Enright, Jean
From:Lisa Eggleston [lisa@egglestonenvironmental.com]
Sent:Wednesday, January 25, 2012 2:21 PM
To:Hughes, Jennifer
Cc:Tymon, Judy
Subject:Volpe Center
Hi Jennifer,
Just want to let you know that I have reviewed the January 19, 2012 response packet from VHB on
the Merrimack College Volpe Center project, per your request. With the exception of the final
approval of the football field detention basin as-built conditions, which appears to be pending from
the Andover Conservation Commission, the submission satisfactorily addresses my review comments.
I have no additional comments on the project at this time.
I do remind you that an illicit discharge statement based on thorough investigation of the facility by
the plumbing engineer is still needed, and the as-built certification prepared by a PE at the
completion of project will need to include confirmation of the roof drainage areas in accordance with
the approved plans; these can be included in your Order of Conditions.
Let me know if you have any questions or need any additional information.
Lisa D. Eggleston, P.E.
Eggleston Environmental
Please note our new mailing address:
32 Old Framingham Rd., Unit #29
Sudbury, MA 01776
tel 508.259.1137
fax 866.820.7840
lisa@egglestonenvironmental.com
Please note the Massachusetts Secretary of State's office has determined that most emails to and from municipal offices and officials are public records. For more
information please refer to: http://www.sec.state.ma.us/pre/preidx.htm.
Please consider the environment before printing this email.
1