Final construction inspection - 50 Sawmill Road
2 messages
Dan Ottenheimer<dano@millriverconsulting.com> Mon, Aug 12, 2019 at 7:56 AM
To: Brian LaGrasse <blagrasse@northandoverma.gov>, Stephen Casey<scasey@northandoverma.gov>, Toni Wolfenden
<tolfenden@northandoverma.gov>
Cc: Sandra Lezcano <sandral@millriverconsulting.com>
Brian, Stephen, Toni -
Attached is our report for the construction inspection which was completed on Friday at 50 Sawmill Road.
You will note there were some minor items still being tended to. I feel confident that the installer will complete these but if
you want to swing over and take a look you certainly can. They were:
• Cleanout on building sewer. The parts were at the site, it just had not yet been plumbed in
• Inlet tee. The tee was at the site, it was just not yet connected
• Manhole cover to grade over effluent filter. The cover was at the site, it had not yet been placed on the tank
• Hydraulic cement at d-box penetrations. This was about to be completed when I left
Any questions do let me know.
Dan
Daniel Ottenheimer, PE
President
https://mail.google.com/mail/u/0?ik=aOc6f4e4cf&view=pt&search=all&permthid=thread-f`/`3Al641662108722481257&simpl=msg-f%3A164166210872... 1/2
8/12/2019 Town of North Andover Mail-Final construction inspection-50 Sawmill Road
MILL RIVER CONSULTING
CiYauYe Soltttious for Unid Develolnnent
6 Sargent Street
Gloucester, MA 01930-2719
Phone: 978-282-0014 ext.802
www.miliriverconsulting.com
Member: New England Water Environment Association, Yankee Onsite Wastewater Association, Massachusetts
Environmental Health Association
c Construction Inspection Form 50 Sawmill Road.docx
63K
Toni Wolfenden <tolfenden@northandoverma.gov> Mon, Aug 12, 2019 at 8:25 AM
To: Dan Ottenheimer<dano@millriverconsulting.com>
Cc: Brian LaGrasse <blagrasse@north and overma.gov>, Stephen Casey<scasey@northandoverma.gov>, Sandra Lezcano
<sandral@millriverconsulting.com>
Thanks for the update.
Toni K. Wolfenden
Health Department Assistant
978-688-9540
...;cid:image002.jpg@01 CD02A1.85A49B40
[Quoted text hidden]
image001.jpg
4K
https://mail.google.com/mai I/u/0?ik=aOc6f4e4cf&view=pt&search=a II&permth id=thread-f%3A1641662108722481257&simpl=msg-f%3A164166210872... 2/2
Jack Sullivan <jacksull53@comcast.net> 4/9/2019 11:17 AM
re: 50 Saw Mill Rd, NA
To Toni Wolfenden <tolfenden@northando\,erma.gov>
Brian LaGrasse <blagrasse@northando\erma.gov>
Brian & Toni,
The approved Septic Plans required a few additional notes with Conservatiion...(add a silt
soxx detail, note on soi stockpile, and extension of the erosion control at site entrance. I
am attaching the plans and will drop off 3 stamped plans to your office on friday.
Sullivan Engineering Group, LLC /u
Jack Sullivan /�,� v
P.O. Box 2004
Woburn, MA 01888 I,hJ
781-854-8644
J
■`l EC ISYHI�7.
p 1 7 2.019
TOVIN01=HUMI1 ANDOVER
' aLFA:TIMENT
10/17/2018 Town of North Andover Mail-50 Saw Mill Road initial plan review
NORTH ANDOVER
Massachusetts Toni Wolfenden <twolfenden@northandoverma.gov>
50 Saw Mill Road initial plan review
1 message
Dan Ottenheimer<dano@millriverconsulting.com> Tue, Oct 16, 2018 at 4:38 PM
To: Brian LaGrasse <blagrasse@northandoverma.gov>, Michele Grant<mgrant@northandoverma.gov>, Toni Wolfenden
<tolfenden@northandoverma.gov>
Cc: Pam Lally<plally@millriverconsulting.com>
Attached please find initial plan review for 50 Saw Mill Road. A few notational adjustments are needed.
Please note the requests for reduced setback from the tank to the foundation wall, and a request for a reduced water
table offset request from 4'to 3' below the soil absorption system.
Please let me know if there are any questions.
Best,
Dan
Daniel Ottenheimer
President
' TMILL RIVER CONSULTING
C r tine&nlutitnis for Lakd Development
6 Sargent Street
Gloucester, MA 01930-2719
Phone: 978-282-0014 ext.802
www.millriverconsulting.com
https://mai l.goog le.com/mail/u/O/?ui=2&ik=a0c6f4e4cf&jsver=OfBPB7niE4Y.en.&cbl=g mai I_fe_181009.09_p3&view=pt&cat=M i I I%20River&search=cat... 112
10/17/2018 Town of North Andover Mail-50 Saw Mill Road initial plan review
Member: New England Water Environment Association, Yankee Onsite Wastewater Association, Massachusetts
Environmental Health Association,
'I 50 Saw Mill Road disapproval v1 October 16, 2018.doc
396K
https://mai l.goog le.com/mail/u/O/?ui=2&i k=a0c6f4e4cf&jsver=OfBPB7niE4Y.en.&cbl=gmail_fe_181009.09_p3&view=pt&cat=Mi 11%20 Rive r&search=cat... 2/2
Sullivan Engineering Group, LLC
Civil Engineers&Land Development Consultants
September 20, 2018
Town of North Andover RECEIVED
Board of Health
120 Main Street
North Andover, MA 01845 SEP 21 2018
TOWN OF NORTH ANDOVER
Re: 50 Sawmill Road, North Andover HEALTH DEPARTMENT
Septic Upgrade Plan
Board of Health;
Enclosed are the following as part of the Septic Upgrade Plan for the above property;
1) A completed Septic Plan submittal form
2) A check for$275.00 payable to "Town of North Andover" for septic plan review
3) A check for$100.00 payable to "Town of North Andover" for variance& LUA
4) Two (2) copies of the completed soil evaluator forms
5) Two (2) copies of Form 9A—Application for Local Upgrade Approval
6) Three (3) sets of the Septic Upgrade Plan
Additionally, due to severe site limitations involving wetlands, floodplain, and other design thresholds the
following variances are required from the Board of Health
1) A variance is requested on the required setback distance from a wetland to a soil absorption field
(100 feet required 72.1 feet provided) State code: 50 feet
2) Reduce minimum cover over septic tank(9 inches required 4 inches requested)
Please feel free to contact me with any questions.
AVery ly Y ,
ck llivan, PE
P.O. Box 2004 Woburn, MA 01888 (781) 854-8644 e-mail:jacksu1153@comcast.net