HomeMy WebLinkAbout1982-05-17May 17, 1982
Regular Meeting
The PLANNING BOARD held a regular meeting on Monday evening, May 17,
1982 in the Town Office Meeting Room with the following members
present and voting: Michael P. Roberts, Vice Chairman~ Walter R.
McDonough, Clerk; and Erich W. Nitzsche. Town Planner Susan M.
St. Pierre and Building Inspector Charles Foster were also present.
PLANS NOT ~E~O,~IRING APPROVAL
Tabled
TRAFALGAR ESTATES Release of Covenant
Mr. Ambrose Flatley was present. He submitted a Letter of Credit
and discussed a completion date with the Board. Susan St. Pierre
warned the Board no.t to accpet the Letter of Credit without a
completion date or making the completion date in line with the
date on the Letter. Also, a public hearing is necessary for a
modification. Member Roberts suggested accepting the Letter of
Credit and set the completion date at the next meeti:ng when the
Highway Surveyor and the Board of Public Works have been notified.
Developer Scott Follansbee (not for Trafalgar Estates) added that
the Highway Surveyor does not want to have a subdivision bonded or
have one completed when the work is still going on. It is difficult
for a developer because the Planning Board holds such a high bond,
five to six times the cost of the work.
Member McDonough suggested a new formula be looked into to correct
this problem.
MOTION:
by Mr. McDonough that pursuant to Section 81-W of M.G.L.
the Planning Board hold a public hearing on June 7, 1982
for the purpose of modifyin? the approval of the Trafalgar
Estates Subdivision and accept the Letter of Credit with
the condition that the binder coat be applied no later
than September 1, 1982 and that all work be completed by
April 1, 1983 unless a Letter of Credit for the balance
is renewed.
SECOND:
VOTE:
MOTION:
SECOND~
VOTE:
by Mr. Nitzsche
Unanimous - motion carries
by Mr. Nitzsche to release the lots as stipulated in the
Release of Covenant dated May 17, 1982 and release Lots
4 through 34 and 39 and 40.
by Mr. McDonough
Unanimous - motion carries.
May 17, 19~2 -2- Regular Meeting
BENJAMIN FARN~U~ - Request for approval to re-petition the Board
of Appeals
Atty. James Hyde was present for the petitioner, All discussions
have taken place at previous meetings.
An affirmative vote from Chairman Hedstrom was submitted in his
absence.
MOTION:
by ~Ir. I.~cDonough that the Planning Board forward a
favorable recommendation to the Board of Appeals to
re-hear the application of Benjamin Farnum.
SECOND: by Mr. Nitzsche
VOTE: Unanimous - motion carries
WILLOWS INDUSTRIAL PARK - set back problem for Lot W (Advanced
Reproduction)
Atty. Joseph Grasso was present representing abutters to Lot W
Condon and Goodrich.
Atty. Grasso summarized what was discussed at the previous meeting.
He also presented a sketch of the premises and stated that as the
development was getting underway, the abutters appeared because
there was a question of where the lines were to be drawn and the
location of the zoning lines. As part of the process, the Planning
Board requested a letter from the Building Inspector in which he
stated that lines were to be measured from property lines. On
the question of zoning, it is up to the Building Inspector, the
Board of Appeals, or Superior Court. However, the problem with
Lot W is for the Planning Board.
A letter from Town Counsel dated Hay 17, 1982 was read and placed
on file. Town Counsel stated in his letter that the Planning Board
should take no action.
Building Inspector Foster stated that he did not handle Lot W
according to his letter. Where the zoning line is in the sub-
division, it does not deal with the particular question that we
are discussing. According to the Zoning By Law, the additional
fifty foot buffer is only effective when the land is adjacent
to Residential land. Lot W abuts Industrial land and it belongs
to the abutters.
Foster then presented a plot plan from a registered land surveyor.
Atty. Grasso reminded the Board that the Condon's appeared at the
public hearings for the subdivision to insure that the buildings
were located at a distance to insure that this would not happen.
The Planning Board assured them that the buildings would be 100'
from their property line.
May 17, 1982 -3- Regular Meeting
Willows Industrial Park continued
Building Inspector Foster stated he believes the Plannino Board
addressed the situation incorrectly by not naming this particular
lot in their decision. He added that the building is now 85%
complete.
Atty. Grasso suggested an adjoining of the building and stated
that the Planning Board has the power to revocation of the building
permit.
Member Roberts reminded the Board that Town Counsel advised no
action and suggested that Atty. Grasso contace Town Counsel. He
also asked if the builder and the abutters could work something
out.
Mr. )like Nicolosi, the builder, said that the land was surveyed
twice and conformed to both state and local regulations. He asked
the abutters why they waited so long to come forward.
Mr. Charles Nigrelli, owner of the property, stated that there
was no deliberate intention of causing any problems. He maintained
the 100' setback from the Reisdential district. He further stated
that one cannot see their (the abutters') homes from his new
building because of trees.
Atty. Grasso and Mr. Nigrelli agreed to discuss the matter and
Member Roberts asked to have the Planning informed of any new
developments.
LETTER FROM MRS. SPRACKLIN HAY)~EADOW ROAD - Lots 16, 18, and 20
A letter from Mrs. Carol Spracklin, dated April 21, 19~2 was read
and placed on file.
Hrs. Spracklin was present and explained that there is a very
dangerous situation on Haymeadow Road. There is a large hole
and a cliff. She has been before the Conservation Commission
and they said it is not their problem.
Scott Follansbee suggested the Bo-ard contact Land Vest, the present
owners of Lots 16, 18, and 20.
The Board instructed the Town Planner to write a letter to Land
Vest, 20 Kilby Street, Boston, Mass., Attention Mr. Richard Perkins,
and send a carbon copy to Mrs. Spracklin.
REQUEST FROM FRANK GELINAS PATTON ROAD FOR SALEm FOSEST II
MOTION:
SECOND:
VOTE;
by Mr. Nitzsche to accept the letter from Frank Gelinas
dated May 17, 1982 regarding the justification on the
waiver on Salem Forest II.
by Mr. McDonough
Unanimous ~ motion carries
May 17, 1982 ~4- Regular Meeting
SUBDIVISION UPDATE
Greenwood East - completion date September 1, 1982
Carleton Farms East - completion date ? October 1, 1982
Atty. Victor Hatem was present. He stated the outlook is better
now. He will formalize it in a letter of understanding and hope
for a resolution.
The Greenwood East bond was already enforced by the Board but is
pending. The update should be in the field,
On Carleton Farms East - it has been completed but there is a
question of whether the Highway Surveyor wants th¢inal coat on.
The houses should be completed in the fall.
The Board placed both items on the next agenda.
Hardtcourt Estates completion date June 1, 1982
Scott Follansbee was present and stated that there are 20 lots,
with 8 remaining and no construction. The drainage is 100% complete
with the exception of the gas and oil trap cover. The binder is
on, the water is in, and there has been a substantial amount of
damage done to the shoulders from seeding, He further stated that
he has been told that, prior to the installation of gas and oil
traps and other things, that the Highway Surveyor would not
release any money until the project is completed. He can complete
it by June 1, 1982, which is the completion date, but he thinks
that would be foolish because time frames that seemed reasonable
a year ago are not reasonable today. Also, there are 2 lots which
will not be built on this year. He thinks the completion date should
be extended and a field inspection should be done.
MOTION:
by Mr. HcDonough to extend the completion date to July 1,
1982 for the Hardtcourt Estates subdivision subject to a
field inspection.
SECOND: by Mr. Nitzsche
Discussion: Town Planner St. Pierre wants Mr. Foll-ansbee's request
in writing.
VOTE: Unanimous - motion carries.
Ingalls Crossing II completion date Sep6ember 24, 1982
Scott Follansbee was present and wants to extend the completion date
to Spetember of 1983. The drainage is in but not complete. The
water is not complete and the road is at gravel grade.
Continued for June 7, 1982.
May 17, 1982 -5- Regular Meeting
Subdivision update - continued
Ingalls Crossing III completion date - November 1, 1983
Scott Follansbee spoke and stated that the plans are not yet signed.
The Planner said that the dates should be revised.
Continued to June 7, 1982.
Abbott Meadows - completion date - November 1, 19A2
Scott Follansbee wants the Planning Board to come up with a new bond
figure because the binder coat is on, the water is in, and the
drainage is in. The current figure is $24,000.00. He stated that
if the figure is not changed, he will complete the subdivision 100%
and arrange a field inspection with the Highway Surveyor.
Continued to June 7, 1982.
Quail
MOTION:
Run completion date June 1, 1982
by Mr. McDonough to notify the owner of Quail Run that
the completion date is June 1, 1982 and that the required
work has not been completed. Also, it is the Planning
Board's intention to enforce the bond on June i 1982
and instruct Town Counsel of this action.
SECOND: by Mr. Nitzsche
VOTE: Unanimous motion carries.
~cky Ridge - completion date - August 1, 1982
Continued to June 7, 1982
Town Planner St. Pierre informed the Board that inter¥iews for
a new Town Planner will be held on Wednesday and invited the
members of the Board-to participate.
The meeting adjourned at 9:10 p.m.