _ 5 10
Tributaries to Surface
Water Supply 325 325
Watercourses or Wetland
Resource Areas 75 100
Wetlands Bordering .
Surface 150 150
Water Supply or Tributary
in watershed district)
Private Well 50
(setbacks tame supplemental to MAD EP 3.10CMR 15)
Pagcg
j MERRIMACK ENGINEERING SERVICES, INC.
` PROFESSIONAL ENGINEERS LAND SURVEYORS PLANNERS
eceM e 8TAETNANDOVER, MA 01810• (978)475-3555,373-5721 • FAX(978)475-1448 • E-MAIL lnfo @merrimackengineering.com
Susan Sawyer ro „
Public Health Director
1600 Osgood Street
Building 20, Suite 2-36 ,�a
North Andover, MA 01845
3O\NN'i£
RE: 940 Johnson Street 'ti � °" � °
wAPPW--
Dear Ms. Sawyer,
We received your review letter dated 12-12-11 for the above referenced site.
We revised the plan with regards to item 41 through 6 and #8.
With regard to item#7, the reviewer is incorrect. T-1 was performed on the side of the lot
which had steep slopes and undulating topography with several small knolls and hills.
The test pit was performed in a saddle at the base of a knoll. Please note that equally as
close to T-1 is a spot elevation of 98.4. Why would the reviewer not assume that the test
pit was closer in elevation to that spot grade?
The fact is that the slope is not consistent between the two contour lines and so it is
incorrect to interpolate grades between the two contours. The grade in reality drops
quickly then flattens before T-1 so the elevation of T-1 is closer in value to spot elevation
98.4 than it is to elevation 99.9 as suggested by the reviewer. Additionally we checked
our survey notes and confirmed the elevation.
Please note that we revised the plan such that a local variance is no longer required for
the setback distance to a wetland for the pump tank or the septic tank. We did however
request an additional LUA for the distance from the septic tank to the foundation from 10
ft. to 7 ft. All LUA requests are noted on the revised plan.
We feel we have adequately addressed your concerns and respectfully request that the
plans be approved as re-submitted.
Yours truly, .v
William Dufresne
Merrimack Engineering services.