HomeMy WebLinkAboutContract #: 1295 - From: 04-09-2020 To: 12-31-2020 - Woodard & Curran - DPW WOODARD&CURRAN
3. Preparing to serve or serving as a consultant or witness for Client in any litigation,arbitration or
other dispute resolution process related to the project.
FEE
The Client acknowledges that W&C's level of effort is a function of many factors depending on the duration
of the construction, Contractor's style and schedule, amount of activity during the warranty period, and
Client requests for services, as examples. The budget was prepared based on a projected 2-month
construction period.
Compensation for the Engineering Services described herein will be based upon the following budgets that
are not to be exceeded without prior written authorizations. If the construction schedule extends beyond the
2 month period, project budgets will be reviewed and a request for an adjustment may be submitted. The
budget for each phase of service is as follows:
Phase/Task Budget Compensation/Billing Method
Construction
Task 1.0 Design and Bidding $73,000 Lump Sum/Percent Complete
Task 2.1 General Supervision $38,400 Lump Sum/Percent Complete
Task 2.2 Resident Project Representative $47,400 Time&Materials
Task 2.3 Record Plans $7,200 Lump Sum/Percent Complete
Total Amount $166,600
The estimated fee for our services under this proposal is $166,600 and will not be exceeded without
approval by the Client.
Compensation is either lump sum billed by percent complete or time and materials as noted in the table
above. Lump sum Tasks 1.0,2.1 and 2.3 will be invoiced monthly on a percent complete basis. Task 2.2 will
be invoiced monthly on a time and materials basis.
SCHEDULE
Work shall commence on receipt of your Notice to Proceed. Design services will be completed within 60
calendar days from receipt of the Notice to Proceed and all services will be completed within 180 calendar
days from receipt of the Notice to Proceed, unless otherwise agreed to by the Town.
Page 7 of 7