75 Park Street, North Andover
Window Well Construction
Conservation Conditions of Approval, NACC #62
Pursuant to section 4.4.2 J of the North Andover Wetlands Protection Regulations,Nunes Trabucco
Architects, on behalf of Stevens Corner Limited Partnership (owners),filed for a small project for
work proposed at 75 Park Street,North Andover. The work consists of excavation associated with the
construction of a 100+/-square foot section of a window well as part of the renovation of an existing
building located at the intersection of Park and Osgood Streets. The closest point of work is
approximately 87 feet from a jurisdictional wetland resource area on the opposite side of Osgood
Street.
During the October 21,2009 public meeting,the North Andover Conservation Commission (NACC)
voted unanimously to approve this project as described above. The following conditions were hereby
mandated for the proposed work:
RECORD DOCUMENTS: Plan titled Grading Plan, Construction Plans for the Residences
at Steven's Corner, Sheet C-3 (of Sheets C1-C6)
Prepared by Marchionda &Associates, L.P.
62 Montvale Avenue Suite 1
Stoneham, MA 02180
Dated 7/1/09 and Revised 8-4-09 &10-30-09
Project description email prepared by Nunes Trabucco
Architects, 315A Chestnut Street,2nd Floor, Needham, MA
1600 Osgood Street,Building 20,Suite 2-36,North Andover,Massachusetts 01845
Phone 978.688.9530 . Fax 978.688.9542 Web www.http://Nvww.townofiiorthandover.corn/conservel.httn
CONDITIONS:
1. Accepted engineering and construction standards and procedures shall be followed in the
completion of the project.
2. Excess material shall be properly disposed of off site and all stockpile areas shall be located
more than 100-feet from resource areas as shown on the record plan.
3. Erosion Control shall be installed according to the approved plan including: installation of
a silt sack in the Park Street catch basin and erosion control around all stockpile areas. In
addition,the existing drain pipe shall be blocked during construction to prevent sediments
from entering the drainage system.
4. Once all erosion controls are in place and prior to the start of excavation,the applicant shall
contact the Conservation Department for a preconstruction inspection.
5. Upon completion of the approved project and site stabilization, please contact the
Conservation Department for a final inspection.
6. This permit shall expire one year from the date of issuance (Due to a delay in the issuance
of other related permits, this permit shall expire one year from the date of delivery-March
15 2010).
Please do not hesitate to contact me should you have any further questions or concerns in this regard.
Thank you in advance for your anticipated cooperation.
Respectfully,
NORTH ANDOVER CONSERVATION DEPARTMENT
pvll�
Jennifer A. Hug es
C servation Administrator