North Andover Health Department
Community and Economic Development Division
ONSITE WASTEWATER SYSTEM CONSTRUCTION NOTES
LOCATION INFORMATION
ADDRESS: 247 Forest Street MAP: 106.A LOT: 39
INSTALLER: John DiVincenzo
DESIGNER:
PLAN DATE:
BOH APPROVAL DATE ON PLAN:
Tank and D-box
INSPECTIONS
TANK INSPECTION: 6/18/2019 ok per Brian LaGrasse
DATE OF BED BOTTOM INSPECTION:
DATE OF FINAL CONSTRUCTION INSPECTION:
DATE OF FINAL GRADE INSPECTION: 6/19/2019
SEPTIC TANK
Building sewer in continuous grade, on
compacted firm base
Cleanouts per plan
Bottom of tank hole has 6” stone base
Weep hole plugged
1500 gallon tank has been installed
H-10 loading
Monolithic tank construction
Water tightness of tank has been achieved by
visual testing
Inlet tee installed, centered under access port
Outlet tee installed, centered under access port
(gas baffle/effluent filter)
_____ inch cover to within 6” of finish grade
installed over one access port
Hydraulic cement around inlet & outlet
Comments: Stone Base Inspections on 6/17/2019 – Brian LaGrasse
DISTRIBUTION-BOX
Installed on stable stone base
H-20 D-Box
Inlet tee (if pumped or >0.08’/foot)
Hydraulic cement around inlet & outlets
Observed even distribution
Speed levelers provided (not required)
Schedule 40 PVC Pipe
Comments:
Ok per Brian LaGrasse
Final Grade over tand and d-box ok seeded – Brian LaGrasse