HomeMy WebLinkAboutGLSD - Organics to Energy Project - Correspondence - 240 CHARLES STREET 3/27/2018 To: Jay Spooner ospooner@methuenconstruction.com); Richard E.Weare
Cc: Irish, Joel R.; McCarthy, Mathew C.
_ Subject: Flare Variance
Attachments: DAGV 150 Install and Test_201803210632 - Flare Variance.pdf; Flare Factory Safety
Testing Results.pdf
Jay,
Attached is the plumbing board variance for the flare as an Unlisted Equipment. This variance requires a 3rd party
certified testing agency or Massachusetts registered engineer witness and submit a testing report for the equipment
prior to start up.
Can you reach out to Varec again regarding providing the " Field Evaluation Final Test Report" noted in the attached
variance. It would appear that performing the "Flare Factory Safety Test" on site witnessed by either a 3`d party or Mass
P.E.familiar with fuel gas train design a could satisfy the Board's testing requirement.
Thanks,
Lee Storrs CDM Smith 75 State Street,Suite 7011 Boston, MA 021091 Tf F: 617.452.6725 1 storrsel(@cdmsmith.com I
\\cdmsmith.com