HomeMy WebLinkAboutCCMeetingMinutes_05.29.13
Conservation Commission Meeting Minutes
May 29, 2013
Members Present:
Louis A. Napoli, Chairman, Joseph W. Lynch, Jr. Vice
Chairman, Deborah A. Feltovic, John T. Mabon, Sean F. McDonough, Douglas W. Saal.
Members Absent:
Albert P. Manzi, Jr.
Staff Members Present:
Jennifer A. Hughes, Conservation Administrator
Pledge of Allegiance
Meeting came to Order at: 7:05 Quorum Present.
Minutes:
Mr. Lynch moves to adopt the minutes of 4/24/13 & 5/8/13 as drafted. Ms.
Feltovic seconds the motion. Vote is unanimous.
Small Project
NACC#107, 34 Raleigh Tavern Lane
The administrator presents the small project to crush and fill a septic tank on the property
Mr. McDonough asks how far the work is from resource area.
area.
Mr. McDonough makes a motion to accept the proposal as a Small Project
seconded by Ms. Feltovic. The vote is unanimous.
Mr. McDonough makes a motion to approve the proposal as submitted, seconded by Ms.
Feltovic. The vote is unanimous.
Documents:
Application Checklist-Small Project
Small Project Procedures
Letter from Kellett Excavating, LLC dated 5/29/13
Upgrade Plan of subsurface sewage disposal system dated 3/23/13
Abbreviated Notice of Resource Area Delineation
242- 1596, 100 Dale Street (Messina Development Corp.) (Christiansen & Sergi, Inc.)
Mr. Saal reads the legal notice.
The administrator states that the applicant has requested a continuance to the June 12
meeting because additional flags need to be added to the plan.
The abutter Ms. Bere of 40 Berrington Place asks about additional flags she saw on the
Town Owned parcel that are not on the plan.
The Administrator states that the area is isolated and does not meet the 1,000 square foot
threshold.
The Commission discusses the delineation.
Ms. Feltovic makes a motion to continue the public hearing until June 12, 2013, seconded
by Mr. Lynch. Vote is unanimous.
Documents:
Application Checklist-Abbreviated Notice of Resource Area Delineation
WPA 4A-Abbrievated Notice of Resource Area Delineation
ANRAD Wetland Fee Transmittal form
Locus Map
Copy of State and Local Checks
Certifie
Letter from Basbanes Wetland Consulting dated 5/13/13
Wetland Location and Soil Types for Watershed Special Permit Plan dated 5/23/13
E/ Mail from Lois Christiansen of Christiansen & Sergi, Inc. requesting a continuance to
June 12, 2013 meeting dated 5/29/13.
Notice of Intent (NOI)
242-1582, 1049 Salem Street (Lot 70) (Hughes) (Merrimack Engineering Services, Inc.)
(cont. from 5/8/13) (Request to cont. to 6/12/13)
Motion by Ms. Feltovic seconded by Mr. McDonough to grant the request for a
continuance to the 6/12/13 meeting.
Vote is unanimous.
Document:
Hand written letter from Doug Ahern in the office requesting a continuance to June 12,
2013 letter dated 5/22/13.
242-1594, 384 Osgood Street/Bunker Hill Street (DPW) (Woodard & Curran) (cont.
from 5/8/13)
Motion by Mr. McDonough to close the public hearing and issue a decision in 21 days,
seconded by Mr. Mabon.
Vote is unanimous.
Documents:
Application Checklist-Notice of Intent
WPA Form 3-Notice of Intent
Project Narrative & Construction sequencing Plan
Existing Conditions
Proposed Construction Activities
Erosion Control Measures
Performance Standards
Schedule
Alternatives Analysis
MESA Review
Stormwater Report
Specifications
Earthwork
Temporary Erosion Control
Figure 1: Bunker Hill Street Proposed work and wetlands
Figure 2: Habitats and 100-year Flood Plain
Figure: 3 USGS MAP dated Summer of 2013
School Street-Plan & Profile/Bunker Hill Street-Plan & Profile dated 4/12/13
Bunker Hill Street and School Street Sewer Upgrade Project dated 4/12/13
242-1593, 16 Berry Street (North Andover Holdings, LLC) (LEC Environmental
Consultants, Inc.) (cont. from 4/24/13)
Ann Marton, of LEC Environmental, presents that there was an error in the abutter
notification due to an -notified and
the meeting was re-advertised.
Ms. Marton recaps the prior meeting and discussion and summarizes the proposal
Mr. Bombaci of GPR reviews the Stormwater Mgt Plan
Mr. Bombaci states that Eggleston Environmental is reviewing the Stormwater
Management Plan and should have her review ready within the next few days.
Mr. Mabon asks about alternatives to the parking proposed in front of Building D.
Ms. Marton presents the Buffer Zone Restoration Plan.
Calvin Goldsmith of GPR presents alternatives and restrictions to moving parking
including keeping open space for residents, NHESP concerns, and view from Windsor
Lane.
Natural Heritage and Endangered Species Program (NHESP) concerns are discussed. Mr.
Goldsmith discusses restriction, trails and fencing.
Mr. Goldsmith states parking kept to the rear of buildings to preserve streetscape, also
difficult soils at center of site and also would like buildings to look out on open space
Mr. Mabon asks if parking can be moved under Building D.
Mr. Goldsmith states parking could not go under Building D due to grade.
Mr. Lynch asks why building cannot be raised and parking put under
Mr. Goldsmith states this would expose the foundation and the ZBA would push back on
the building height.
Mr. Lynch asks why could there not just be one row of parking under with no change in
height. Mr. Lynch asks that this be looked at more closely
The administrator asks if all of the parking is necessary.
Mr. Goldsmith states that 1.6 spaces per unit are required and the project currently
supplies 1.68.
Mr. Napoli asks about plans to widen the road and what stormwater management will be
provided.
Mr. Bombaci states that all drainage to street will be handled on-site. Also states there
will be slight widening of the road (DPW request) plus an emergency entrance.
Mr. McDonough asks about problems with abutter list. Ms. Marton responds
Mr. McDonough asks alternative location in the open space area.
Mr. Goldsmith responds that this is not proximate to Building D.
Mr. McDonough asks that parking be moved away from the wetland.
Mr. Lynch asks if there will be a restriction on the open space.
Ms. Marton presents the planting plan and discusses mitigation to enhance vegetation for
wildlife.
Mr. Mabon asks the applicant to look at minimizing or relocating parking spaces.
Ms. Marton reviews the NHESP letter stating that the project will not have any impact on
the identified rare species. There is still a fencing issue to be worked out.
Mr. Lynch asks about snow storage.
Mr. Bombaci states that it will not be put into the stormwater BMPs and that guard rail
could be used.
Mr. Lynch states snow should be loaded off the site.
Mr. Napoli states that if the commission allows wetland fill and work in th-
Disturb, a restriction on the open space should be required.
Mr. Goldsmith states he will take this information back to the team and requests a
continuance to the June 12, 2013 meeting.
Motion by Mr. Lynch to grant the continuance request, seconded by Ms. Feltovic
Vote is unanimous.
Documents:
Buffer Zone Impact Comparison Table
Presentation Plan Date: April 2013
Appendix F Buffer Zone Restoration Plan Date: 4/12/13
Buffer Zone Exhibit Plan Date May 2013
General Business
242-1315, COC Request, 85 Ogunquit Road (Lot 6) (Breen) (The Neve-Morin
Group, Inc.) (cont. from 5/8/13)
.
The commission discusses the overall order.
Mr. Mabon makes a motion to grant the COC request for 85 Ogunquit (Lot 6), second by
Ms. Feltovic.
Vote is unanimous.
Documents:
Letter from The Neve-Morin Group, Inc. dated 4/12/13
WPA Form 8A-Request for Certificate of Compliance
As-Built Site Conditions Plan of Land dated 7/5/12
Photos dated 5/29/13
242-1555, COC Request, 72 Patton Lane (Uttley) (Hancock Associates)
The applicant Kristine Uttley is present
The administrator presents photos and the report prepared by the field inspector. The spa
and shed were not built and the old shed was removed from the property and not
relocated. A small retaining wall was also not needed.
Mr. McDonough asks about the retaining wall
Mr. Lynch asked about restoration which is complete.
Mr. Mabon makes a motion to grant the COC request for 72 Patton Lane, Ms. Feltovic
seconds.
The vote is unanimous.
Documents:
Letter from Hancock Associates dated 12/5/12
North Andover Conservation Commission Order of Conditions Compliance Certificate
Form dated 12/5/12
Conservation As-Built Plan dated 12/19/12
Photos dated 5/29/13
242-95, PCOC Request, 222 Bridges Lane (Lot 18) (Goudreau)
yard at this site. The request is for partial releases from a roadway order and from an
order to construct several houses (but not this one).
Mr. Lynch asks if there are any stormwater structures on this lot. There are not.
Ms. Feltovic makes a motion to grant the PCOC for 222 Bridges Lane (Lot 18), seconded
by Mr. Lynch.
The vote is unanimous.
Document:
WPA Form 8A-Request for Partial Certificate of Compliance
242-140, PCOC Request, 222 Bridges Lane (Lot 18) (Goudreau)
The applicant Roger L. Goudreau is present
Mr. Lynch makes a motion to grant the PCOC for 222 Bridges Lane (Lot 18), seconded
by Ms. Feltovic.
Vote is unanimous.
Document:
WPA Form 8A-Request for Partial Certificate of Compliance
Decision
242-1594, 384 Osgood Street/Bunker Hill Street
Administrator reviews the draft Order of Conditions.
Mr. Lynch makes a motion to accept the Order of Conditions as drafted.
Mr. Lynch makes a motion to adjourn the meeting at: 8:28 PM, seconded by Ms.
Feltovic. The vote is unanimous.