HomeMy WebLinkAboutTOWN OF NORTH ANDOVER DEPT OF PUBLIC WORKS (5) Massachusetts Department of Environmental Protection
\ ,- Bureau of Resource Protection - Wetlands DEP File Number:
WPA Form 5 - Order of Conditions 242-1332
4
Massachusetts Wetlands Protection Act M.G.L. c. 131, §40
A. General Information
Important: North Andover
When filling From: 1.Conservation Commission
out forms on
the computer, 2. This issuance is for(check one): ® Order of Conditions ❑ Amended Order of Conditions
use only the
tab key to 3. To: Applicant:
move your
cursor-do not William Hmurciak Town of North Andover(DPW)
use the return a. First Name b.Last Name c.Company
key. 384 Osgood Street
d.Mailing Address
North Andover MA. 01845
e.City/Town f.State g.Zip Code
4. Property Owner(if different from applicant):
a. First Name b.Last Name c.Company
d.Mailing Address
e.City/Town f.State g.Zip Code
5. Project Location:
Wood Ave, Academy Rd, Chestnut St, Forest St North Andover
a.Street Address b.City/Town
Map 58, 60, 73, 106A Street Right of Way
c.Assessors Map/Plat Number d.Parcel/Lot Number
Latitude and Longitude, if known (note:
electronic filers will click for GIS locator): e.Latitude f.Longitude
6. Property recorded at the Registry of Deeds for(attach additional information if more than one parcel):
Essex North
a.County b.Certificate(if registered land)
c.Book d.Page
8/12/05
7. Dates: a.Date Notice of Intent Filed b.Date Oublit Hearing Closed cc.Date of4ssuance
8. Final Approved Plans and Other Documents(attach additional plan or document references as
neeriprf):
t.4'"?..t... �+.. L
a. Plan Title
Westin & Sampson Engineers, Inc. Ranthus B. Fouch, III, P. E.
b. Prepared By c.Signed and Stamped by
July 2005 1"=40'
d. Final Revision Date e.Scale
f.Additional Plan or Document Title g.Date
9. Total WPA Fee Paid: Exempt under 810 i
CMR 4.02 b.State Fee Paid c.City/Town Fee Paid
wpaform5.doc• rev.3/1105 Page 1 of 9
'L7, Massachusetts Department of Environmental Protection DEP File Number:
Bureau of Resource Protection - Wetlands
WPA Form 5 - Order of Conditions 242-1332
Massachusetts Wetlands Protection Act M.G.L. c. 131, §40
B. Findings
t. Findings pursuant to the Massachusetts Wetlands Protection Act:
Following the review of the above-referenced Notice of Intent and based on the information provided
in this application and presented at the public hearing, this Commission finds that the areas in which
work is proposed is significant to the following interests of the Wetlands Protection Act. Check all that
apply
a. ® Public Water Supply b. ❑ Land Containing Shellfish c. ® Prevention of Pollution
d. ® Private Water Supply e. ❑ f. Z Protection of Wildlife Habitat
g. ® Groundwater Supply h. Z Storm Damage Prevention i. ® Flood Control
2. This Commission hereby finds the project, as proposed, is: (check one of the following boxes)
Approved subject to:
® the following conditions which are necessary in accordance with the performance standards set forth
in the wetlands regulations. This Commission orders that all work shall be performed in accordance
with the Notice of Intent referenced above, the following General Conditions, and any other special
conditions attached to this Order. To the extent that the following conditions modify or differ from the
plans, specifications, or other proposals submitted with the Notice of Intent, these conditions shall
control.
Denied because:
❑ the proposed work cannot be conditioned to meet the performance standards set forth in the wetland
regulations. Therefore, work on this project may not go forward unless and until a new Notice of Intent is
submitted which provides measures which are adequate to protect these interests, and a final Order of
Conditions is issued.A description of the performance standards which the proposed work cannot
meet is attached to this Order.
❑ the information submitted by the applicant is not sufficient to describe the site, the work, or the effect
of the work on the interests identified in the Wetlands Protection Act. Therefore, work on this project may
not go forward unless and until a revised Notice of Intent is submitted which provides sufficient information
and includes measures which are adequate to protect the Act's interests, and a final Order of Conditions
is issued. A description of the specific information which is lacking and why it is necessary is
attached to this Order as per 310 CMR 10.05(6)(c).
Inland Resource Area Impacts: Check all that apply below. (For Approvals Only)
❑ Buffer Zone Impacts: Shortest distance between limit of project disturbance and
wetland boundary (if available) linear feet
Proposed Permitted Proposed Permitted
Resource Area Alteration Alteration Replacement Replacement
3. ❑ Bank a.linear feet b.linear feet c.linear feet d.linear feet
4. ❑ Bordering Vegetated —
Wetland a.square feet b.square feet c.square feet d.square feet
5. ❑ Land Under a.square-feet b.square feet c.square feet d.square feet
Waterbodies and
Waterways e.cu.yd dredged f.cu.yd dredged
Page 2 of 9
wpaform5.doc-rev.311105
\ Massachusetts Department of Environmental Protection DEP File Number:
Bureau of Resource Protection - Wetlands
WPA Form 5 - Order of Conditions 242-1332
Massachusetts Wetlands Protection Act M.G.L. c. 131, §40
B. Findings (cont.)
Resource Area Proposed Permitted Proposed Permitted
Alteration Alteration Replacement Replacement
6. ❑ Bordering Land
Subject to Flooding a.square feet b.square feet c.square feet d.square feet
Cubic Feet Flood
Storage e.cubic feet f.cubic feet -j.--cubic feet h:cubic feet
7. ❑ Isolated Land Subject
to Flooding a.square feet b.square feet
Cubic Feet Flood
Storage c.cubic feet d.cubic feet e.cubic feet f.cubic feet
8. ❑ Riverfront area a.total sq.feet b.total sq.feet
Sq ft Within 100 ft c.square feet d.square feet e.square feet f.square feet
Sq ft between 100-200 ft e.square feet f.square feet e.square feet f.square feet
Coastal Resource Area Impacts: Check all that apply below. (For Approvals Only)
s. ❑ Designated Port Indicate size under Land Under the Ocean, below
Areas
1o. ❑ Land Under the
Ocean a.square feet b.square feet
c.cu.yd dredged d.cu.yd dredged
11. ❑ Barrier Beaches Indicate size under Coastal Beaches and/or Coastal Dunes below
12. ❑ Coastal Beaches a.square feet b.square feet c.c/y nourishmt. d.c/y nourishmt.
13. ❑ Coastal Dunes a.square feet b.square feet c.cty nourishmt. d.c/y nourishmt
14. ❑ Coastal Banks a.linear feet b.linear feet
15. ❑ Rocky Intertidal
Shores a.square feet b.square feet
16. ❑ Salt Marshesa.square feet b.square feet c.square feet d.square feet
17. ❑ Land Under Salt
Ponds a.square feet b.square feet
c.cu.yd dredged d.cu.yd dredged
18. ❑ Land Containing
Shellfish a.square feet b.square feet c.square feet d.square feet
19. ❑ Fish Runs Indicate size under Coastal Banks, inland Bank, Land Under the
Ocean, and/or inland Land Under Waterbodies and Waterways,
above
a.cu.yd dredged b.cu.yd dredged
20. ❑ Land Subject to
Coastal Storm Flowage a.square feet b.square feet
wpaform5.doc• rev.311105 Page 3 of 9
Massachusetts Department of Environmental Protection DEP File Number:
Lll �
Bureau of Resource Protection -Wetlands
WPA Form 5 - Order of Conditions 242-1332
Massachusetts Wetlands Protection Act M.G.L. c. 131, §40
C. General Conditions Under Massachusetts Wetlands Protection Act
(only applicable to approved projects)
1. Failure to comply with all conditions stated herein, and with all related statutes and other regulatory
measures, shall be deemed cause to revoke or modify this Order.
2. The Order does not grant any property rights or any exclusive privileges; it does not authorize any
injury to private property or invasion of private rights.
3. This Order does not relieve the permittee or any other person of the necessity of complying with all
other applicable federal, state, or local statutes, ordinances, bylaws, or regulations.
4. The work authorized hereunder shall be completed within three years from the date of this Order
unless either of the following apply:
a. the work is a maintenance dredging project as provided for in the Act; or
b. the time for completion has been extended to a specified date more than three years, but less
than five years, from the date of issuance. If this Order is intended to be valid for more than three
years, the extension date and the special circumstances warranting the extended time period are
set forth as a special condition in this Order.
5, This Order may be extended by the issuing authority for one or more periods of up to three years each
upon application to the issuing authority at least 30 days prior to the expiration date of the Order.
6. Any fill used in connection with this project shall be clean fill. Any fill shall contain no trash, refuse,
rubbish, or debris, including but not limited to lumber, bricks, plaster,wire, lath, paper, cardboard,
pipe, tires, ashes, refrigerators, motor vehicles, or parts of any of the foregoing.
7. This Order is not final until all administrative appeal periods from this Order have elapsed, or if such
an appeal has been taken, until all proceedings before the Department have been completed.
8. No work shall be undertaken until the Order has become final and then has been recorded in the
Registry of Deeds or the Land Court for the district in which the land is located, within the chain of title
of the affected property. In the case of recorded land, the Final Order shall also be noted in the
Registry's Grantor Index under the name of the owner of the land upon which the proposed work is to
be done. In the case of the registered land,the Final Order shall also be noted on the Land Court
Certificate of Title of the owner of the land upon which the proposed work is done. The recording
information shall be submitted to this Conservation Commission on the form at the end of this Order,
which form must be stamped by the Registry of Deeds, prior to the commencement of work.
9. A sign shall be displayed at the site not less then two square feet or more than three square feet in
size bearing the words,
"Massachusetts Department of Environmental Protection" [or, WA DEP]
"File Number 242-1332
Page 4 of 9
wpaform5.doc• rev.311105
Massachusetts Department of Environmental Protection
Bureau of Resource Protection - Wetlands DEP File Number:
WPA Form 5 - Order of Conditions 242-1332
Massachusetts Wetlands Protection Act M.G.L. c. 131, §40
C. General Conditions Under Massachusetts Wetlands Protection Act
10. Where the Department of Environmental Protection is requested to issue a Superseding Order, the
Conservation Commission shall be a party to all agency proceedings and hearings before DEP.
11. Upon completion of the work described herein, the applicant shall submit a Request for Certificate of
Compliance (WPA Form 8A)to the Conservation Commission.
12. The work shall conform to the plans and special conditions referenced in this order.
13. Any change to the plans identified in Condition#12 above shall require the applicant to inquire of the
Conservation Commission in writing whether the change is significant enough to require the filing of a
new Notice of Intent.
14. The Agent or members of the Conservation Commission and the Department of Environmental
Protection shall have the right to enter and inspect the area subject to this Order at reasonable hours
to evaluate compliance with the conditions stated in this Order, and may require the submittal of any
data deemed necessary by the Conservation Commission or Department for that evaluation.
15. This Order of Conditions shall apply to any successor in interest or successor in control of the
property subject to this Order and to any contractor or other person performing work conditioned by
this Order.
16. Prior to the start of work, and if the project involves work adjacent to a Bordering Vegetated Wetland,
the boundary of the wetland in the vicinity of the proposed work area shall be marked by wooden
stakes or flagging. Once in place,the wetland boundary markers shall be maintained until a Certificate
of Compliance has been issued by the Conservation Commission.
17. All sedimentation barriers shall be maintained in good repair until all disturbed areas have been fully
stabilized with vegetation or other means.At no time shall sediments be deposited in a wetland or
water body. During construction,the applicant or his/her designee shall inspect the erosion controls
on a daily basis and shall remove accumulated sediments as needed. The applicant shall immediately
control any erosion problems that occur at the site and shall also immediately notify the Conservation
Commission,which reserves the right to require additional erosion and/or damage prevention controls
it may deem necessary. Sedimentation barriers shall serve as the limit of work unless another limit of
work line has been approved by this Order.
18. All work associated with this Order is required to comply with the Massachusetts Stormwater Policy
Standards.
Special Conditions:
If you need more See attached
space for -
additional
conditions,
select box to
attach a text _
document
Page 5 of 9
wpaform5,doc• rev,311/05
Massachusetts Department of Environmental Protection
Bureau of Resource Protection - Wetlands DEP File Number:
Ll
� �WPA Form 5 - Order of Conditions 242-1332
Massachusetts Wetlands Protection Act M.G.L. c. 131, §40
D. Findings Under Municipal Wetlands Bylaw or Ordinance
1. Is a municipal wetlands bylaw or ordinance applicable? 0 Yes ❑ No
2. The North Andover hereby finds(check one that applies):
Conservation Commission
3. ❑ that the proposed work cannot be conditioned to meet the standards set forth in a municipal
ordinance or bylaw specifically:
a. Municipal Ordinance or Bylaw b.Citation
Therefore, work on this project may not go forward unless and until a revised Notice of Intent is
submitted which provides measures which are adequate to meet these standards, and a final Order of
Conditions is issued.
4. ® that the following additional conditions are necessary to comply with a municipal ordinance or
bylaw:
North Andover Wetland Protection Bylaw Chapter 178
a.Municipal Ordinance or Bylaw b.Citation
The Commission orders that all work shall be performed in accordance with the following conditions
and with the Notice of Intent referenced above. To the extent that the following conditions modify or
differ from the plans, specifications, or other proposals submitted with the Notice of Intent, the
conditions shall control.
If you need more c. The special conditions relating to municipal ordinance or bylaw are as follows:
space for
additional See attached
conditions,
select box to
attach a text
document
wpaform5.doc• rev.311105 Page 6 of 9
DEP FILE #242 - 1332
Therefore, the North Andover Conservation Commission(hereafter the "NACC") hereby
finds that the following conditions are necessary, in accordance with the Performance
Standards set forth in the State Regulations, the local ByLaw and Regulations, to protect
those interests noted above. The NACC orders that all work shall be performed in
accordance with said conditions and with the Notice of Intent referenced below. To the
extent that the following conditions modify or differ from the plans, specifications or other
proposals submitted with the Notice of Intent, the conditions shall control.
GENERAL CONDITIONS
Mi
18. Failure to comply with all conditions stated herein, and with all related statutes and other
regulatory measures, shall be deemed cause to revoke or modify this Order.
19. This Order does not grant any property rights or any exclusive privileges; it does not
authorize any injury to private property or invasion of property rights. However, the
NACC, agent of the NACC or the Department of Environmental Protection(DEP)
reserves the right to enter and inspect the property at all reasonable times until a
Certificate of Compliance is issued, to evaluate compliance with this Order of Conditions,
the Act (310 CMR 10.00), the North Andover Wetland ByLaw and Regulations, and may
require any information,measurements,photographs, observations, and/or materials, or
may require the submittal of any data or information deemed necessary by the NACC for
that evaluation. Further, work shall be halted on the site if the NACC, agent or DEP
determines that any of the work is not in compliance with this Order of Conditions.
Work shall not resume until the NACC is satisfied that the work will comply and has so
notified the applicant in writing.
20. This Order does not relieve the permittee or any other person of the necessity of
complying with all other applicable federal, state or local statutes, ordinances,by-laws or
regulations.
21. The work authorized hereunder shall be completed within three years from the date of
this order.
22. This Order may be extended by the issuing authority for one or more periods of up to one
year each upon application to the issuing authority at least thirty days (30) prior to the
expiration date of the Order (Refer to Section 8.3 (p.37)of the North Andover Wetland
Regulations).
23. The NACC reserves the right to amend this Order of Conditions after a legally advertised
public hearing if plans or circumstances are changed or if new conditions or information
so warrant.
C:\Winword\000\DPWWatermain.doe I NACC 10/3/2005
DEP FILE # 242 - 1332
24. Where the Department of Environmental Protection (DEP) is requested to make a
determination and to issue a Superseding Order, the Conservation Commission shall be a
party to all agency proceedings and hearings before the Department.
25. This Order of Conditions is issued under File No.242-1332.
26. The conditions of this decision shall apply to, and be binding upon, the applicant, owner,
its employees and all successors and assigns in interest or control. These obligations shall
be expressed in covenants in all deeds to succeeding owners of portions of the property.
27. The term"Applicant" as used in this Order of Conditions shall refer to the owner, any
successor in interest or successor in control of the property referenced in the Notice of
Intent, supporting documents and this Order of Conditions. The NACC shall be notified
in writing within 30 days of all transfers of title of any portion of property that takes place
prior to the issuance of a Certificate of Compliance.
28. The proposed work includes: The installation of new water mains and five hydrants
along the right-of-way of several town owned streets including Chestnut Street,Forest
Street,Wood Avenue, and Academy Road within the buffer zone to Bordering
Vegetated Wetlands and several certified and potential vernal/ephemeral pools.
29. The work shall conform to the following (except as noted in the remainder of this
document where revisions may be required):
Notice of Intent filed by: Town of North Andover-Department of Public Works
(Applicant)
384 Osgood Street
North Andover, MA 01845
Prepared by: Weston & Sampson Engineers, Inc.
Five Centennial Drive
Peabody,MA 01960
Dated August 12,2005
Site Plans prepared by: Weston & Sampson Engineers, Inc.
Five Centennial Drive
Peabody, MA 01960
Dated July 2005
Signed & Stamped by Ranthus B. Fouch III, P.E.
Entitled: Water Main Replacement Contract 05-1,
Sheets 2-7.
Sheet 2 or G-1 entitled "Abbreviations, Notes, And Legend";
Sheet 3 or C-1 entitled "Forest Street";
Sheet 4 or C-2 entitled"Academy Road";
Sheet 5 or C-3 entitled "Chestnut Street";
CAW inword\00C\DPW Watermain.doc 2 NACC 10/3/2005
DEP FILE #242- 1332
Sheet 6 or C-4 entitled "Johnson Street";
Sheet 7 or C-5 entitled "Details".
Other Record Documents: Letter from Division of Fisheries &Wildlife Natural
Heritage Endangered Species Program dated September 9,
2005.
30. The following wetland resource areas are affected by the proposed work: Buffer Zone to
Bordering Vegetated Wetland (BVW) and certified/potential vernal/ephemeral pools
(local jurisdiction only). These resource areas are significant to the interests of the Act
and Town ByLaw as noted above and therein. The applicant has not attempted to
overcome the presumption of significance of these resource areas to the identified
interests.
31. The NACC agrees with the applicant's delineation of the wetland resource areas on the
site as shown on the plans referenced herein. However,the associated buffer zones
shown on the approved plans referenced herein are not approved under this filing.
32. The NACC finds that the intensive use of the upland areas and buffer zone proposed on
this site will cause further alteration of the wetland resource areas. In order to prevent
any alteration of wetland resource areas a twenty five foot (25') No-Disturbance Zone
and a fifty foot (50')No-Construction Zone shall be established from the edge of the
adjacent wetland resource area and a fifty foot(50') No-Disturbance Zone and seventy-
five (75') No-Construction Zone shall be established from the edge of any adjacent vernal
pool or potential vernal pool except in those areas as shown on the approved plans. A
waiver of the local 25' No-Disturbance Zone and the 50' No-Disturbance zone has been
granted to facilitate the installation of the new water mains. The Conservation
Administrator and/or other agents of the NACC do not have the authority to waive these
setbacks as established under the local bylaw. No disturbance of existing grade, soils or
vegetation is permitted in the No-Disturbance zone. (See Section 3.4 &Appendix F of the
local Regulations).
33. All work conducted along Forest Street shall be minimized to the greatest extent
feasible or altogether avoided during the amphibian breeding/migration season(March
15th through June 15th) to protect and minimize impacts to the identified
vernal/ephemeral pools or potential vernal/ephemeral pools. The applicant shall make
every effort to conduct work activities on Forest Street between November and March,
when amphibians are less likely to be present. The applicant shall notify the
Conservation Department prior to any work on Forest Street to verify that conditions
are suitable. To this effect, the sequence of construction shall clearly identify the
construction start and completion date on Forest Street to comply with said condition.
34. There shall be no increase in the post development discharges from the storm drainage
system or any other changes in post development conditions that alter the post
development watershed boundaries as currently depicted in the Notice of Intent and
C:AWimvord\OOC\DPWWattermain.doc 3 NACC 10/3/2005
DEP FILE # 242 - 1332
approved by this Order of Conditions, unless specifically approved in writing by the
Commission.
35. This document shall be included in all construction contracts, subcontracts, and
specifications dealing with the work proposed and shall supersede any conflicting
contract requirements. The applicant shall assure that all contractors, subcontractors, and
other personnel performing the permitting work are fully aware of the permits terms and
conditions. Thereafter, the contractor will be held jointly liable for any violation of this
Order resulting from failure to comply with its conditions.
36. The owners of the project and their successors in title, in the event they proceed to alter
areas subject to the Commission's jurisdiction under the order, agree that the Order does
not in itself impose upon the Town any responsibility to maintain the proposed drainage
system and that said Town shall not be liable for any damage in the event of failure. By
acceptance of this Order, the owners agree to indemnify and hold harmless to the Town
and its residents for any damage attributable to alterations undertaken on this property
pursuant to the Order.
37. Issuance of these Conditions does not in any way imply or certify that the site or
downstream areas will not be subject to flooding, storm damage or any other form of
water damage.
PRIOR TO CONSTRUCTION
38. No work shall be undertaken until all administrative appeal periods from this Order have
elapsed or, if such an appeal has been filed, until all proceedings before the Department
or Court have been completed.
39. This Order shall be recorded by the applicant at the Registry of Deeds immediately after
the expiration of all appeal periods. No work shall be undertaken until the Final Order
has been recorded in the Registry of Deeds or the Land Court for the district in which the
land is located, within the chain of title of the affected property. In the case of recorded
land, the Final Order shall also be noted in the Registry's Grantor Index under the name
of the owner of the land upon which the proposed work is to be done. In the case of
registered land, the Final Order shall also be noted on the Land Court Certificate of Title
of the owner of the land upon which the proposed work is to be done. The recording
information shall be submitted to the North Andover Conservation Commission on the
form at the end of this Order prior to commencement of the work. Any Order not
recorded by the applicant before work commences may be recorded by the NACC at
the applicant's expense.
40. Signs shall be displayed at each site/street location not less than two square feet or more
than three square feet in size bearing the words"Massachusetts DEP,File Number 242-
1332".
C:AWinword\OOC\DPWWatermain.doc 4 NACC 10/3/2005
DEP FILE #242 - 1332
41. Any changes in the submitted plans caused by the applicant, another Board's decision or
resulting from this Order of Conditions must be submitted to the NACC for approval
prior to implementation. If the NACC finds said changes to be significant, the NACC will
call for another public hearing(at the expense of the applicant). Within 21 days of the
close of said public hearing the NACC will issue an amended or new Order of Conditions.
Any errors found in the plans or information submitted by the applicant shall be
considered as changes.The proposed project may be still under review by other local or
state boards or agencies. This may result in changes to the project plans or wetland
impacts. If any such changes occur a revised plan and an explanation of the revisions shall
be submitted to the NACC for review and approval prior to the start of construction. No
work shall begin on a project until written approval has been granted by the NACC.
42. It is the responsibility of the applicant, owner, and/or successor(s) to ensure that all
conditions of this Order of Conditions are complied with. The project engineer and
contractors are to be provided with a copy of this Order of Conditions and referenced
documents before commencement of construction.
43. Prior to any work commencing on-site, the applicant shall submit to the NACC for
approval, a detailed sequence of construction, including the construction of compensation
and retention areas, installation of sedimentation/erosion control devices and re-
vegetation to be completed before other work begins on-site.
44.Wetland flagging shall be checked prior to start of construction and shall be re-
established where missing (several wetland flags were missing and/or not numbered
upon initial project review).All wetland flagging shall remain visible and enumerated
per the approved plan(s) throughout the life of the project and until a Certificate of
Compliance is issued so that erosion control measures can be properly placed and
wetland impacts can be monitored. The proposed limit of work shall be shall be clearly
marked with stakes or flags and shall be confirmed by the NACC. Such markers shall be
checked and replaced as necessary and shall be maintained until all construction is
complete. Workers should be informed that no use of machinery, storage of machinery or
materials, stockpiling of soil, or construction activity is to occur beyond this line at any
time. All flags used for the above purposes shall be of a color different from other
flagging used on the site.
45. A row of staked hay bales backed by trenched siltation fence shall be placed between all
construction areas and wetlands. If work along Forest Street cannot be avoided during
the specified time period (condition 33),the applicant shall ensure that the contractor
provides sufficient gaps in the siltation fence and/or haybale line along Forest Street in
order to allow the passage of breeding amphibians. Further,the applicant shall ensure
that once work has been completed and all disturbed areas have been stabilized against
erosion along Forest Street that the Conservation Department is immediately notified
to perform a final inspection for authorization of the removal of the erosion controls
(Forest Street only). All other erosion controls within the project corridor shall remain
in place and in tact until all work had been completed and the site has been fully
stabilized. The erosion control barrier will be properly installed and placed as shown on
C:AWinword\OOC\DPWWatermain.doc 5 NACC 10/3/2005
DEP FILE # 242 - 1332
the approved plans referenced herein and shall be inspected and approved by the NACC
prior to the start of construction and shall remain intact until all disturbed areas have
been permanently stabilized to prevent erosion, except as noted above. All erosion
prevention and sedimentation protection measures found necessary during construction
shall be implemented at the direction of the NACC. The NACC reserves the right to
impose additional conditions on portions of this project to mitigate any impacts which
could result from site erosion, or any noticeable degradation of surface water quality
discharging from the site. For example, installation of erosion control measures may be
required in areas not shown on the plan(s) referenced in this Order of Conditions. Should
such installation be required by the NACC,they shall be installed within 48 hours of the
Commissions request.
46. The applicant shall have on hand at the start of any soil disturbance, removal or
stockpiling, a minimum of 40 hay bales (10 at each street location) and sufficient stakes
for staking these bales (or an equivalent amount of silt fence). Said bales shall be used
only for the control of emergency erosion problems and shall not be used for the normal
control of erosion.
47. A check payable to the Town of North Andover shall be provided in the amount of
$2,500, which shall be in all respects satisfactory to Town Counsel,Town Treasurer, and
the NACC, and shall be posted with the North Andover Town Treasurer through the
NACC before commencement of work. Said deposit of money shall be conditioned on the
completion of all conditions hereof, shall be signed by a party or parties satisfactory to the
NACC, and Town Counsel, and shall be released after completion of the project, provided
that provisions, satisfactory to the NACC, have been made for performance of any
conditions which are of continuing nature. The applicant may propose a monetary
release schedule keyed to completion of specific portions of the project for the NACC's
review and approval. This condition is issued under the authority of the local ByLaw.
48. The applicant shall designate a Professional Wetland Scientist as the project's "Erosion
Control.Monitor" (ECM) to oversee any emergency placement of controls and regular
inspection or replacement of sedimentation control devices. The name and phone
number of the erosion control monitor must be provided to the NACC in the event that
this person has to be contacted, due to an emergency at the site, during any 24-hour
period, including weekends. This professional must submit a letter to the Conservation
Department, on company letterhead stating they have been retained as the project's
Erosion Control Monitor. The designated Erosion Control Monitor is subject to
approval by the NACC. This person shall also be given the authority to stop
construction for erosion control purposes. The ECM will be required to inspect all such
devices and oversee cleaning and the proper disposal of waste products. Cleaning shall
include removal of any entrapped silt.
49. On every MONDAY of each week, in which construction activities occurs on-site and for
as long thereafter as ground remains unstabilized, the applicant shall submit a written
report from the ECM to the NACC certifying that,to the best of his/her knowledge and
C:\Winrord',00C\D1'WWatermain.doc 6 NACC 10!3!2005
DEP FILE #242- 1332
belief based on a careful site inspection, all work is being performed in compliance with
this Order of Conditions and that approved setbacks are being adhered to. The EMC must
visually inspect all sedimentation/erosion control measures and assume responsibility for
their maintenance on a weekly basis and that they are functioning as intended. In addition,
all wetland resource areas must be visually inspected for'Siltation, turbidity, and/or other
water quality impacts. The erosion control monitor shall also be responsible for ensuring
that sufficient gaps are provided in the erosion controls within the specific locations as
outlined in condition 45.
50.The ECM shall be on site on a full time basis for any work performed on Forest Street to
ensure that the identified and potential vernal/ephemeral pool areas are not adversely
impacted.
51. The ECM shall be on site during and/or following a major storm event of 1 inch of
rain or greater to ensure that soils remain stable, erosion controls are adequate and secure,
and that all BMP's are adequately functioning.
52. Once these above mentioned pre-construction requirements are complete,the applicant
shall contact the Conservation Office prior to site preparation or construction and shall
arrange an on-site conference with an NACC representative,the contractor,the engineer,
wetland scientist and the applicant to ensure that all of the Conditions of this Order are
understood. This Order shall be included in all construction contracts, subcontracts, and
specifications dealing with the work proposed and shall supersede any conflicting contract
requirements. The applicant shall assure that all contractors, subcontractors and other
personnel performing the permitted work are fully aware of the permit's terms and
conditions. Thereafter, the contractor will be held jointly liable for any violation of this Order
of Conditions resulting from failure to comply with its conditions. The applicant or
contractor shall notify the NACC in writing of the identity of the on-site construction
supervisor hired to coordinate construction and to ensure compliance with this Order. A
reasonable period of time shall be provided as notice of the pre-construction meeting(e.g. 72
hours).
DURING CONSTRUCTION
53. Accepted engineering and Best Management Practices (BMPs) for construction standards
shall be followed in the conduct of all work.
54. Erosion control devices shall be inspected regularly; any entrapped silt shall be removed
to an area outside of the buffer zone and wetland resource areas; silt fence and hay bales shall .
be replaced as necessary. The areas of construction shall remain in stable condition at the
close of each construction day. All erosion controls shall be in place throughout the duration
of any construction on site or unless authorized by the Conservation personnel.
C:\Winword\UOC.DPWWatermain.doc 7 NACC 10/3/2005
DEP FILE # 212 - 1332
55. Upon beginning work, the applicant shall submit written progress reports every month
detailing what work has been done in or near resource areas, and what work is anticipated to
be done over the next,period. This will update the construction sequence.
56. All catch basins within 100' of a protected wetland resource area shall be adequately
protected as shown on the approved plans. Further protection may be required by the
Conservation Administrator and/or the Erosion Control Monitor at any time. All catch
basins shall be free of all accumulated silt and debris before Compliance is issued and the
owner or his/her agent shall so specify in the request for Compliance.
57. The Erosion Control Monitor shall be on site during and/or following a major storm
event of 1 inch of rain or greater to ensure that soils remain stable,erosion controls are
adequate and secure,and that all BMP's are adequately functioning.
58. Approved de-watering activities anticipated shall be supervised and witnessed by the
designated erosion control monitor. De-watering activities shall be conducted as shown on
the approved plans referenced herein and shall be monitored daily by the erosion control
monitor to ensure that sediment laden water is appropriately settled prior to discharge
toward the wetland resource areas. No discharge of water is allowed directly into an area
subject to jurisdiction of the Wetlands Protection Act and/or the North Andover Wetland
Bylaw. If emergency de-watering requirements arise, the applicant shall submit a
contingency plan to the Commission for approval, which provides for the pumped water to
be contained in a settling basin, to reduce turbidity prior to discharge into a resource area.
59. Any fill used in connection with this project shall be clean fill,containing no trash, refuse,
rubbish or debris, including but not limited to lumber,bricks, plaster,wire lath, paper,
cardboard, pipe, tires, ashes,refrigerators, motor vehicles or parts on any of the foregoing.
60. No exposed area shall remain unfinished for more than thirty (30) days, unless approved
by the NACC.
61. No re-grading in the buffer zone shall have a slope steeper than 2:1 (horizontal: vertical).
Slopes of steeper grade shall be rip-rapped to provide permanent stabilization.
62. There shall be no stockpiling of soil or other materials within twenty-five (25) feet of any
resource area.
63. The roadways shall be swept at least once per week or as directed by the Erosion
Control monitor,the Site Supervisor, Project Manager,or the Conservation staff for as
long as the site remainsexposed and unstabilized.
61. All exposed soil finish grade surfaces shall be immediately landscaped and stabilized, or
loamed, seeded and mulched, with a layer of mulch hay. All disturbed areas must be
graded,loamed and seeded prior to November 1st of each year.Outside of the growing
season, exposed soil finish grade surfaces shall be stabilized with a layer of mulch hay until
climate conditions allow for seeding. During construction, any area of exposed soils that will
C:\Winword\OOC\DPWWatermain.doc 8 NACC 10/3/2005
DEP FILE #242 - 1332
be left idle for more than 30 days shall be stabilized with a layer of mulch hay or other means
approved by the NACC.
65. Washings from concrete trucks, or surplus concrete, shall not be directed to, any drainage
system, or wetland resource area.
66. All waste generated by, or associated with, the construction activity shall be contained
within the construction area, and away from any wetland resource area. There shall be no
burying of spent construction materials or disposal of waste on the site by any other means.
The applicant shall maintain dumpsters (or other suitable means) at the site for the storage
and removal of such spent construction materials off-site. However, no trash dumpsters will
be allowed within 50'of areas subject to protection under the Act or local ByLaw.
67. Accepted engineering and construction standards and procedures shall be followed in the
completion of the project.
68. During and after work on this project, there shall be no discharge or spillage of fuel, or
other pollutants into any wetland resource area. If there is a spill or discharge of any
pollutant during any phase of construction the NACC shall be notified by the applicant
within one (1)business day. No construction vehicles are to be stored within 100 feet of
wetland resource areas, and no vehicle refueling, equipment lubrication, or maintenance is to
be done within 100 feet of a resource area.
AFTER CONSTRUCTION
69. No underground storage of fuel oils shall be allowed on any lot within one hundred (100)
feet of any wetland resource area. This condition shall survive this Order of Conditions and
shall run with the title of the property. This condition is issued under the authority of the
Town's Wetland protection ByLaw.
70. Fertilizers utilized for landscaping and lawn care shall be slow release, low-nitrogen types
(< 5%), and shall not be used within 25 feet of a resource area. Pesticides and herbicides shall
not be used within 100 feet of a wetland resource area. This condition shall survive this Order
of Conditions and shall run with the title of the property. This condition is issued under the
authority of the Town's Wetland Protection ByLaw and shall remain in perpetuity.
71. Upon completion of construction and grading,all disturbed areas located outside
resource areas shall be stabilized permanently against erosion. This shall be done either by
loaming and seeding according to SCS standards. If the latter course is chosen, stabilization
will be considered complete once vegetative cover has been achieved.
72. Upon approved site stabilization by Conservation staff, the erosion controls shall be
removed and properly disposed of and all exposed unvegetated areas shall be seeded.
C:AWinword\OOC\DPWWatermain.doc 9 NACC 10/3/2005
DEP FILE #242 - 1332
73. Upon completion of the project the applicant shall submit the following to the
Conservation Commission as part of a request for a Certificate of Compliance:
a. WPA Form 8A - "Request for a Certificate of Compliance."
b. A letter from the applicant requesting a Certificate of Compliance.
c. The name and address of the current landowner.
d. Signed statements from the individual property owners shall be submitted with
the request for a Certificate of Compliance indicating that they read and
understood the recorded Order of Conditions prior to purchasing their property.
e. The name and address of the individual/trust or corporation to whom the
compliance is to be granted.
f. The street address and assessor's map/parcel number for the project.
g. The DEP file number.
h. A written statement from a Registered Professional Civil Engineer (and/or
Registered Professional Land Surveyor) of the Commonwealth certifying that the
work has been conducted as shown on the plan(s) and documents referenced
above, and as conditioned by the Commission.
i. An"As-Built" plan prepared and signed and stamped by a Registered Professional
Civil Engineer (and/or Registered Professional Land Surveyor) of the
Commonwealth, for the public record. This plan will include:
r "As-Built" post-development elevations of all drainage &stormwater
management structures constructed within 200 feet of any wetland resource
area. NOTE: If portions of the stormwater systems exist partially within the
Buffer Zone than the entire structure must be depicted to accurately verify
compliance.
y "As-Built" post-development elevations and grades of all filled or altered
wetland resource areas including the encompassing buffer zone, which is
regulated as a resource area under the local Wetland Protection Bylaw.
Distances from structures to wetland resource areas. Structures include (but
are not limited to) septic systems, additions, fences, sheds, stone walls,
pools, retaining walls, subsurface utilities and decks.
y A line showing the limit of work and the extent of existing erosion control
devices. "Work" includes ay disturbance of soils or vegetation.
Location of all subsurface utilities entering the property.
74. The following special conditions shall survive the issuance of a Certificate of
Compliance (COC) for this project:
i 25' No-Disturbance Zone and a 50' No-Construction Zone shall be
established from the edge of adjacent wetland resource areas and a 50' No-
Disturbance Zone and a 75'No-Construction Zone shall be established from
any certified or potential vernal/ephemeral pool except in those locations
approved this filing. Future work within 100' of existing wetland resource
C:'WinFordl,00 \DPWWatermain.doc 10 NACC 10/3/2005
DEP FILE # 242 - 1332
areas will require a separate filing with the NACC. The Conservation
Administrator and/or other agents of the NACC do not have the authority
to waive these setbacks as established under the local ByLaw (Condition
#32);
Maintenance of catch basins (Condition #56);
;- Discharge or spillage of pollutants (Condition #68);
Prohibition of underground fuels (Condition #69);
r Limitations on the use of fertilizers, herbicides, and pesticides (Condition
#70).
C:\Winvord\OOC\DP WWatermain.doe I I NACC 10/3/2005
DEP FILE #242 - 1332
APPENDIX A- AFFIDAVIT
t, on oath do hereby depose and state:
(authorized agent applicant and/or current owner)
(PLEASE CHECK AT LEAST ONE BLOCK)
1. I am the of
(position with applicant) (applicant name or company name)
the applicant upon whom Order of Conditions
have been placed upon by (DEP or NACC number)
the North Andover Conservation Commission.
&/or
2. I am the of
(position with owner) (owner name)
the owner upon whose land Order of Conditions
have been placed up by (DEP or NACC number)
the North Andover Conservation Commission.
&
3. I hereby affirm and acknowledge that I have received said Order of Conditions
and have read the same and understand each
(DEP File#) and every condition which has been set forth
in said Order of Conditions.
&
4. I hereby affirm and acknowledge that on this day of 19
I inspected said property together with any and all improvements which have
been made to the same and hereby certify that each and every condition set
forth in Order of Conditions are presently incompliance.
(DEP File#)
&
5. I hereby affirm and acknowledge that this document will be relied upon by the
North Andover Conservation Commission as well as any potential buyers of
said property which is subject to said Order of Conditions
(DEP File#)
Signed under the pains and penalties of perjury this day of 19
(Signature-authorized agent of applicant or owner)
C:AWinword\OOC\DPWWatermain.doc 12 NACC 10/3/2005
Massachusetts Department of Environmental Protection DEP File Number:
Bureau of Resource Protection - Wetlands
WPA Form 5 - Order of Conditions 242-1332
Massachusetts Wetlands Protection Act M.G.L. c. 131, §40
E. Issuance
This Order is valid for three years, unless otherwise specified as a special / y' '`5 _
condition pursuant
General Conditions#4, from the date of issuance. 1.Date o Issuance
to
Please indicate the number of members who will sign this form:
This Order must be signed by a majority of the Conservation Commission. 2.Number of Signers
The Order must be mailed by certified mail (return receipt requested) or hand delivered to the applicant. A
copy also must be mailed or hand delivered at the same time to the appropriate Department of
Environmental Protection Regional Office, if not filing electronically, and the property owner,if different
from applicant.
Signatures:
J
r
Notary Acknowledgement
Commonwealth of Massachusetts County of
Essex North
On this pay of MonntH- Year
Before me, the undersigned Notary Public, SCc,4+
personally appeared Name of Document Signer
proved to me through satisfactory evidence of identification,which was/were
Massachusetts License
Description of evidence of identification
to be the person whose name is signed on the preceding or attached document, and acknowledged to
me that he/she signed it voluntarily for its stated purpose.
North Andover Conservation-Commission
As member of City/Town
Y a ��.>Y-WPOUT0
y `� racy Public r
of Massachusetts / p � .� Ia
/ Ay Commission Expires
1e 7.2f?47 Signatu a of Notary Public 4V"
IV
Printed Nar�(e of Notary Pu
I .
Place notary seal and/or any stamp aboveT��
My Commission Expires(Date) ¢� ,
This Order is issued to the applicant as follows:
by hand delivery on ❑ by certified mail, return receipt requested, on
Date Date
Page 7 of 9
wpaform5.00c• rev.311/05
Massachusetts Department of Environmental Protection DEP File Number:
Bureau of Resource Protection -Wetlands
WPA Form 5 Order of Conditions 242-1332
Massachusetts Wetlands Protection Act M.G.L. c. 131, §40
F. Appeals
The applicant, the owner, any person aggrieved by this Order, any owner of land abutting the land subject
to this Order, or any ten residents of the city or town in which such land is located, are hereby notified of
their right to request the appropriate DEP Regional Office to issue a Superseding Order of Conditions.
The request must be made by certified mail or hand delivery to the Department,with the appropriate filing
fee and a completed Request of Departmental Action Fee Transmittal Form, as provided in 310 CMR
10.03(7)within ten business days from the date of issuance of this Order. A copy of the request shall at
the same time be sent by certified mail or hand delivery to the Conservation Commission and to the
applicant, if he/she is not the appellant.Any appellants seeking to appeal the Department's Superseding
Order associated with this appeal will be required to demonstrate prior participation in the review of this project.
Previous participation in the permit proceeding means the submission of written information to the
Conservation Commission prior to the close of the public hearing, requesting a Superseding Order or
Determination, or providing written information to the Department prior to issuance of a Superseding Order
or Determination.
The request shall state clearly and concisely the objections to the Order which is being appealed and how
the Order does not contribute to the protection of the interests identified in the Massachusetts Wetlands
Protection Act, (M.G.L. c. 131, §40) and is inconsistent with the wetlands regulations(310 CMR 10.00).
To the extent that the Order is based on a municipal ordinance or bylaw, and not on the Massachusetts
Wetlands Protection Act or regulations, the Department has no appellate jurisdiction.
Section G, Recording Information is available on the following page.
Page B of 9
wpafcrm5.doc• rev.311105
Massachusetts Department of Environmental Protection DEP File Number:
Bureau of Resource Protection -Wetlands
WPA Form 5 - Order of Conditions 242-1332
Massachusetts Wetlands Protection Act M.G.L. c. 131, §40
G. Recording Information
This Order of Conditions must be recorded in the Registry of Deeds or the Land Court for the district in
which the land is located,within the chain of title of the affected property. In the case of recorded land,the
Final Order shall also be noted in the Registry's Grantor Index under the name of the owner of the land
subject to the Order. In the case of registered land, this Order shall also be noted on the Land Court
Certificate of Title of the owner of the land subject to the Order of Conditions. The recording information
on Page 7 of this form shall be submitted to the Conservation Commission listed below.
Conservation Commission
Detach on dotted line,have stamped by the Registry of Deeds and submit to the Conservation Commission.
--------------------------------------------------- -----------------------
To:
Conservation Commission
Please be advised that the Order of Conditions for the Project at:
Project Location DEP File Number
Has been recorded at the Registry of Deeds of:
County
Book Page
for:
Property Owner
and has been noted in the chain of title of the affected property in:
Book Page
In accordance with the Order of Conditions issued on:
Date
If recorded land,the instrument number identifying this transaction is:
Instrument Number
If registered land,the document number identifying this transaction is:
Document Number
Signature of Applicant
Pana A of A
v 3N ff1F
F '
Massachusetts Department of Environmental Protection
Bureau of Resource Protection - Wetlands
i DEP File Number:
WPA Form 8B — Certificate of Compliance
Massachusetts Wetlands Protection Act M.G.L. c. 131, 40 242-1332
Provided by DEP
A. Project Information
Important:
When filling out 1• This Certificate of Compliance is issued to:
forms on the Town of North Andover Department of Public Works
computer, use Name
only the tab
key to move 384 Osgood Street
your cursor- Mailing Address
do not use the North Andover MA. 01845
return key. City/Town State Zip Code
VQ 2. This Certificate of Compliance is issued for work regulated by a final Order of Conditions issued to:
Town of North Andover Department of Public Works
Name
10/3/05 242-1332
Dated DEP File Number
3. The project site is located at:
Wood Ave, Academy Rd. Chesnut St., Forest St North Andover
Street Address City/Town
Map 58, 60, 73, 106A Street Right of Way
Assessors Map/Plat Number Parcel/Lot Number
the final Order of Condition was recorded at the Registry of Deeds for:
Property Owner(if different)
Essex North
County Book
Page
Certificate
4. A site inspection was made in the presence of the applicant, or the applicant's agent, on:
1/19/07
Date
B. Certification
Check all that apply:
® Complete Certification: It is hereby certified that the work regulated by the above-referenced
Order of Conditions has been satisfactorily completed.
❑ Partial Certification: It is hereby certified that only the following portions of work regulated by the
above-referenced Order of Conditions have been satisfactorily completed. The project areas or work
subject to this partial certification that have been completed and are released from this Order are:
wpaform 8b.doc•rev,7/13/04
Page 1 of 4
Massachusetts Department of Environmental Protection
Bureau of Resource Protection - Wetlands DEP File Number:
WPA Form 8B — Certificate of Compliance
Massachusetts Wetlands Protection Act M.G.L. c. 131, 40 24vb
Provided Provided by DEP
B. Certification (cont.)
❑ Invalid Order of Conditions: It is hereby certified that the work regulated by the above-referenced
Order of Conditions never commenced. The Order of Conditions has lapsed and is therefore no
longer valid. No future work subject to regulation under the Wetlands Protection Act may
commence without filing a new Notice of Intent and receiving a new Order of Conditions.
® Ongoing Conditions: The following conditions of the Order shall continue: (Include any
conditions contained in the Final Order, such as maintenance or monitoring, that should continue
for a longer period).
Condition Numbers:
74
C. Authorization
Issued by:
North Andover d
Conservation Commission Date Ff!;Zinc
This Certificate must be signed by a majority of the Conservation Commission copy sent to the
applicant and appropriate DEP Regional Office(See Attachment).
Signatures:
wpaform 8b.doc-rev.7/13/04
Page 2 of 4
I
Massachusetts Department of Environmental Protection
Bureau of Resource Protection - Wetlands
WPA Form 8B — Certificate of Compliance DEP File Number:
Massachusetts Wetlands Protection Act M.G.L. c. 131, 40 242-1332
Provided by DEP
C. Authorization (cont.)
Notary Acknowledgement
Commonwealth of Massachusetts County of Essex North
On this D Day J4% OfR007Month Year
before me, the undersigned Notary Public, personally appeared
SCn,4 MCLSSR--
Name of Document Signer
proved to me through satisfactory evidence of identification, which was/were
Massachusetts License
Description of evidence of identification
to be the person whose name is signed on the preceding or attached document, and acknowledged
to me that he/she signed it voluntarily for its stated purpose.
As member of North Andover
cityrrown Conservation Commission
Signature of Notary Public or
nh .4 a,EOG
DOWKVMWE Pnn ed Nameo Notary Public
NOTARY PUBLIC
D T-
COMMONWEALTH OF MASSA C"'`,ETTS
My COMM.Expi,� /`i l!
My Co is ion pines(Date)
Place notary seal and/or any stamp above
-
Sig ture of Notary Public If
wpaform Bb.doc•rev.7/13/04
Page 3 of 4
ILI Massachusetts Department of Environmental Protection
Bureau of Resource Protection - Wetlands DEP File Number:
WPA Form 8B — Certificate of Compliance
Massachusetts242-1332
Wetlands t ands Protection Act M.G.L. c. 131, §40 Provided by DEP
D. Recording Confirmation
The applicant is responsible for ensuring that this Certificate of Compliance is recorded in the Registry of
Deeds or the Land Court for the district in which the land is located.
Detach on dotted line and submit to the Conservation Commission.
To:
North Andover
Conservation Commission
Please be advised that the Certificate of Compliance for the project at:
242-1332
Project Location DEP File Number
Has been recorded at the Registry of Deeds of:
County
for:
Property Owner
and has been noted in the chain of title of the affected property on:
Date Book Page
If recorded land, the instrument number which identifies this transaction is:
If registered land, the document number which identifies this transaction is:
Document Number
Signature of Applicant
wpaform Bb.doc•rev.7/13/04 Page 4 of 4
Massachusetts Department of Environmental Protection
Bureau of Resource Protection - Wetlands
DEP Regional Addresses
Massachusetts Wetlands Protection Act M.G.L. c. 131, §40
Mail transmittal forms and DEP payments,payable to:
Commonwealth of Massachusetts
Department of Environmental Protection
Box 4062
Boston, MA 02211
DEP Western Region Adams Colrain Hampden Monroe Pittsfield
Agawam ConwayWales 436 Dwight Street Y Hancock Montague Plainfield
Alford Cummington Hatfield Wales
Suite 402 Amherst Monterey Richmond Ware
Dalton Hawley Montgomery
Springfield,MA 01103 Ashfield Deerfield Heath g Rowe Warwick
Becket Monson Russell Washington
Phone:413-784-1100 Easthampton Hinsdale Mount Washington Sandisfield Wendell
Fax:413-784-1149 Belchertown East Longmeadow Holland New Ashford Savo
Bernardston Egremont Holyoke Y Westfield
Blandford Y New Marlborough Sheffield Westhampton
Erving Huntington New Salem Shelburne West Springfield
Brimfield Florida Lanesborough North Adams Shutesb
Buckland Gill Lea urY West Stockbridge
Charlemont Goshen Northampton Southampton Wilbrah
Cheshire Lenox Northfield South Hadley Wilbraham
Granby Leverett Orange
Southwick WilliamsburgChester Granville Leyden Otis Springfield
Williamstown
Chesterfield Great Barrington Longmeadow Palmer Stockbridge Windsor
Chicopee Greenfield Ludlow Pelham Sunderland Worthington
Clarksburg Hadley Middlefield Peru Tolland
DEP Central Region Acton Charlton Hopkinton Millbury Rutland Uxbridge
627 Main Street Ashburnham Clinton Hubbardston Millville Shirley Warren
Ashby Douglas Hudson New Braintree Shrewsbury Webster
Worcester,MA 01608 Athol Dudley Holliston Northborough Southborough Westborough
Phone:508-792-7650 Auburn Dunstable Lancaster Northbridge Southbridge West Boylston
Fax:508-792-7621 Ayer East Brookfield Leicester North Brookfield Spencer West Brookfield
Barre Fitchburg Leominster Oakham Sterling Westford
TDD:508-767-2788 Bellingham Gardner Littleton Oxford Stow
Westminster
Berlin Grafton
Lunenburg Paxton Sturbridge Winchendon
Blackstone Groton Marlborough Pepperell Sutton Worcester
BolBoltton borou h Harvard Maynard Petersham Templeton
9 Hardwick Medway Phillipston Townsend
Boylston Holden Mendon
Brookfield pe Milford Princeton UptonTyngsorough
Hopedale Royalston Upton
DEP Southeast Region Abington Dartmouth Freetown Mattapoisett Provincetown Tisbury
20 Riverside Drive Acushnet Dennis Gay Head Middleborough Raynham Truro
Lakeville,MA 02347 Attleboro Dighton Gosnold Nantucket Rehoboth Wareham
Avon Duxbury Halifax New Bedford Rochester Weilfieet
Phone:508-946-2700 Barnstable Eastham Hanover North Attleborough Rockland West Bridgewater
Fax:508-947-6557 y EastBridgewater Hanson
Berkley Norton Sandwich Westport
Bourne Easton Harwich Norwell Scituate West isbury
TDD:508-946-2795 Brewster Edgartown Kingston Oak Bluffs Seekonk Whitman
Bridgewater Fairhaven Lakeville Orleans Sharon Wrentham
Brockton Fall River Mansfield Pembroke Somerset Yarmouth
Carver Falmouth Marron Plainville Stoughton
Chatham Foxborough Marshfield Plymouth Swansea
Chilmark Franklin Mashpee Plympton Taunton
DEP Northeast Region Amesbury Chelmsford Hingham Merrimac Quincy Wakefield
1 Winter Street Andover Chelsea Holbrook Methuen Randolph Walpole
Boston,MA 02108 Arlington Cohasset Hull Middleton Reading Waltham
Ashland Concord Ipswich Millis Revere Watertown
Phone:617-654-6500 Bedford Danvers Lawrence Milton Rockport Wayland
Belmont Dedham Lexington Fax: 617-556-1049 Nahant Rowley Wellesley
Beverly Dover Lincoln Natick Salem Wenham
TDD:617-574-6868 Billerica Dracut Lowell Needham Salisbury West Newbury
Boston Essex Lynn Newbury Saugus Weston
Boxford Everett Lynnfield Newburyport Sherbom Westwood
Braintree Framingham Malden Newton Somerville Weymouth
Brookline Georgetown Manchester-By-The-Sea Norfolk Stoneham Wilmington
Burlington Gloucester Marblehead North Andover Sudbury Winchester
Cambridge Groveland Medfield North Reading Swampscott WinthropCanton
Hamilton Medford Norwood Tewksbury Woburn
Carlisle Haverhill Melrose Peabody Topsfield
wpaform8b.doc DEP Addresses-rev.1/22/07
Page 1 of 1