HomeMy WebLinkAbout2004-03-15 Planning Board Minutes North Andover Planning Board
Unapproved Minutes
March 15,2004
Regular Meeting
Members Present: Alberto Angles,Chair,George White,Vice Chair,John Simons
James Phinney,Associate Member,Felipe Schwarz,Clerk
Rick Nardella
Stoff Present: Julie Parrino,Town Planner,Debbie Wilson,Planning Assistant
The Chair called the meeting to order:
Informal Discussions:
ANR plan reviews:
215 & 225 Old Cart Way-Approved
Merrimack College-Approved
Bradford Street-Denied
Falcon Air Bond Release
Applicant has submitted request for a bond release. As-built plans have been submitted stamped by a P.E.
Decision issued April 3,2002 for construction of a metal hanger building 5,920 s.f in size. A$1,000
bond was posted. Site has been reviewed and all work is completed. Recommend release of the$1,000
bond.
Town Meeting Article Discussion(Updates)
• Residential Adaptive Re-Use Special Permit
• Phased Development Bylaw
• Flood Plain District
• R4 Zoning Amendment for 2 Family Dwellings
• Definition article
Approval of the Minutes
Continued Public Hearings:
80 Saile Way-Watershed Special Permit-(Cont. from February 3,2004)
At the last hearing the applicant submitted calculations from the engineer stating the installed infiltration
systems have been over sized and the percentage of groundwater recharge is approximately 89%. It
appeared that the impervious area from the pool was not being infiltrated. We requested either an
additional infiltration system be added or the pool runoff somehow be tied into the existing infiltration
system which appears adequate to handle the additional water. Revised plans have been submitted
showing a drip line around the edge of the pool. V14B has reviewed the revised plans and calculations
submitted by the applicant at the last hearing. VBB has submitted a final review letter with one
outstanding comment to display a perforated pipe on the plan. Comments forwarded to applicant. If Board
is satisfied, I recommend we close the public hearing,
17$9 Great Pond Road-Arnone(Cont. from 1/6104)
Summary: Applicant submitted an application for a Watershed Special Permit on August 18, 2003 for
construction of a new single family house located across the street from Lake Cochichewick within the
Non-Discharge Zone and Non-Disturbance Zone. The existing lot was to be serviced from an existing
common driveway,however, late into the permitting process it was discovered that the common driveway
already serviced two existing homes. The Bylaw does not allow a common driveway to service more
than three lots. The applicant was instructed to file for a variance with the Zoning Board of Appeals for
access off the existing common driveway. In lieu of filing with ZBA,the applicant has resubmitted a
plan proposing a completely separate driveway off Great Pond Road. The plan was forwarded over to
VHB for final review and the following comments were highlighted in their March 11, 2004 letter:
• Plan should be stamped(progress print was submitted);
• The driveway slope ranges from 15%to 12%.The Zoning Bylaw does not have design criteria
for driveways, however MHD allows driveway vertical profiles ranging from 10%to 15%. A
driveway slope of 15% is not desirable but is acceptable by MHD.
• VHB feels given the horizontal curvature of the proposed driveway in combination with the steep
driveway slope, negotiating the driveway will be difficult, especially in winter months.
• The plan indicates the driveway will be cut into the existing hill. Surface water will runoff onto
the driveway surface and cause a potential ice condition in the winter. Has driveway side
treatments,ditches, swales, subdrains been considered.
• Applicant should determined site distance along Great Pond Road at the proposed driveway
location.
• VHB recommends the clap pipes to the west and east of the proposed catch basin be replaced
with 12-inch reinforced pipes.
Upon discussions with DPW,in order to obtain a DPW driveway access permit,the driveway entrance
will have to be regraded(length from roadway to property boundary, approximately 7')so that the pitch
does not exceed 3%. Currently approximately 20%pitch. Comments have been forwarded to the
applicant.
CV5 (continued from]march 2,2004)
VHB submitted revised plans dated March 9,2004. Sidewalks have been shown on the plan along the
route 114 and Peters Street property boundaries. Sidewalks are located outside of the Mass Highway
Right of Way on the CVS property,therefore the walls and landscaping have been moved.
VAI submitted a letter dated March 11, 2004 with final comments. Comments and outstanding issues are
as follows:
• At the intersection of Salem Turnpike at Peters Street and Haverhill Street, improvement
measures have been identified to alleviate impacts with queuing at the site driveway on Peters
Street.VHB Concept 1 plan, dated 2/5/04 indicates that additional pavement markings should be
included to channelize traffic flow into a single lane as it enters Peters Street from Turnpike or
Haverhill Street. Review of the latest Concept 1, shows additional striping to channelize flow into
Peters Street
• The Concept plan shows a minor widening of Peters Street at the intersection with Turnpike
Street,yet the site plans do not reflect any changes in curb geometry. This needs to be rectified.
• The sidewalk along Peters Street, from the proposed site driveway to Turnpike Street, needs to be
adjusted. The Concept Plan shows this curb line being slightly moved,yet the site plans show the
sidewalk against the existing edge of road. If the sidewalk is to be against the edge of road,
vertical granite curbing should be used in lieu of sloped granite edging.
• It is not clear,when comparing the Concept Plan to the site plans as to the limit of curb work
along Turnpike Street, from Peters Street to the proposed Turnpike Street driveway. This should
be clarified.
MI:V submitted a review letter dated March 11, 2004 in response to the revisedplans submitted from
VHB. No memorandum addressing the previous outstanding issues was submitted. The following
outstanding issues were addressers in the memorandum:
• Many outstanding issues have not even been attempted to be addressed;
• The Floor Plan should be re-included into the Site Plan Sheet;
® Signage: Two proposed monument signs are shown at entrance,no details are provided;are they
directional in nature,will they have external illumination? The applicant should address if any
freestanding site signs are proposed.
• Wall signage needs specification for colors, areas,confirmation on projection dimensional limits, -
and materials.
• The maximum number of signs allowed is one primary and one secondary,which are both
assumed to be two wall signs. Free standing signs must be addressed.
o Parking: The Peters Street driveway is not provided with an adequate leveling platform. Distance
of 20 feet with 2%slope should be provided.
• Supplementary regulations: Construction easement for the wall needs to be verified by the
abutter via an easement deed reference on the plan.Include this in the conditions.
• Possible conflicts between the wall-pak building light mounting heights and locations should be
shown on the building elevations.
• MHD application permit should be filed with the State. This is a requirement and no proof has
been submitted to date,
a SMH 2 Rim will be raised up out of the pavement by about 6 inches. This has not been addressed
by showing grading on the sewer design plan.
• Consideration should be made to extending the landscape island near DMH-AS to the north for
visual screening and safety reasons.
Upon receipt of these comments,VHB submitted a response memo stating how each concern would be
resolved. Final changes will be applied on the mylar plans and I recommend we condition several of the
items. If Board is satisfied,I recommend we close the public hearing.
New Public Hearings
Brooks School
The applicant, Brooks School, is filing a Watershed Special Permit under Section 4.136 of the Zoning
Bylaw for construction of two single family faculty structures and associated site work and utility
connections located in the Non-Discharge Zone.Each building is intended as a residence for a faculty
member or his or her family. Each dwelling will be two stories with attached two-car garages, full
basement with bulkhead and on-grade rear patio. Best Management practices have been proposed and
include the construction of drainage swales,catch basins and groundwater recharge systems for roof
runoff.VHB has reviewed the project and has provided comments. See detailed review.
Decisions:
80 Saile Way
492 Sutton Street