North Andover Health Department
Community and Economic Development Division
August 24, 2017
Livingstone Development Corp
PO Box 50
Tewksbury, MA 01876 1
Re: Subsurface Sewage Disposal System. Pian for 1.975 Salem Street—Lot 1
(Map 1.0613, Parcel 16, Lot 1)
To Whom It May Concern:
The proposed wastewater system design plan for the above site dated May 5, 2017 with a final
revision date of August 14, 2017 and received on August 17, 2017 has been approved.
The design has been approved for use in the construction of a new on-site septic system for a five
(5) bedroom, eleven(11)total room residential dwelling, utilizing a gravity leach:held system.
This design plan approval is valid until August 24, 2020.
During this time, a licensed septic system installer must obtain a permit and complete this work,
and a Certificate of Compliance be endorsed by the installer, designer and the Town of North
Andover.
This approval is also subject to the following conditions:
1. Prior to the issuance of the Disposal Works Construction Permit, the applicant must
submit a foundation as-built at the same scale as the approved plan.
2. Prior to the issuance of the Disposal Works Construction Permit, the applicant must
submit the floor plans of the proposed dwelling showing no greater than five (5)
bedrooms or eleven (11) total rooms.
3. Prior to construction, the designer must establish a benchmark within seventy-five
(75) feet of the proposed system. The location and elevation of the benchmark must
be submitted to the Health Department.
Page 1 of 2
North Andover I3ealth Department
Town I-fall, 120 Main Street,
North Andover, MA 01.845
Phone: 978.688.9540 Fax: 078.688. 9542
1.975 Salem Street----Lot I August 24, 2017
4. If site conditions are -found in the field to be different from those indicated on the
design plan and/or soil evaluation, the originally issued Disposal System Construction
Permit is void, installation shall stop, and the applicant shall reapply for a new
Disposal Systems Construction Permit (3 10 CMR 15.020(1)).
5. It is the responsibility of the applicant and/or the applicant's septic system designer,
septic system installer or other representative to ensure that all other state and
municipal requirements arc met. These may include review by the Conservation
Commission, Zoning Board, Planning Board, Building Inspector, Plumbing Inspector
and/or Electrical Inspector. The issuance of a Disposal System Construction Permit
shall not construe and/or imply compliance with any of the aforementioned
requirements.
Please feel free to contact the office with any questions you may have. We look forward to
working with you to obtain a wastewater treatment and dispersal system which will be in
compliance with all regulations and assure protection of public health and the environment of
North Andover.
Sinceiply,
Van/Lai
ri'ai
I Grasse, CEHT
Director of Public Health
Encl. Installers list
cc: Christiansen& Sergi, Inc. 160 Sumner Street, Haverhill MA 01830
File