HomeMy WebLinkAboutMiscellaneous - Exception (546)b) All dumpsters must be placed on concrete. pads and enclosed on all sides with a
permanent fence. The location of the dumpsters must be reviewed and approved
by the Board of Health and Fire Department for conformance to their regulations.
2) Deliveries:
a) Deliveries to the site must be limited to between the hours of 7:00 a.m. and 9:00
p.m. with the exception of individual vendors approved by the Board of Health.
3) Hours of Operation:
a) The hours of operation of the retail/office complex will be between the hours of
6:00 a.m. and 12:00 midnight.
4) Parking/Uses•
a) The site as currently configured contains sufficient parking for retail/office use
only. No restaurants, seats, booths, stools, counters or table for eating or drinking
will be allowed without the closing off of some of the existing office/retail space or
the creation of additional parking spaces in a number sufficient to meet the
requirements of the Zoning Bylaw.
5) Prior to the endorsement of the plans by the Planning Board, the applicant must
comply with the following conditions: ,
ja) A FORM A plan must be submitted to the Planning Board for review and
approval separating the "back land" as shown on Exhibit A which will be
donated to the Trustees of Reservations.
The final plan must be reviewed and approved by the engineering
consultant, DPW and the Town Planner and subsequently endorsed by the
Planning Board. The final plans must be submitted for review within
ninety days of filing the decision with the Town Clerk.
c) A bond in the amount of ten thousand dollars ($10,000) shall be posted
for the purpose of insuring that a final as -built plan showing the location of
all on-site utilities, structures, curb cuts, parking spaces and drainage
facilities is submitted. The bond is also in place to insure that the site is
constructed in accordance with the approved plan. This bond shall be in
the form of a check made out to the Town of North Andover. This check
will then be deposited into an interest bearing escrow account.
2. Prior to the start of construction:
2