HomeMy WebLinkAboutTOWN OF NORTH ANDOVER DIVISION OF PUBLIC WRKS Massachusetts Department of Environmental Protection 242-1455
Bureau of Resource Protection - Wetlands MassDEP File Number
WPA Form 5 — Order of Conditions Document Transaction Number
LA
r
Massachusetts Wetlands Protection Act M.G.L. c. 131, §40 North Andover
City/Town
A. General Information
Important: North Andover
When filling out 1. From:
forms on the Conservation Commission
computer, use 2. This issuance is for check one): a.
only the tab key ( ) ® Order of Conditions b. El Amended Order of Conditions
to move your
cursor-do not 3. To: Applicant:
use the return
key.
a. First Name b. Last Name
Town of North Andover Division of Public Works
c.Organization
384 Osgood Street
erg d. Mailing Address
North Andover MA 01845
e. City/Town f.State g.Zip Code
4. Property Owner(if different from applicant):
a. First Name b.Last Name
Sewer Easement
c.Organization
d. Mailing Address
e.City/Town f.State g.Zip Code
5. Project Location:
Rea's Pond, Bridle Path,Winter Street North Andover
a. Street Address b.City/Town
c.Assessors Map/Plat Number d.Parcel/Lot Number
Latitude and Longitude, if known: e. Latitude f. Longitude
6. Property recorded at the Registry of Deeds for(attach,additional information if,more than one parcel):
Essex North
a. County b.Certificate Number(if registered land)
c.Book d.Page
7. Dates: 6/25/09 8/12/09 8/14/09
a. Date Notice of Intent Filed b. Date Public Hearing Closed c. Date of Issuance
8. Final Approved Plans and Other Documents (attach additional plan or document references as
needed):
Sewer Manhole Rehabilitations Plan
a. Plan Title
Tutela Engineering Associates Thomas J. Keeffe
b. Prepared By c.Signed and Stamped by
June 18, 2009 1"=40'
d. Final Revision Date e.Scale
f.Additional Pian or Document Title g.Date
wpaform5-doe• rev.11/08 Pagel of 11
Massachusetts Department of Environmental Protection 242-1455
Bureau of Resource Protection - Wetlands MassDEP File Number
Ll
WPA Form 5 — Order of Conditions Document Transaction Number
Massachusetts Wetlands Protection Act M.G.L. c. 131, §40 North Andover
City/Town
B. Findings
i. Findings pursuant to the Massachusetts Wetlands Protection Act:
Following the review of the above-referenced Notice of Intent and based on the information provided
in this application and presented at the public hearing, this Commission finds that the areas in which
work is proposed is significant to the following interests of the Wetlands Protection Act(the Act).
Check all that apply:
a. ® Public Water Supply b. ❑ Land Containing Shellfish c. ® Prevention of Pollution
d. ® Private Water Supply e. ❑ Fisheries f. ®Protection of Wildlife
Habitat
g. ® Groundwater Supply h. ® Storm Damage Prevention i. ® Flood Control
2. This Commission hereby finds the project, as proposed, is: (check one of the following boxes)
Approved subject to:
a. ® the following conditions which are necessary in accordance with the performance standards set
forth in the wetlands regulations. This Commission orders that all work shall be performed in
accordance with the Notice of Intent referenced above, the following General Conditions,and any
other special conditions attached to this Order. To the extent that the following conditions modify or
differ from the plans, specifications, or other proposals submitted with the Notice of Intent, these
conditions shall control.
Denied because:
b. ❑ the proposed work cannot be conditioned to meet the performance standards set forth in the
wetland regulations. Therefore, work on this project may not go forward unless and until a new Notice
of Intent is submitted which provides measures which are adequate to protect the interests of the Act,
and a final Order of Conditions is issued..A description of the performance standards which the
proposed work cannot meet is attached to this Order.'
c. ❑ the information submitted by the applicant is not sufficient to describe the site, the work, or the
effect of the work on the interests identified in the Wetlands Protection Act. Therefore, work on this
project may not go forward unless and until a revised Notice of Intent is submitted which provides
sufficient information and includes measures which are adequate to protect the Act's interests, and a
final Order of Conditions is issued. A description of the specific information which is lacking and
why it is necessary is attached to this Order as per 310 CMR 10.05(6)(c).
Inland Resource Area Impacts: Check all that apply below. (For Approvals Only)
3. ❑ Buffer Zone Impacts: Shortest distance between limit of project disturbance and
Bank or Bordering Vegetated Wetland boundary(if available) a.linear feet
Resource Area Proposed Permitted Proposed Permitted
Alteration Alteration Replacement Replacement
4. ❑ Bank a. linear feet b.linear feet c.linear feet d.linear feet
5. ® Bordering Vegetated 2,000 s.f. 2,000 s.f. 2,000 s.f. 2,000 s.f.
Wetland a.square feet b.square feet c square feet d.square feet
800 s.f. 800 s.f. 800 s.f 800 s.f.
6. ® Land Under Waterbodies a.square feet b.square feet c.square feet d.square feet
and Waterways
e.c/y dredged f.c/y dredged
wpaform5.doc• rev.11/08 - Page 2 of 11
Massachusetts Department of Environmental Protection 242-1455
�- Bureau of Resource Protection - Wetlands MassDEP File Number
WPA Form 5 -- Order of Conditions Document Transaction Number
Massachusetts Wetlands Protection Act M.G.L. c. 131, §40 North Andover
City/Town
B. Findings (cont.)
Resource Area Proposed Permitted Proposed Permitted
Alteration Alteration Replacement Replacement
7. El Bordering Land
Subject to Flooding a.square feet b.square feet c.square feet d.square feet
Cubic Feet Flood Storage
e.cubic feet f.cubic feet g.cubic feet h.cubic feet
8. ❑ Isolated Land Subject
to Flooding a.square feet b.square feet
Cubic Feet Flood Storage c.cubic feet d.cubic feet e.cubic feet f.cubic feet
9. ❑ Riverfront Area a.total sq.feet, b.total sq.feet
Sq ft within 100 ft c.square feet d.square feet e.square feet f.square feet
Sq ft between 100-200 ft square feet h.square feet i.square feet
9• 4 q q j.square feet
Coastal Resource Area Impacts: Check all that apply below. (For Approvals Only)
10. ❑ Designated Port Areas Indicate size under Land Under the Ocean,below
11. ❑ Land Under the Ocean a.square feet b.square feet
c.cy dredged d.c/y dredged
12. ❑ Barrier Beaches Indicate size under Coastal Beaches and/or Coastal Dunes below
13. ❑ Coastal Beaches a.square feet b.square feet c.c!y nourishmt. d.cfy nourishmt.
14. ❑ Coastal Dunes a.square feet b.square feet c.c/y nourishmt. d.c/y nourishmt.
15. ❑ Coastal Banks a.linear feet b.linear feet
16. ❑ Rocky Intertidal Shores a.square feet b.square feet
17. ❑ Salt Marshes a.square feet b.square feet c.square feet d.square feet
18. ❑ Land Under Salt Ponds a.square feet b.square feet
c.Gy dredged d.c/y dredged
19. ❑ Land Containing
Shellfish a.square feet b.square feet c.square feet d.square feet
20. ❑ Fish Runs Indicate size under Coastal Banks, Inland Bank, Land Under the
Ocean, and/or inland Land Under Waterbodies and Waterways,
above
a.c/y dredged b.c/y dredged
21. ❑ Land Subject to Coastal
Storm Flowage a.square feet b.square feet
wpaform5.doc• rev.11/08
Page 3 of 11
L11Massachusetts Department of Environmental Protection 242-1455
Bureau of Resource Protection - Wetlands MassDEP Fife Number
WPA Form 5 — Order of Conditions Document Transaction Number
Massachusetts Wetlands Protection Act M.G.L. c. 131, §40 North Andover
City/Town
C. General Conditions Under Massachusetts Wetlands Protection Act
The following conditions are only applicable to Approved projects.
1. Failure to comply with all conditions stated herein, and with all related statutes and other regulatory
measures, shall be deemed cause to revoke or modify this Order.
2. The Order does not grant any property rights or any exclusive privileges; it does not authorize any
injury to private property or invasion of private rights.
3. This Order does not relieve the permittee or any other person of the necessity of complying with all
other applicable federal, state, or local statutes, ordinances, bylaws, or regulations.
4. The work authorized hereunder shall be completed within three years from the date of this Order
unless either of the following apply:
a. the work is a maintenance dredging project as provided for in the Act; or
b. the time for completion has been extended to a specified date more than three years, but less
than five years, from the date of issuance. If this Order is intended to be valid for more than three
years, the extension date and the special circumstances warranting the extended time period are
set forth as a special condition in this Order.
5. This Order may be extended by the issuing authority for one or more periods of up to three years each
upon application to the issuing authority at least 30 days prior to the expiration date of the Order.
6. Any fill used in connection with this project shall be clean fill.Any fill shall contain no trash, refuse,
rubbish, or debris, including but not limited to lumber, bricks, plaster, wire, lath, paper, cardboard,
pipe, tires, ashes, refrigerators, motor vehicles, or parts of any of the foregoing.
7. This Order is not final until all administrative appeal periods from this Order have elapsed, or if such
an appeal has been taken, until all proceedings before the Department have been completed.
8. No work shall be undertaken until the Order has become final and then has been recorded in the
Registry of Deeds or the Land Court for the district in which the land is located', within the chain of title
of the affected property. In the case of recorded land, the Final Order shall also be noted in the
Registry's Grantor Index under the name of the owner of the land upon which the proposed work is to
be done. In the case of the registered land,the Final Order shall also be noted on the Land Court
Certificate of Title of the owner of the land upon which the proposed work is done. The recording
information shall be submitted to the Conservation Commission on the form at the end of this Order,
which form must be stamped by the Registry of Deeds, prior to the commencement of work.
9. A sign shall be displayed at the site not less then two square feet or more than three square feet in
size bearing the words,
"Massachusetts Department of Environmental Protection" [or, "MassDEP"]
"File Number
242-1455
wpaform5.doc• rev.11/08 Page 4 of 11
LlMassachusetts Department of Environmental Protection 242-1455
Bureau of Resource Protection - Wetlands MassDEP File Number
WPA Form 5 - Order of Conditions Document Transaction Number
Massachusetts Wetlands Protection Act M.G.L. o. 131, §40 North Andover
City/Town
C. General Conditions Under Massachusetts Wetlands Protection Act
10. Where the Department of Environmental Protection is requested to issue a Superseding Order, the
Conservation Commission shall be a party to all agency proceedings and hearings before MassDEP.
11. Upon completion of the work described herein,the applicant shall submit a Request for Certificate of
Compliance(WPA Form 8A)to the Conservation Commission.
12. The work shall conform to the plans and special conditions referenced in this order.
13. Any change to the plans identified in Condition #12 above shall require the applicant to inquire of the
Conservation Commission in writing whether the change is significant enough to require the filing of a
new Notice of Intent.
14. The Agent or members of the Conservation Commission and the Department of Environmental
Protection shall have the right to enter and inspect the area subject to this Order at reasonable hours
to evaluate compliance with the conditions stated in this Order, and may require the submittal of any
data deemed necessary by the Conservation Commission or Department for that evaluation.
15. This Order of Conditions shall apply to any successor in interest or successor in control of the property
subject to this Order and to any contractor or-other person performing work conditioned by this Order.
16. Prior to the start of work, and if the project involves work adjacent to a Bordering Vegetated Wetland,
the boundary of the wetland in the vicinity of the proposed work area shall be marked by wooden
stakes or flagging. Once in place,the wetland boundary markers shall be maintained until a Certificate
of Compliance has been issued by the Conservation Commission.
17. All sedimentation barriers shall be maintained in good repair until all disturbed areas have been fully
stabilized with vegetation or other means. At no time shall sediments be deposited in a wetland or
water body. During construction, the applicant or his/her designee shall inspect the erosion controls
on a daily basis and shall remove accumulated sediments as needed. The applicant shall immediately
control any erosion problems that occur at the site and shall also immediately notify the Conservation
Commission, which reserves the right to require additional erosion and/or damage prevention controls
it may deem necessary. Sedimentation barriers shall serve as the limit of work unless another limit of
work line has been approved by this Order.
NOTICE OF'STORMWATER CONTROL AND-MAINTENANCE REQUIREMENTS
18. The work associated with this Order(the"Project")is(1)® is not(2)❑ subject to the
Massachusetts Stormwater Standards. If the work is subject to the Stormwater Standards,
then the project is subject to the following conditions:
a) All work, including site preparation, land disturbance, construction and redevelopment, shall be
implemented in accordance with the construction period pollution prevention and erosion and
sedimentation control plan and, if applicable, the Stormwater Pollution Prevention Plan required by the
National Pollution Discharge Elimination System Construction General Permit as required by
Stormwater Condition 8. Construction period erosion, sedimentation and pollution control measures
and best management practices (BMPs)shall remain in place until the site is fully stabilized.
wpaform5.doc• rev.11108
-Page 5 of 11
L7, 1 Massachusetts Department of Environmental Protection 242-1455
Bureau of Resource Protection - Wetlands MassDEP File Number
WPA Form 5 — Order of Conditions Document Transaction Number
Massachusetts Wetlands Protection Act M.G.L. c. 131, §40 North Andover
City/Town
C. General Conditions Under Massachusetts Wetlands Protection Act (cont.)
b) No stormwater runoff may be discharged to the post-construction stormwater BMPs unless and
until a Registered Professional Engineer provides a Certification that:
i. all construction period BMPs have been removed or will be removed by a date certain specified in
the Certification. For any construction period BMPs intended to be converted to post construction
operation for stormwater attenuation, recharge, and/or treatment, the conversion is allowed by the
MassDEP Stormwater Handbook BMP specifications and that the BMP has been properly cleaned or
prepared for post construction operation, including removal of all construction period sediment trapped
in inlet and outlet control structures;
ii. as-built final construction BMP plans are included, signed and stamped by a Registered
Professional Engineer, certifying the site is fully stabilized;
iii. any illicit discharges to the stormwater management system have been removed, as per the
requirements of Stormwater Standard 10;
iv, all post-construction stormwater BMPs are installed in accordance with the plans(including all
planting plans)approved by the issuing authority, and have been inspected to ensure that they are not
damaged and that they are in proper working condition
v. any vegetation associated with post-construction BMPs is suitably established to withstand erosion.
c) The landowner is responsible for BMP maintenance until the issuing authority is notified that
another party has legally assumed responsibility for BMP maintenance. Prior to requesting a
Certificate of Compliance, or Partial Certificate of Compliance, the responsible party(defined in
General Condition 18(e))shall execute and submit to the issuing authority an Operation and
Maintenance Compliance Statement("O&M Statement)for the Stormwater BMPs identifying the party
responsible for implementing the stormwater BMP Operation and Maintenance Plan ("O&M Plan")and
certifying the following: i.)the O&M Plan is complete and will be implemented upon receipt of the
Certificate of Compliance, and ii.)the future responsible parties shall be notified in writing of their
ongoing legal responsibility to operate and maintain the stormwater management BMPs and
implement the Stormwater Pollution Prevention Plan.
d) Post-construction pollution prevention and source control shall be implemented in accordance
with the long-term pollution prevention plan section of the approved Stormwater Report and, if
applicable, the Stormwater Pollution Prevention Plan required by the National Pollution Discharge
Elimination System Multi-Sector General Permit.
e) Unless and until another party accepts responsibility,the landowner, or owner of any drainage
easement, assumes responsibility for maintaining each BMP. To overcome this presumption, the
landowner of the property must submit to the issuing authority a legally binding agreement of record,
acceptable to the issuing authority, evidencing that another entity has accepted responsibility for
maintaining the BMP, and that the proposed responsible party shall be treated as a permittee for
purposes of implementing the requirements of Conditions 18(f)through 18(k)with respect to that
BMP. Any failure of the proposed responsible party to implement the requirements of Conditions 18(f)
through 18(k)with respect to that BMP shall be a violation of the Order of Conditions or Certificate of
Compliance. In the case of stormwater BMPs that are serving more than one lot, the legally binding
agreement shall also identify the lots that will be serviced by the stormwater BMPs. A plan and
easement deed that grants the responsible party access to perform the required operation and
maintenance must be submitted along with the legally binding agreement.
f) The responsible party shall operate and maintain all stormwater BMPs in accordance with the
design plans, the O&M Plan, and the requirements of the Massachusetts Stormwater Handbook.
wpaform5.doc• rev.11/08
Page 6 of 11
Massachusetts Department of Environmental Protection 242-1455
Bureau of Resource Protection Wetlands MassDEP File Number
WPA Form 5 — Order of Conditions Document Transaction Number
Massachusetts Wetlands Protection Act M.G.L. c. 131, §40 North Andover
City/Town
C. General Conditions Under Massachusetts Wetlands Protection Act (cont.)
g) The responsible party shall:
1. Maintain an operation and maintenance log for the last three(3)consecutive calendar years
of inspections, repairs, maintenance and/or replacement of the stormwater management
system or any part thereof, and disposal(for disposal the log shall indicate the type of material
and the disposal location);
2. Make the maintenance log available to MassDEP and the Conservation Commission
("Commission") upon request; and
3. Allow members and agents of the MassDEP and the Commission to enter and inspect the site
to evaluate and ensure that the responsible party is in compliance with the requirements for
each BMP established in the O&M Plan approved by the issuing authority.
h) All sediment or other contaminants removed from stormwater BMPs shall be disposed of in
accordance with all applicable federal, state, and local laws and regulations.
i) Illicit discharges to the stormwater management system as defined in 310 CMR 10.04 are
prohibited.
j) The stormwater management system approved in the Order of Conditions shall not be changed
without the prior written approval of the issuing authority.
k) Areas designated as qualifying pervious areas for the purpose of the Low Impact Site Design
Credit(as defined in the MassDEP Stormwater Handbook, Volume 3, Chapter 1, Low Impact
Development Site Design Credits)shall not be altered without the prior written approval of the issuing
authority.
1) Access for maintenance, repair,and/or replacement of BMPs shall not be withheld. Any fencing
constructed around stormwater BMPs shall include access gates and shall be at least six inches
above grade to allow for wildlife passage:
Special Conditions(if you need more space for additional conditions, please attach a text document):
D. Findings Under Municipal Wetlands Bylaw or Ordinance
1. Is a municipal wetlands bylaw or ordinance applicable? Z Yes ❑ No
2. The North Andover hereby finds(check one that applies):
Conservation Commission
a. ❑ that the proposed work cannot be conditioned to meet the standards set forth in a municipal
ordinance or bylaw specifically:
1.Municipal Ordinance or Bylaw 2.Citation
Therefore, work on this project may not go forward unless and until a revised Notice of Intent is
submitted whichrovides measures which are
p adequate to meet these standards and a final
Order of Conditions is issued.
wpaform5.doc• rev.11/08
- Page 7 of 11
Massachusetts Department of Environmental Protection 242-1455
Bureau Of Resource Protection - Wetlands MassDEP File Number
WPA Form 5 -- Order of Conditions Document Transaction Number
Massachusetts Wetlands Protection Act M.G.L. c. 131, §40 North Andover
Cityrrown
D. Findings Under Municipal Wetlands Bylaw or Ordinance (cont.)
b. ® that the following additional conditions are necessary to comply with a municipal ordinance or
bylaw:
North Andover Wetlands Protection Bylaw Chapter 178
1.Municipal Ordinance or B law
Y 2.Citation
3. The Commission orders that all work shall be performed in accordance with the following conditions
and with the Notice of Intent referenced above. To the extent that the following conditions modify or
differ from the plans, specifications, or other proposals submitted with the Notice of Intent, the
conditions shall control.
The special conditions relating to municipal ordinance or bylaw are as follows(if you need more space
for additional conditions, attach a text document): -
See Attached
wpaform5.doc• rev.11/08
Page 8 of 11
DEP FILE#242 - 1455
Therefore, the North Andover Conservation Commission (hereafter the "NACU') hereby
finds that the following conditions are necessary,in accordance with the Performance
Standards set forth in the State Regulations, the local ByLaw and Regulations, to protect
those interests noted above. The e NACU.orders that all work shall beerf m
p
or ed in
accordance with said conditions and with the
Notice of Intent referenced below. To the
extent that the following conditions modify or differ from the plans, specifications or other
proposals submitted with the Notice of Intent, the conditions shall control.
GENERAL CONDITIONS
19. The proposed work includes: the rehabilitation of existing sewer manholes located near
Rea's Pond and in the vicinity of Bridle Path and Winter Street. The project purpose is to
remove extraneous inflow and infiltration from entering the wastewater collection
system. Work is proposed within Bordering Vegetated Wetland (BVW) and Land Under
Waterbodies and Waterways (LUWW).
20. The work shall conform to the following:
Notice of Intent: Sewer Department Manhole Improvement Project Near
Rea's Pond and Bridle Path/Winter Street
June 18, 2009
Prepared for: Town of North Andover
Sewer Department
384 Osgood Street
North Andover, MA 01845
Prepared by: Thomass Keeffe
Tutela Engineering Associates
12 Bay Street
Wilmington, MA 01887
Site Plans prepared by: Thomas Keeffe,Tutela Engineering Associates
12 Bay Street,Wilmington, MA 01887
Titled:Sewer Manhole Rehabilitations,Winter Street Area;
Sheets 1, 2, &4; Dated: June 2009;Sheet 3 of 4
Revised: 7/22/09
Sewer Manhole Rehabilitations, Rea's Pond Area-1
Sheets 1-4
Dated: June 2009
Other Record Documents: Letter from Division of Fisheries &Wildlife
Dated:July 8, 2009
NHESP Tracking No. 09-26747
242-1455 Sewer Manhole Rehabilitations Rae's Pond&Bridle Path—Winter St.doc I NACC
8/14/2009
DEP FILE #242 - 1455
Letter from Division of Fisheries &Wildlife
Dated: August 10, 2009
NHESP Tracking No. 09-26747
21. The term"Applicant" as used in this Order of Conditions shall refer to the owner, any
successor in interest or successor in control of the property referenced in the Notice of
Intent, supporting documents and this Order of Conditions. The NACC shall be notified
in writing within 30 days of all transfers of title of any portion of property that takes place
prior to the issuance of a Certificate of Compliance.
22. The conditions of this decision shall apply to,and be binding upon, the applicant, owner,
its employees and all successors and assigns in interest or control. These obligations shall
be expressed in covenants in all deeds to succeeding owners of portions of the property.
23. Failure to comply with all conditions stated herein, and with all related statutes and other
regulatory measures, shall be deemed cause to revoke or modify this Order.
24. This Order does not grant any property rights or any exclusive privileges; it does not
authorize any injury to private property or invasion of property rights. However, the
NACC, agent of the NACC or the Department of Environmental Protection(DEP)
reserves the right to enter and inspect the property at all reasonable times until a
Certificate of Compliance is issued, to evaluate compliance with this Order of Conditions,
the Act (310 CMR 10.00), the North Andover Wetland ByLaw and Regulations, and may
require any information, measurements, photographs, observations,and/or materials, or
may require the submittal of any data or information deemed necessary by the NACC for
that evaluation. Further,work shall be halted on the site if the NACC, agent or DEP
determines that any of the work is not in compliance with this Order of Conditions.
Work shall not resume until the NACC is satisfied that the work will comply and has so
notified the applicant in writing.
25. This Order does not relieve the permittee or any other person of the necessity of
complying with all other applicable federal, state or local statutes, ordinances,by-laws or
regulations.
26. The work authorized hereunder shall be completed within three years from the date of
this order.
27. This Order may be extended by the issuing authority for one but not more than two
periods of up to one year each upon application to the issuing authority at least thirty
days(30) prior to the expiration date of the Order (Refer to Section VIII (B)(p.33) of the
North Andover Wetland Regulations).
28. The NACC reserves the right to amend this Order of Conditions after a legally advertised
public hearing if plans or circumstances are changed or if new conditions or information
so warrant.
242-1455 Sewer Manhole Rehabilitations Rae s Pond&Bridle Path_. W
inter St.doc 2 NACC
8/14/2009
DEP FILE #242 - 1455
29. Where the Department of Environmental Protection (DEP) is requested to make a
determination and to issue a Superseding Order, the Conservation Commission shall be a
party to all agency proceedings and hearings before the Department.
30. The following wetland resource areas are affected by the proposed work: Bordering
Vegetated Wetland (BVW) and Land Under Waterbodies and Waterways (LUWW) and
the buffer zones thereto. These resource areas are significant to the interests of the Act
and Town ByLaw as noted above and therein. The applicant has not attempted to
overcome the presumption of significance of these resource areas to the identified
interests.
31. The NACC agrees with the applicant's delineation of the wetland resource areas as
revised on Sheet 3 of 4 of the approved plan(Wetland Flags 2-001 through 2-014).
Wetland Flags in the Rae's Pond area are approximate and shall not be used for purposes
other than those proposed and approved in this Order.
32. The NACC finds that the intensive use of the upland areas and buffer zone proposed on
this site will cause further alteration of the wetland resource areas. In order to prevent
any alteration of wetland resource areas a twenty five foot (25') No-Disturbance Zone and
a fifty foot 50') No-Construction Zone shall be established from the edge of the adjacent
wetland resource except as follows: Waiver of the 25-foot No-Disturbance Zone and 50-
foot No-Build Zone for temporary disturbance within sewer easement. The Conservation
Administrator and/or other agents of the,NACC do not have the authority to waive these
setbacks as established under the local bylaw. No disturbance of existing grade, soils or
vegetation is permitted in the No-Disturbance zone except as noted herein. (See Section
I11(D) &Appendix G of the local Regulations).
33. Any temporary alterations to resource areas shall be substantially restored in accordance
with the approved methodologies and in accordance with the supporting documents
referenced herein and shall be restored to pre-existing hydrology and topography.
Wetland restoration shall include seeding with a wetland seed mix or plantings approved
by the Conservation Administrator. If construction is completed outside the growing
season, the applicant shall propose other methods of stabilization including mulching,
and/or matting the area with final restoration to occur when seasonally appropriate.
Restoration areas shall be monitored for 2 growing seasons following construction.
Reports, including photos, shall be submitted to the NACC following each growing
season.
34. This document shall be included in all construction contracts, subcontracts, and
specifications dealing with the work proposed and shall supersede any conflicting
contract requirements. The applicant shall assure that all contractors, subcontractors, and
other personnel performing the permitting work are fully aware of the permits terms and
conditions. Thereafter,the contractor will be held jointly liable for any violation of this
Order resultingfrom failure to comply with its conditions.
pY
242-1455 Sewer Manhole Rehabilitations Rae's Pond&Bridle Path Winter St.doc 3 NACC
8/14/2009
DEP FILE #242 - 1455
35.Issuance of these Conditions does not in any way imply or certify that the site or
downstream areas will not be subject to flooding, storm damage or any other form of
water damage.
PRIOR TO CONSTRUCTION
36. No work shall be undertaken until all administrative appeal periods from this Order have
elapsed or, if such an appeal has been filed, until all proceedings before the Department
or Court have been completed.
37. This Order shall be recorded by the applicant at the Registry of Deeds immediately after
the expiration of all appeal periods. No work shall be undertaken until the Final Order
has been recorded in the Registry of Deeds or the Land Court for the district in which the
land is located, within the chain of title of the affected property. In the case of recorded
land, the Final Order shall also be noted in the Registry's Grantor Index under the name
of the owner of the land upon which the proposed work is to be done.In the case of
registered land,the Final Order shall also be noted on the Land Court Certificate of Title
of the owner of the land upon which the proposed work is to be done. The recording
information shall be submitted to the North Andover Conservation Commission on the
form at the end of this Order prior to commencement of the work. Any Order not
recorded by the applicant before work commences may be recorded by the NACC at the
applicant's expense.
38. A sign shall be displayed at the sites not less than two square feet or more than three
square feet in size bearing the words"Massachusetts DEP, File Number 242-1455."
39. Any changes in the submitted plans caused by the applicant, another Board's decision or
resulting from this Order of Conditions must be submitted to the NACC for approval
prior to implementation. The Natural Heritage and Endangered Species Program
(NHESP) shall also be notified of any proposed changes in accordance with the letter
issued by NHESP and referenced herein. If the NACC finds said changes to be
significant, the NACC will call for another public hearing (at the expense of the
applicant). Within 21 days of the close of said public hearing the NACC will issue an
amended or new Order of Conditions. Any errors found in the plans or information
submitted by the applicant shall be considered as changes. No work shall begin on a
project until written approval has been granted by the NACC.
40. It is the responsibility of the applicant,,owner, and/or successor(s) to ensure that all
conditions of this Order of Conditions are complied with. The project engineer and
contractors are to be provided with a copy of this Order of Conditions and referenced
documents before commencement of construction.
242-1455 Sewer Manhole Rehabilitations Rae's Pond&Bridle Path Winter St.doc 4 NACC
8/14/2009
DEP FILE #242 - 1455
41. Prior to any work commencing on-site, the applicant shall submit to the NACC for
approval, a detailed sequence of construction, including the construction of compensation
and retention areas, installation of sedimentation/erosion control devices and re-
vegetation to be completed before other work begins on-site.
42. No work shall occur between 25 May and 4 July as recommended in the herein referenced
letter from NHESP.
43. Wetland flagging shall be checked prior to start of construction and shall be re-established
where missing. All wetland flagging shall remain visible and enumerated per the
approved plan(s) throughout the life of the project and until a Certificate of Compliance is
issued so that erosion control measures can be properly placed and wetland impacts can
be monitored. The proposed limit of work shall be shall be clearly marked with erosion
controls or temporary fencing and shall be confirmed by the NACC. Such barriers shall
be checked and replaced as necessary and shall be maintained until all construction is
complete. Workers should be informed that no use of machinery, storage of machinery or
materials, stockpiling of soil, or construction activity is to occur beyond this line at any
time.
44. A row of staked hay bales (certified "weed free" or salt marsh hay only per Division of
Fisheries &Wildlife letter referenced herein) backed by trenched siltation fence and other
erosion control detailed in the Notice of Intent shall be placed between all construction
areas and wetlands. The certified"weed free" erosion control barriers will be properly
installed and placed as shown on the plans approved and referenced herein and shall be
inspected and approved by the NACC or its agent prior to the start of construction and
shall remain intact until all disturbed areas have been permanently stabilized to prevent
erosion. All erosion prevention and sedimentation protection measures found necessary
during construction shall be implemented at the direction of the NACC or its agent. The
NACC reserves the right to impose additional conditions on portions of this project to
mitigate any impacts which could result from site erosion, or any noticeable degradation
of surface water quality discharging from the site. For example, installation of erosion
control measures may be required in areas not shown on the plan(s) referenced in this
Order of Conditions. Should such installation be required by the NACC, they shall be
installed within 48 hours of the Commission's request.
45. The applicant shall have on hand at the start of any soil disturbance, removal or
stockpiling, a minimum of 15 hay bales and sufficient stakes for staking these bales (or an
equivalent amount of silt fence, 1 hay bale to equal 3 feet of fence). Said bales shall be
used only for the control of emergency erosion problems and shall not be used for the
normal control of erosion.
46. Prior to the start of work suitable locations and methodologies for dewatering activities
shall be identified.
242-1455 Sewer Manhole Rehabilitations Rae's Pond&Bridle Path Winter St.doe 5 NACC
8/14/2009
DEP FILE # 242 - 1455
47. A check payable to the Town of North Andover shall be provided in the amount of$3,000
which shall be in all respects satisfactory to Town Counsel, Town Treasurer, and the
NACC, and shall be posted with the North Andover Town Treasurer through the NACC
before commencement of work. Said deposit of money shall be conditioned on the
completion of,all conditions hereof, shall be signed by a party or parties satisfactory to the
NACC, and Town Counsel, and shall be released after completion of the project, provided
that provisions, satisfactory to the NACC, have been made for performance of any
conditions which are of continuing nature. The applicant may propose a monetary
release schedule keyed to completionletion of specific portions of the project for the NACC's
review and approval. This condition is issued under the authority of the local ByLaw.
48. The applicant shall designate a Wetland Scientist(or other environmental professional as
approved by the NACC or its agent) as an"Erosion Control Monitor' to oversee any
emergency placement of controls and regular inspection or replacement of sedimentation
control devices. The name and phone number of the erosion control monitor must be
provided to the NACC in the event that this person has to be contacted, due to an
emergency at the site, during any 24-hour period, including weekends. This person shall
be given the authority to stop construction for erosion control purposes and will
immediately notify the Conservation agent of any matter that requires attention by the
Commission or the agent. The erosion control monitor will be required to inspect all such
devices and oversee cleaning and the proper disposal of waste products. Cleaning shall
include removal of any entrapped silt. At least once during each week in which
construction activities occurs on-site and for as long thereafter as ground remains
unstabilized, the applicant shall submit a written report from the "Erosion Control
Monitor" to the NACC certifying that, to the best of his/her knowledge and belief based
on a careful site inspection, all work is being performed in compliance with this Order of
Conditions and that approved setbacks are being adhered to. The erosion control monitor
must visually inspect all sedimentation/erosion control measures and assume
responsibility for their maintenance on,a weekly basis and that they are functioning as
intended. In addition, all wetland resource areas must be visually inspected for siltation,
turbidity, and/or other water quality impacts. The Erosion Control Monitor shall be on
site during and/or following a major storm event of 1/2" inch of rain or greater (24 hour
event) to ensure that soils remain stable, and erosion controls are adequate and secure.
49. Once these above mentioned pre-construction requirements are complete, the applicant
shall contact the Conservation Office prior to site preparation or construction and shall
arrange an on-site conference with an NACC representative, the contractor, the engineer,
wetland scientist and the applicant to ensure that all of the Conditions of this Order are
understood. This Order shall be included in all construction contracts, subcontracts, and
specifications dealing with the work proposed and shall supersede any conflicting
contract requirements. The applicant shall assure that all contractors, subcontractors and
other personnel performing the permitted work are fully aware of the permit's terms and
conditions. Thereafter, the contractor will be held jointly liable for any violation of this
Order of Conditions resulting from failure to comply with its conditions. The applicant or
contractor shall notify the NACC in writing of the identity of the on-site construction
242-1455 Sewer Manhole Rehabilitations Rae's Pond&Bridle Path Winter St.doc 6 NACC
8/14/2009
DEP FILE #242 - 1455
supervisor hired to coordinate construction and to ensure compliance with this Order. A
reasonable period of time shall be provided as notice of the pre-construction meeting(e.g.
72 hours).
11STORMWATER MANAGEMENT CONDITIONS
50. Water quality in down gradient BVW's shall not differ significantly following completion
of the project from the pre-development conditions. There shall be no sedimentation into
wetlands or water bodies from discharge pipes or surface runoff leaving the site.
DURING CONSTRUCTION
51. Upon beginning work, the applicant shall submit written progress reports every week
detailing what work has been done in or near resource areas,and what work is
anticipated to be done over the next period. This will update the construction sequence.
52. Approved de-watering activities anticipated shall be supervised and witnessed by the
designated erosion control monitor. De-watering activities shall be conducted as detailed
on the approved plans and shall be monitored daily by the erosion control monitor to
ensure that sediment laden water is appropriately settled prior to discharge toward the
wetland resource areas. No discharge of water is allowed directly into an area subject to
jurisdiction of the Wetlands Protection Act and/or the North Andover Wetland Bylaw. If
emergency de-watering requirements arise, the applicant shall submit a contingency plan
to the Commission for approval,which provides for the pumped water to be contained in
a settling basin, to reduce turbidity prior to discharge into a resource area.
53. To minimize disturbance to existing vegetation, swamp mats or other suitable material
approved by the NACC shall be used to access all work areas within wetland resources.
54. Clearing within the sewer easement to access sewer manholes shall be limited to an area
15-feet wide.
55. Any fill used in connection with this project shall be clean fill, containing no trash,refuse,
rubbish or debris, including but not limited to lumber,bricks,plaster, wire, lath, paper,
cardboard,pipe, tires, ashes, refrigerators, motor vehicles or parts on any of the
foregoing.
56. No exposed area shall remain unfinished for more than thirty (30) days, unless approved
by the NACC.
57. No re-grading in the buffer zone shall have a slope steeper than 2:1 (horizontal: vertical).
Slopes of steeper grade shall be rip-rapped to provide permanent stabilization.
242-1455 Sewer Manhole Rehabilitations Rae's Pond&Bridle Path Winter St.doc 7 NACC
8/14/2009
DEP FILE#242 - 1455
58. There shall be no stockpiling of soil or other materials beyond the limit of work
established by the erosion control line. No materials shall be stockpiled overnight within
100-feet of a resource area.
59. Washings from concrete trucks,or surplus concrete, shall not be directed to, any drainage
system, or wetland resource area. No truck washing shall occur within 100' of any
resource area.
60. All waste generated by, or associated with, the construction activity shall be contained
within the limit of work, and away from any wetland resource area. There shall be no
burying of spent construction materials or disposal of waste on the site by any other
means. The applicant shall maintain dumpsters (or other suitable means) at the site for
the storage and removal of such spent construction materials off-site. However, no trash
dumpsters will be allowed within 50' of areas subject to protection under the Act or local
Bylaw.
61. Accepted engineering and construction standards and procedures shall be followed in the
completion of the project.
62. During and after work on this project, there shall be no discharge or spillage of fuel, or
other pollutants into any wetland resource area. If there is a spill or discharge of any
pollutant during any phase of construction the NACC shall be notified by the applicant
within one (1) business day. No construction vehicles are to be stored within 100 feet of
wetland resource areas, and no vehicle refueling, equipment lubrication, or maintenance
is to be done within 100 feet of a resource area.
AFTER CONSTRUCTION
63. No underground storage of fuel oils shall be allowed on any lot within one-hundred (100)
feet of any wetland resource area. This condition shall survive this Order of Conditions
and shall run with the title of the property. This condition is issued under the authority
of the Town's Wetland protection ByLaw.
64. Fertilizers utilized for landscaping and lawn care shall be slow release, low-nitrogen types
(< 5%), and shall not be used within 25 feet of a resource area. Pesticides and herbicides
shall not be used within 100 feet of a wetland resource area. This condition shall survive
this Order of Conditions and shall run with the title of the property. This condition is
issued under the authority of the Town's Wetland Protection ByLaw and shall remain in
perpetuity.
65. Upon completion of construction and grading, all disturbed areas located outside
resource areas shall be stabilized permanently against erosion. This shall be done by
loaming and seeding according to NRCS standards. Seed mixes used for stabilization
shall be native per the NHESP letter. Seed mixes shall be approved by the Conservation
242-1455 Sewer Manhole Rehabilitations Rae's Pond&Bridle Path Winter St.doc 8 NACC
8/14/2009
DEP FILE #242 - 1455
Department prior to the end of construction.Stabilization will be considered complete
once full vegetative cover has been achieved.
66. Upon approved site stabilization by Conservation staff, the erosion controls shall be
removed and properly disposed of and all exposed unveg etated areas shall be seeded.
67. A post construction inspection by the Conservation Department shall be requested upon
final stabilization of the site.
68. Upon completion of the project the applicant shall submit the following to the
Conservation Commission as part of a request for a Certificate of Compliance:
a. WPA Form 8A- "Request for a Certificate of Compliance."
b. A letter from the applicant requesting a Certificate of Compliance.
c. The name and address of the current landowner.
d. Signed statements from the individual property owners shall be submitted with
the request for a Certificate of Compliance indicating that they read and
understood the recorded Order of Conditions prior to purchasing their property.
e. The name and address of the individual/trust or corporation to whom the
compliance is to be granted.
f. The street address and assessor's map/parcel number for the project.
g. The DEP file number.
h. A written statement from a Registered Professional Civil Engineer (and/or
Registered Professional Land Surveyor) of the Commonwealth certifying that the
work has been conducted as shown on the plan(s) and documents referenced
above, and as conditioned by the Commission.
i. An"As-Built" plan or final plans/documents submitted to the Town of North
Andover Sewer Department.
69. The following special conditions shall survive the issuance of a Certificate of
Compliance (COC) for this project:
➢ 25' No-Disturbance Zone and a 50' No-Construction Zone shall be
established from the edge of adjacent wetland resource areas except in those
locations approved under DEP# 242-1455. Future work within 100' of
existing wetland resource areas will require a separate filing with the NACC
(refer to Section XI (page 18) of the Regulations for performance standards
within these zones) The Conservation Administrator and/or other agents of
the NACC do not have the authority to waive these setbacks as established
under the local ByLaw;
➢
Discharge or spillage ofpollutants (Condition #62);
➢ Prohibition of underground fuels (Condition#63);
242-1455 Sewer Manhole Rehabilitations Rae's Pond&Bridle Path Winter St'.doc 9 NACC
8/14/2009 —
Massachusetts Department of Environmental Protection 242-1455
i
Bureau of Resource Protection - Wetlands MassDEP File Number
WPA Form 5 Order Of Conditions Document Transaction Number
Massachusetts Wetlands Protection Act M.G.L. c. 131, §40 North Andover
City/Town
E. Signatures,and Notary Acknowledgement
This Order is valid for three years, unless otherwise specified as a special k /` '9
condition pursuant to General Conditions#4, from the date of issuance. 1.Date of lss ance
Please indicate the number of members who will sign this form.
This Order must be signed by a majority of the Conservation Commission. 2.Number of signers
The Order must be mailed by certified mail(return receipt requested)or hand delivered to the applicant. A
copy also must be mailed or hand delivered at the same time to the appropriate Department of
Environmental Protection Regional Office, if not filing electronically, and the property owner, if different
from applicant.
Signatures: /i
Notary Acknowledgement
Commonwealth of Massachusetts County of Essex North
On this l4/ fh of /1909011— �Go 9
Day Month Year
Before me, the undersigned Notary Public, John Mabon
personally appeared Name of Document signer
proved to me through satisfactory evidence of identification,which was/were
Massachusetts License
Description of evidence of identification
to be the person whose name is signed on the preceding or attached document, and acknowledged to
me that he/she signed it voluntarily for its stated purpose.
As member of North Andover Conservation Commission
City/Town
2,1
Signature pfNotary Publi V _ 1,
Printed Name Notary Public
Place notary seal and/or any stamp above. /a1
My Commission Expires(D ')
This Order is issued to the applicant as follows:
❑ by hand delivery on ❑ by certified mail, return receipt requested, on
Date Date ® Notary Public
o Commonwealth of Massachusetts
My
wpaform5.doc• rev.11/08 May
Commission 16,,20014 EX�ireS
MPa e 9 of 11
May
Massachusetts Department of Environmental Protection 242-1455
Bureau of Resource Protection - Wetlands MassDEP File Number
WPA Form 5 — Order Of Conditions Document Transaction Number
I
Massachusetts Wetlands Protection Act M.G.L. c. 131, §40 North Andover
City/Town
F. Appeals
The applicant, the owner, any person aggrieved by this Order, any owner of land abutting the land subject
to this Order, or any ten residents of the city or town in which such land is located, are hereby notified of
their right to request the appropriate MassDEP Regional Office to issue a Superseding Order of
Conditions. The request must be made by certified mail or hand delivery to the Department, with the
appropriate filing fee and a completed Request of Departmental Action Fee Transmittal Form,as provided
in 310 CMR 10.03(7)within ten business days from the date of issuance of this Order. A copy of the
request shall at the same time be sent by certified mail or hand delivery to the Conservation Commission
and to the applicant, if he/she is not the appellant.
Any appellants seeking to appeal the Department's Superseding Order associated with this appeal will be
required to demonstrate prior participation in the review of this project. Previous participation in the permit
proceeding means the submission of written information to the Conservation Commission prior to the
close of the public hearing, requesting a Superseding Order, or providing written information to the
Department prior to issuance of a Superseding Order.
The request shall state clearly and concisely the objections to the Order which is being appealed and how
the Order does not contribute to the protection of the interests identified in the Massachusetts Wetlands
Protection Act(M.G.L. c. 131, §40), and is inconsistent with the wetlands regulations(310 CMR 10.00).
To the extent that the Order is based on a municipal ordinance or bylaw,and not on the Massachusetts
Wetlands Protection Act or regulations, the Department has no appellate jurisdiction.
Section G, Recording Information, is available on the following page.
wpaform5.doc• rev.11!08 Page 10 of 11
Massachusetts Department of Environmental Protection 242-1455
Bureau of Resource Protection - Wetlands MassDEP File Number
WPA Form 5 - Order of Conditions Document Transaction Number
Massachusetts Wetlands Protection Act M.G.L. c. 131, §40 North Andover
City/Town
G. Recording Information
This Order of Conditions must be recorded in the Registry of Deeds or the Land Court for the district in
which the land is located, within the chain of title of the affected property. In the case of recorded land, the
Final Order shall also be noted in the Registry's Grantor Index under the name of the owner of the land
subject to the Order. In the case of registered land, this Order shall also be noted on the Land Court
Certificate of Title of the owner of the land subject to the Order of Conditions. The recording information on
this page shall be submitted to the Conservation Commission listed below.
North Andover
Conservation Commission
Detach on dotted line, have stamped by the Registry of Deeds and submit to the Conservation Commission.
---------------------------------------------------------------------------------------------------------------------------
To:
North Andover
Conservation Commission
Please be advised that the Order of Conditions for the Project at:
Rea's Pond, Bridle Path, Winter Street 242-1455
Project Location MassDEP File Number
Has been recorded at the Registry of Deeds of:
Essex North
County Book Page
for:
Town of North Andover
Property Owner
and has been noted in the chain of title of the affected property in:
Book Page
In accordance with the Order of Conditions issued on -
Date
If recorded land, the instrument number identifying this transaction is:
Instrument Number
If registered land, the document number identifying this transaction is:
Document Number
Signature of Applicant
wpaform5.doc• rev.11/08
Page 11 of 11