HomeMy WebLinkAboutCorrespondence - 800 JOHNSON STREET 5/30/2018 (3) 1
North .Andover Health Department
Community and Economic Development Division
August 24, 2017
TKZ, LLC
4 High Street, Suite 201
North Andover, MA 01845
Re: Subsurface Sewage Disposal System Plan for 1300 .Johnson Street (Map 38, Lot 1.06)
TKZ, LLC:
The proposed wastewater system design plan for the above site dated June 21, 2017 with a final
revision date of August 7, 2017. and received on August 7, 2017 has been approved.
The design has been approved for use in the construction of a new on-site septic system for a 4-
bedroom (max 9-room)home utilizing a gravity Leaching field system. This design plan approval
is valid until August 24, 2020.
During this time, a licensed septic system installer must obtain a permit and complete this work,
and a Certificate of Compliance be endorsed by the installer, designer and the Town of North
Andover.
This approval is also subject to the following conditions:
1. Prior to the issuance of the Disposal Works Construction Permit, the applicant must
submit a foundation as-built at the same scale as the approved plan;
2. Prior to the issuance of the Disposal Works Construction Permit, the applicant must
submit the floor plans of the proposed dwelling showing no greater than 4 bedrooms
or a total of 9 rooms;
1
_. ... ._..._... _ _. __ _...... _. . __._._.
i
I
Page 1 of 2
North Andover Health Department, Town Hall, 120 Main Street,
North Andover, MA 01845 Phone: 978.688.9540 lax: 978.688. 9542
800 Johnson Street August 24, 2017
3. If site conditions are found in the field to be different from those indicated on the
design plan and/or soil evaluation,the originally issued Disposal System Construction
Permit is void, installation shall stop, and the applicant shall reapply for a new
Disposal Systems Construction Permit (3 10 CMR 15.020(1));
4. It is the responsibility of the applicant and/or the applicant's septic system designer,
septic system installer or other representative to ensure that all other state and
municipal requirements are met. These may include review by the Conservation
Commission, Zoning Board, Planning Board, Building Inspector, Plumbing Inspector
and/or Electrical Inspector. The issuance of a Disposal System Construction Permit
shall not construe and/or imply compliance with any of the aforementioned
requirements.
Please feel free to contact the office with any questions you may have. We look forward to
working with you to obtain a wastewater treatment and dispersal system which will be in
compliance with all regulations and assure protection of public health and the environment of
North Andover.
Sincer-ply,
Brian f. LaGrasse, CEHT
Director of Public Health
Encl. Installers list
cc: John D. Sullivan, III P.E., Sullivan Engineering Group, LLC , P.O. Box 2004, Woburn,
MA 01888
File
.............................
Page 2 of 2
North Andover Health Department, Town Hall, 120 Main Street,
North Andover, MA 01.845 Phone: 978.688.9540 Fax: 978.688. 9542