HomeMy WebLinkAboutCorrespondence - 130 WINDKIST FARM ROAD 6/20/2018 (5) r
Of
II
North Andover Health Department
Community and Economic Development Division
August 14, 2017
Philip Christiansen,P.E.
Christiansen and.Sergi, Inc.
160 Surrraner Street
Haverhill, MA 01830
Re: .Lot 9 Windkist Farm Road (Map 109,Lot 54)
Dear Mr. Christiansen,
The proposed wastewater system design plan for the above site dated August 25, 2000 last
revised on June 30, 2017 and received on July 24, 2017 has been reviewed. Unfortunately, the
plan cannot be approved until the following items are corrected. The specific section in'Title 5:
310 CMR 15.000, or North Andover regulation that is not met by this design follows each item
where applicable,
1. On sheet 1. of 2, indicate the holder of the drain easement shown on the design plan (3 10
CMR 15.220(4)(c))
2. On sheet .1 of 2, a north arrow is not shown on the design plan (310 CMR 15.220(4)(8)).
3. 7'be statement indentifying the property is within or not within the watershed of Lake
Cochichewick is not depicted on the design plan(NA 3.2).
4. The designer certification is not depicted on the design plan (NA 3.2).
5. A note to indicate all system components shall be marked with magnetic marking tape is
not depicted on the design plan(3 10 CMR 15.221).
6. The foundation drain location and the elevation are not shown on the design plan (NA
3.2).
7. The profile view and site plan view both represent more than.36" of cover material above
the septic tank(3 10 CMR 15.221(7)).
8. The septic tank is required to be monolithic(NA 3.2).
9. The distribution box is required to be I1-20 (NA 3.2).
Page 1 of 2
North Andover Health Department, Town Hall, 120 Main Street,
North Andover,MA 01845 Phone: 978.688.9540 Fax: 978.688. 9542
10. Specify the manufacturer and model numbers for the septic tank and distribution box
(NA 3.2).
11. Please provide a note on the design plan to indicate that a riser to within 6"of finish
grade is required if the distribution box has more than 9" of cover material (3 10 CMR
15.221.(13) and 1.5,232(3)),
12. An inspection port is required (3 10 CMR 15.240(13)).
13. On sheet I of 2,the site plan view indicates the primary and reserve leach trenches are
49' long,
Please feel free to contact the office or Mill River Consulting at 978-282-0014 with any
questions you may have. We look forward to working with you to obtain a wastewater treatment
and dispersal system which will be in compliance with all regulations and assure protection of
public health and the environment of North Andover,
-ySincer ly,
me
rian I aGrasse, CERT
Director of Public Health
cc: Steven Knight
File
Page 2 of 2
North Andover Health Department, Town Hall, 120 Main Street,
North Andover,MA 01845 Phone: 978.688.9540 Fax: 978.688. 9542