Carpentry:
Existing window to remain.
• Remove existing vanity base & dispose.
e Remove existing shower & dispose.
e Remove existing bath frame & dispose.
Remove any tile on the walls of the bathroom & dispose.
e Board & plaster where necessary, ceiling to have a smooth finish.
e Remove acrylic shower unit & dispose.
e Frame for custom shower (48" x 38").
e Frame for shampoo niche on the right wall of the shower to go from one end of the shower to the
other (36" x 18" high x 4" deep).
e Add support to the shower back wall to accept future grab bar installation.
e Add support to the right wall of the shower to accept fold down shower seat.
e Install clients fold down shower seat.
e Install cement board on the floor of the bathroom to prepare for tile installation.
e Install cement board on the walls of the shower to prepare for tile installation.
e Install clients vanity base 58" x 21" x 34'/2' w. four -doors w. three drawers with a floor mount roll
out in each of the sink bases.
e Install clients shower door — clear glass, chrome hardware (Weaver Glass)
e Install clients recessed medicine cabinets w. electrical inside above each sink. (medicine cabinet
size to be determined after bathroom demo).
Install clients white large crown molding on the ceiling perimeter of the bathroom.
e Install clients accessories (towel bar, toilet tissue holder, cabinet hardware).
Electrical:
o All electrical work will follow Massachusetts Code.
e Remove clients speaker system, he would like to send it back once it is down.
e All electrical receptacles and switches are to be decors white.
e Remove clients speaker and speaker control as carefully as possible, he would like to return the
unit.
e Relocate the electrical outlets to the left of the vanity area, either to be placed higher up on the wall
or in a completely different location.
• Add electrical inside of the vanity area:
e Remove the electrical for the existing jacuzzi bath.
e Supply & install one five inch recessed light in the shower area.
e Install clients two three bulb light fixtures over each sink in the vanity base.
e Supply & install two five inch recessed lights over the free standing tub area.
Supply & install electric heat on the floor of the bathroom w. separate thermostat.
e Install clients heat fan light in the ceiling of the bathroom w. timer switch:
0 Install clients hardwired towel warmer w. timer switch.