HomeMy WebLinkAbout20170905 Misc./construction schedule - Miscellaneous - 25 ORCHARD HILL ROAD 2/9/2018 UMASS Kitchen to Office Conversion
r.REEN LEAF Construction Schedule
N.11 UCT...
ID Task Name Duration 1st Quarter 2nd Quarter 3rd Quarter
Jan Feb Mar A r Ma tun Jul
1 Grace Point Renovation 95 days
- ----- - - C I
2 Preconstruction 3S days
3 Issue Permit Documents/Apply for Permit 0 days 2/1 k
4 Finalize GMP 10 days 2/1 ' 2/14
5 i Order Steel 5 days 2/1 MMM 2/21
6 Steel Lead Time 4 wks ( 2/22 3/21
7 Furniture Install 13 days 3/5 IN 3/7
8 Construction 53 days p
9 Arch&MEP Demo 2 wks 3/8 3121
10 Cut Slab for Footings 3 days ( 3/8 g= 3/12
it New Footings 1 wk ? 3/13 EME 3/19
12 Structural Steel 1 wk + 3/20 EMM 3/26
- --13 : Infill Floor/Slab on Deck 3days 3/27 ME 3/29
14 ADA Lift Shaft -- - 1 wk 3/30 415
15 Paint _-- - - - - -- 4days 3/30 OW 4/4
16 Floor Leveler @ Quarry Tile 1 wk 4/5 NME 4/11
17 ADA Lift Z3 days 4/6 4/10
18 Metal Pan Stair 3 days 4/6 4/10
19 Infill Metal Pan Stair 2 days E 4/11 0 4/12
20 In Wall Inspections 2 days ( 4/12 4/13
21 Electrical Rough and Fire Alarm 11 wk 4116 EMM 4/23
--
22 Interior Window 1 wk ( 4/24 4/30
23 Plumbing Rough 2 wks 5/1 MEIIEMMM 5/14
24 Flooring 1 wk 5/15 111111111 5/21
25 Electrical Finish 1 wk , 5/15 5/21
26 Above Ceding Inspection/Rough Fire Inspection 0 days 5/21 I
27 Close Out 17 days
28 Final Building&Fire Inspection/C of O 2 days j I 5/22 5/23 I
29 Final Data Devices(UMass) 2wks ( 5/31 ` 6/13
Task Split Milestone ♦ Summary W"m--------V Critical Task NOMENNIONOM Progress
Grace Point Preliminary Schedule 2019 02 09 1 of 1