HomeMy WebLinkAboutCCMeetingMinutes_10.12.11
Conservation Commission Meeting Minutes
October 12, 2011
Members Present:
Louis A. Napoli, Chairman,Deborah A. Feltovic, Albert P. Manzi, Jr.,
Douglas W. Saal.
Members Absent:
John T. Mabon, Vice Chairman, Joseph W. Lynch,Jr.,Sean F. McDonough.
Staff Members Present:
Jennifer A. Hughes, Conservation Administrator, Heidi M. Gaffney,
Conservation Field Inspector, Donna M. Wedge, Conservation Secretary.
Pledge of Allegiance
Meeting came to Order at:7:31 PM Quorum Present.
General Business
242-1505, COC Request, 125 Sherwood Drive (Spitzer) (The Neve-Morin Group, Inc.)
(cont. from 9/28/11)
The field inspector states the site is stable and constructed according to plan the wetland
markers are up.
A motion to grant the COC and release the bond is made by Ms. Feltovic, seconded by Mr.
Saal.
Vote unanimous.
Documents:
Letter from The Neve-Morin Group, Inc. dated 8/30/11
o
WPA Form 8A-Request for Certificate of Compliance dated 9/1/11
o
Plan of Land As-Built Site Conditions for 125 Sherwood Drive dated 8/24/11
o
prepared by The Neve-Morin Group, Inc.
Photos dated 10/12/11
o
242-1429, COC Request, 673 Great Pond Road (ICB Realty Trust) (Wetlands Preservation,
Inc.)
Geoffrey Andrews ofWetlands Preservation, Inc. was present.
The administrator statesthat thesite is stabilized and constructed according to plan.
Mr. Saal askswhythereareso many catch basins installed.
Mr. Andrews states the requirement was because of the Watershed Special Permit through
the Planning Board.
A motion to grant the COC and release the bondismade by Ms. Feltovic, seconded by Mr.
Saal.
Vote unanimous.
Documents:
Letter by Wetlands Preservation, Inc. signed by Curtis R. Young dated 9/22/11
o
WPA Form 8A-Request for Certificate of Compliance dated 9/22/11
o
Letter by Cuoco & Cormier Engineering Associates for a Watershed Special Permit
o
dated 9/19/11
As-Built Plan done by Cuoco & Cormier Engineering Associates, Inc. dated 5/25/11
o
242-482, 295 Forest Street (Lot B) (Lombard, LLC)
The field inspector statesthat this is an older fileand that the Order of Conditions was
somehow recorded twice and theoriginalOrder of Conditions expired and the project was re-
filed. An“administrative purposes only”COC was issued which referenced the new file #
242-955, but had the wrong book and page number, so wasn’t acceptable to clear the title.
242-955 was withdrawn and file number 242-985 was issued an Order of Conditions under
which the project was built and received a full COC. This request is fromthe attorneys
which are requesting corrected COC’s which properly reference the two different book and
page numbers in order toproperly clear the title. This will require two COC’s to be issued.
They have requested that the fees be waived.
Mr. Manzi states that the Order of Conditions being recorded twice as well as the lack of a
proper COC request previously is not the fault of the commission and therefore the fees
would not be waved and the COC’s can be issued when the fee of $400is received.Mr. Saal
concurs.
A motion to issue two COC’sidentifying the correct book and page numbers for 242-482
(fees to be received prior to issuance)ismade by Mr. Manzi, seconded by Mr. Saal.
Vote unanimous.
Documents:
A letter submitted from Michael E. Lombard dated 10/7/11
o
WPA Form 8A-Request for Certificate of Compliance dated 10/7/11
o
Copy of Order of Conditions reference to DEP#242-482 dated 11/22/1988
o
Discussion
242-1401, 495 Forest Street (Lot 2) (cont. from 9/28/11)
Benjamin C. Osgood, Jr. P.E. of Pennoni Associates, Inc.,Robert Innis of RLI Corporation,
and new owner Josiah E. Haley of 495 Forest Street arepresent.
Mr. Osgood states that the constructed swale hashad some erosion which has been addressed
withrip-rap. He reviews the settlement agreementand states that the contractor placed large
boulders where the fence was to be installed and wishes to leave the boulders in place in lieu
of the fence.
Mr. Osgood presents photos
Mr. Napoli states if the Conservation Commission would accept the boulder wall verses the
fence then we have to talk to Town Counsel before the ConservationCommission can make
any decision due to the settlement agreement.
The Field Inspector states that Town Counsel provided the revised copy of the settlement
agreement.
The commission discusses the stone wall and states that if the stone wall is allowed to remain
that markers should be placed along this area.
Mr. Manzi statesthat thestonewall is around the edge of the lawn for most of the property
and is a good thing.
Will also need confirmation from Natural Heritage.
Documents:
Photos submitted by Mr. Osgood
o
Settlement Agreement (as referenced in the Order of Conditions)
o
Public Hearings: 8:00 PM
Notice of Intent (NOI)
242-1531, 315 Turnpike Street (Merrimack College) (VHB, Inc.) (cont. from 9/28/11)
(Request to cont. to 10/26/11)
The administrator statesthatthe applicant requestsa continuance totheOctober 26, 2011
meeting, and that a meeting is scheduledwith Merrimack and Eggleston Environmental for
Thursday, October 13, 2011.
A motion to grant the request for a continuance totheOctober 26, 2011 meeting is made by
Ms. Feltovic, seconded by Mr. Manzi.
Vote Unanimous.
242-1523, 273 Berry Street (Quimby) (Christiansen & Sergi, Inc.) (cont. from 9/28/11)
PhilChristiansen of Christiansen & Sergi, Inc. ispresent.
The administrator states that a new planhas been submittedshowing the new no-disturbance
zone and a planting plan.The plan is similar to what was discussed at the last meeting,
giving more no-disturbance area than is required by the regulations in some locations and
less inothers.
The wall location and construction is discussed.
Mr. Christiansen requests planting requirements be determined following wall construction
A motion toaccept the waivers for 50-foot No-Disturbancezone, and 75-footNo-Build zone
from an ephemeral pool is made by Mr. Manzi, seconded by Ms. Feltovic.
Vote unanimous.
A motion to close the public hearing and issue a decision within 21 days is made by Mr.
Manzi, seconded Ms. Feltovic.
Vote unanimous.
Documents:
E/Mail from Phil Christiansen dated 10/11/11
o
Planting Plan submitted by Norse Environmental Services, Inc, dated 10/11/11
o
Revised Plans dated 9/29/11
o
242-1523, 16 Berry Street (Fiore) (Goldsmith, Prest, & Ringwall, Inc.) (cont. from 9/28/11)
No one is present for the applicant and the matter is tabled.
When the matter is taken up at the end of the meeting, the administrator states that a review
letter fromEggleston Environmentalhasjustbeenreceived.
A motion to grant a continuance to the October 26, 2011 meetingismade by Mr. Manzi,
seconded by Ms. Feltovic.
Vote unanimous.
Documents:
Review letter from Eggleston Environmental dated10/12/11
o
242-1536, 357 Candlestick Road (Gill) (LJR Engineering)
The applicantsKenneth & Pamela Connolly, Dan Gill of Earthworks, Nelson Rose of
Earthworks andLuke Roy of LJR Engineering arepresent.
Mr. Saal readsthe legal notice.
The administrator statesthatthis is an after the fact filingfor ahot tub and patiowhich have
already been installed, portions are within the 75-foot No-Build zone to a Vernal Pool.A
building permit was also not obtained.
Mr. Gill reviews how the project was started and why there were not permits.
The commission discusses a stonewall along the no-disturb area to prevent any future
encroachment.
Mr. Saal states the stonewall should be installed along the topof the slope.
Mr. Manzi states that the brush removal would have to be doneby handand thatno heavy
equipmentwill beallowed. The applicant would have to draw on the plan where the stone
wall willbe placed.
Discussion regarding the plumbing and electrical permit process
Discussion of possible need for plantings when brush removed.
The applicant requests a continuance to the October 26, 2011 meeting to make the necessary
changes to the plan.
A motion to grant the request for a continuance to the October 26, 2011 meetingismade by
Mr. Manzi, seconded by Ms. Feltovic.
Vote unanimous.
Documents:
Mandatory Pre-Filing Checklist
o
WPA Form 3-Notice of Intent Application Booklet with associated documents as well
o
as a waiver requestand additional photo and plans
Plan titled “Existing Conditions Site Plan”, prepared by LJR Engineering and dated
o
September 26, 2011
Photos dated 8/12/11 and 10/12/11
o
242-1534, 500 Great Pond Road (North Andover Country Club) (The Neve-Morin Group,
Inc.)
Greg Hochmuth of The Neve-Morin Group, Inc ispresent.
Ms. Feltovic readsthe legal notice.
The administrator statesthat prior to filing this Notice of Intent, representativesof the
Country Club met with the Planning and Conservation Departmentsto discussthis project.
Mr. Hochmuth discusses the drainage, fence and how the work will be done.
Mr. Manzi asks about the infiltration trench and states that in his experience this area is all
clay, which will not infiltrate well.
Mr. Saal statesthat they should test the soils where the infiltration is proposed.
Mr. Hochmuth states that theinfiltration trench might work but that he will check with John
Morin regarding the suitability of the soils.
Mr. Napoli asks about soil stockpiling.
Mr. Hochmuth states that the materials will be trucked off site immediately.
Mr. Hochmuth states the tennis court fencing would be replaced with black vinyl coated
fencing but wouldbein the same footprint as exists now.
No DEP File No. available
Mr. Hochmuth requests a continuance to the October 26, 2011 meeting.
A motion to grant the request for continuance totheOctober 26, 2011 meeting is made by
Mr. Manzi, seconded by Ms. Feltovic.
Vote unanimous.
Documents;
Letter from the Neve-Morin Group, Inc. dated 9/29/11
o
Waiver Request
o
WPA Form 3-Notice of Intent and associated documents
o
Plan titled “ Proposed Tennis Court Reconstruction, 500 Great Pond Road”,
o
prepared by The Neve-Morin Group, Inc., dated 9/28/11, revised 10/12/11
Photos dated 10/12/11
o
242-1535, 2009 Salem Street (Haseltine) (Merrimack Engineering Services, Inc.)
Theapplicant George Haseltine of 2009 Salem Street Realty Trust, and William Dufresne of
Merrimack Engineering Services, Inc. arepresent.
Mr. Saal readsthe legal notice.
The administrator states the consultant was unable to meetto review the wetland line, and
wetland flags are not in place.
Mr. Dufresne states that the project proposes to rehab the existing house and construct two
new house lots. The work within jurisdiction includes widening of the existing driveway and
constructing a treatment swale. He states that the project will be before the planning board
next week and that he will review Eggleston Environmental’s latest comments and make any
necessary changes.Mr. Dufresne also presents the NHESP agreement
Mr. Manzi states that the alternativesanalysis cannot be waivedand thatit isarequirement
of theNorth Andover Wetlands Protection By-Law.
Mr. Saal states that although the tops of the two new driveways are not within jurisdiction the
applicant should consider adding a turnaroundor other area to allow easier access and turn
around for fire trucks.
Discussion of construction sequence, catch basin protection and access.
Mr. Haseltine states all the houses would have sprinkler systems installed and that the fire
trucks should have adequate access and the fire department has already reviewed the plans.
The applicant requests a continuance to the October 26, 2011 meeting.
A motion to grant the request for a continuance totheOctober 26, 2011 meeting is made by
Mr. Manzi, seconded by Ms. Feltovic
Vote unanimous.
Documents:
Application Checklist-Notice of Intent
o
Waiver Request Form
o
Complete Notice of Intent and associated documents
o
Quitclaim Deed Guy N. Richards and Carol A. Richards
o
Declaration of Restriction
o
Concrete Bound Detail plan dated 7/13/11, revised 9/14/11
o
Plan titled “Salem Woods North Andover, MA”, prepared by Merrimack Engineering
o
Services,dated 7/13/11. And 9/14/11
Letter from Merrimack Engineering Services, Inc dated 9/19/11
o
Redevelopment/Alternatives Analysis, prepared by Norse Environmental Services,
o
Inc., dated 10/12/11
Eggleston Environmental review for stormwater management system dated 8/29/11
o
E/Mail from Eggleston Environmental dated 10/4/11
o
Letter from Division of Fishery & Wildlife dated 10/4/11
o
Decision
242-1523, 273 Berry Street
The administrator reviews the drafted Order of Conditions and states that conditions will be
added regarding staking the foundation and the vernal pool certification as requested by the
commission.
A motion toissuethe Order of Conditions as drafted and amendedismade by Mr. Manzi,
seconded by Ms. Feltovic.
Vote unanimous.
A motion toadjourn the meeting at: 9:15 PM made by Ms. Feltovic, seconded by Mr. Manzi.
Vote unanimous.