2016-07-05 Monitoring Reports (B) 384 Osgood St
Sullivan Engineering Group, LLC Civil Engineers&Land Development Consultants Monitoring Report March 2, 2018 384 Osgood Street, North Andover (DPWBuilding) DEP File No.: 242-1681 Monitor: John(Jack)D. Sullivan,III P.E. Date of Inspection: March 2,2018 @ 2:45 pm Weather: 36 degrees/heavy rain 9EP Sign: Up &Visible from street * of Conditions recorded: Yes T _'._ n�st'ruction Schedule: On-file Wetland flagging: Present in field Erosion Control: Installed in correct location Emergency Erosion Control: Yes additional haybales available Bond: Town Project(n/a) Field Notes: - Inspection took place during 1"-2"rain event(heavy with high winds) - Catchbasin in front parking lot which was,previously flooding due to a clogged silt sac is now flowing freely(silt sac has been removed to unrestrict the flow) - Erosion control in good condition - Site is holding up really well;no signs of site erosion - Parking lot draining well - Site Photos: Four(4) PO Box 2004 Woburn, MA 01888 (781) 854-8644 e-mail:jacksu1153@comcast.net rc fl t� �R ,a A h ti �? �x � L 4 � �;.iL. �� I .�� �� i,:j � � 2 f �yf 4 �� z t r i� s� k � � _ _..._.. _. o t ��,.. <}�{ t R?. �, j Sf}2� �i �G � b}�, lttt[f � ` �1'1 st uy � � � F�,� 4 � t � � ti�� � `1fi"", � ;� ��t � �s n ; � � t ���� �� 4�. i t �1�a� �{tztfs i ( I �� �� � � it�t it�,t,? VV �Szz 11��������� i ���� � ���� I111 9 y � � ; � �{��,� 4 t��1 t t i�i t��t �k f� �1 �. �9 l���tt l�} Ati 1 � l.�f �, k �t S i;. �' ,'. l t f a# } n F W F t e r gr s ��' M } e bb { . # h a ; �tf V tf �F P r �i �z,P � v rsx E� ?fi, �iN�\,ti";.< ; ;•-`�"' #�,,hn.< F�',r s l r} a �;r �'t t -2"� t:� �t} ��",} .,,j'rA a s F�zu 9.r „r K i 4 g s r � 1 f w r f a d' r ; _ �w r w ,u- n w. a I r r, �. .. �`. � rv �„ _w �,.�r �,. � ti �� ,, M G. ,, ��. 7 _�� .. ., y :r� '�''"a �„ -. �. �.. :�...�. r.. y lM 1 �1�t sFS} ''} �". r� /. �, '. z�.. ���! (y� ��� 1 s i ?� _, ..., �r �,. �. �,� .-� � U r� ... n �, x o- .,_v-, .. y „, � _� �,� - � � � r ,> s. n;' - �w .� ...„ � ,. w �.. �i ,� �.. .,, :� i �� ram"' � � �_ - ,� '-- �. -� ,.�-;..r.� N .. .�,-_. „_, m * �, .„�- ;� - m - �;�� .. �, :, Sullivan Engineering Group, LLC Civil Engineers&Land Development Consultants Monitoring Report January 23, 2018 384 Osgood Street, North Andover (DPW Building) DEP File No.: 242-1681 Monitor: John(Jack)D. Sullivan, III P.E. Date of Inspection: January 23,2018 @ 3:45 pm Weather: 36 degrees/steady rain DEP Sign: Up &Visible from street Order of Conditions recorded: Yes Construction Schedule: On-file Wetland flagging_ Present in field Erosion Control: Installed in correct location Emergency Erosion Control: Yes—additional haybales available Bond: Town Project(n/a) Field Notes: - Inspection took place during forecasted 1"rain event(0.8" fell at time of inspection) - Site is holding up well;no signs of site erosion - Water ponding in front parking area; it appears the fabric under the double catchbasin maybe restricting water entering the basin - Erosion control in good condition - Site Photos: Five (5) PO Box 2004 Woburn, MA 01888 (781) 854-8644 e-mail:jacksu1153@comeast.net u 5 5 � < s —T ti I — isl 4.r M G r rx r� r, S yg1 I� a tetra i �r LL r i I � nF �ft"jii i la�ii '. �l `�"� �� cv � J r r• r u i 'g la t�l r ry _ r r•� � 1 s i I Jl, m � r, «4 ��M• I xt, rt � Y t�ri Y _ i s 1 i11 ��I �t� , s,.tare t soon - } t�'It� I c�� ��}1 Y{ �F t �~••t k t tfi�} x�w��l� �. „t t OR um ti ;;y t t` c Not 2w 2 yyy� tl{{ti•�S} I4 } i{x' 1 aRi AM I i I n ma, k 5 tr Sullivan Engineering Group, LLC Civil Engineers&Land Development Consultants Monitoring Report January 13, 2018 384 Osgood Street, North Andover (DPW Building) DEP File No.: 242-1681 Monitor: John (Jack) D. Sullivan, III P.E. Date of Inspection: January 13, 2018 @ 8:30 am Weather: 54 degrees/light rain DEP Sign: Up &Visible from street Order of Conditions recorded: Yes Construction Schedule: On-file Wetland flaggin& Present in field Erosion Control: Installed in correct location Emergency Erosion Control: Yes—additional haybales available Bond: Town Project(n/a) Field Notes: - Inspection took place due to 0,8"rain event Friday into Saturday morning - Site held up very well; no signs of erosion - Hydroseeded areas did not wash out - The front parking lot does not fully drain to the catchbasins; Area of puddling just to the right of the site entrance off of Osgood Street(See Photo 41) - Erosion control barriers still in good condition - Site Photos: Five (5) PO Box 2004 Woburn, MA 01888 (781) 854-8644 e-mail:jacksu1153@comeast.net k �t•N�,z ' r£fiin v t yy ,„ 4,N: � �� t 1 t •.,:, '{tt }fit �" 1`, �t 4 tt1 f e, y si• £�a � z�{ 1 '•ir �- 4}3 `.. t a t {t fi�� •t � 4, i ,'6'•; { �£t v 31 'v 1 `z 7}" ;Tt t nn 11#;�,i c s t.,r £ �rtry 5t{ti 1�t t` {k 1 tt�.. r4 �Ie V �3ti g t t t4£ ,, y ti {t}1y1 #�S tti i cif ti t, xW4 : rr•� � "n H4P# 4k z n z i €tfz . t t tit t t4 "`xv xi4 , a I � t r rs t } �t, 3 r i IWO �h t ztk, �t £ tii♦V����#s't t �qt i{��� }�tt �yi: tij{{t t a C �'y '� r• t. � ' a �� (� { P k F 1 a'fl t�t is" 4�,, { � ��, `��� 4 -`a;£tk£�l „4;1_:t•, i��a �� � � 1 ���a"��' �e i t ;��a � §�' �,�; �r u� �! � �'t P ^�� e I � '� � � Cyr:��,'� k�! s �� 1 £ 1 � ' �� a S �a t }Cs�S, $£ t � FS� F ���y �',, h t r ����:.a��j���' <' � � l; ��� t t a � � �� fi � � � �( x � �� ' � t r � �� �.. ``����tl� t �� �4�� x� " '„ t x } `��u rs �h m�: {t' '�j� tx`�tt�x. YS�€�n i� �.,��5�}}r t? t t M jy Y i � ��� �t A� ��� �� s �,� ��{��,�r �, r �Sh� «1�,�, i � ��" j t � t. � ��� y� 5��� t � 1 �� �����t�, t i hqi � �� ���sj i Cp'� �� v: � 5r tk 3 11�{k �� it iR{ r�'ifY# { t� � 4 s}z 4R i <°�'. i � jt 1 � rt`s��i�' � � r{> � �„ t� � � ` �' � S�j�i��������t��tet�{lj � k �� ��,,,,k?�s~q �� `fit k�,�r �' �: tAr c �5, <" t t. .„� ft 3�. e � � �� t t � :`�'t b � $�•` 4r',i' tnt� r s �s s2. 4i' x N r w r t W 1 q l� I� iti �7 r. �i �r #�� 1�` �� �' i2� � £i I,� �vy f s ti ( �, x> ,,t .i`, `i' ' ��q ty � ty.���+ ff t �� 1. 4 �� U� !. � ��� � � �{ „ 1 {� t 71 � j t �� :, � US` �e � � � t x ia� � �'f a� Yq x �$ �J 3 � 'a`} E7,�' 2 �t 2n� Cara '' a� �'t �0 ��{� � z '}� ' m�, � «� � � � �,�� ,. r � � � ��tzt �� t � , � $� �� _ �� S`"' tt. j � `� �� �� � t�i �7 iPt s., J � ttf, aj as KS �� j�.;�. .�,a;, � Y ��� � s�� <� ��,' �t r,., .� � _ z..C, } t g � A �1 � g, ��� L S �K l�§ {Z 1 u°4 =3:.. Y} ���" � It �`�r�i a ; ' ?; A �I�i Fi � �i� �� ,. _ �� �t s� �„ rw�� ���. �`' S tea �„ !� s Vf S� 15 t 31 �� � t t, m� t ' �:�'t� '� t +,itlt t �5 � � � 2 ���, �a � � �� yr i 'Y �� x� .,�._ +."�,� Sullivan Engineering Group, LLC Civil Engineers&Land Development Consultants Weekly Monitoring Report Week of November 27t , 2017 384 Osgood Street, North Andover (DPW Building) DEP File No.: 242-1681 Monitor: John (Jack)D. Sullivan, III P.E. Date of Inspection: November 28, 2017 @ 11:30 am Weather: 42 degrees/clear DEP Sign: Up &Visible from street Order of Conditions recorded: Yes Construction Schedule: On-file Wetland flagging: Present in field Erosion Control: Installed in correct location Emergency Erosion Control: Yes—additional haybales available Bond: Town Project(n/a) Field Notes: - Erosion control in good shape - All disturbed areas have been foamed; but have not been hydroseeded - Hydroseed with tackifier to be completed later this week or early next week - Concrete work has been completed out front - Some plantings have been installed in the riverfront area at the front of the site - Site Photos: Five (5) PO Box 2004 Woburn, MA 01888 (781) 854-8644 e-mail:jacksu1153@comcast.net �? .` �t � s� �. r � �,;� ig "� �' �4, E' t � � �� rt h # �� k t i:� � y !!_= 3 '��. � �fi� t ;, ,,�_;, � �'�" }; ��, �i�� �. �� w ,��,��p rr�� � �.. � v �, r {1' v r, r a� R IlFl �} f � � tr `i�4�� z�.� �� r Y � h i', 4 r ��� s 3 ���,,, �Y�4�r �` t�,°s� 4''i r�, � ) ,t � z, t5 t•. " � i � � � � � , v�� � F t „�. .�.„ J t � �. t � 1 s, � �«, t td `v t' �� �4 "'n { � � '� ��. '� 1. ]] k4 4¢i.. pb. t 't �I .„.k it u q� 9{ }�' �. f ;�� U ��� :k'�.t Yin ' a� EF ,1�� ;.., ��4 r �" �� � ,a>��" !., ya � � � 14�I �� r ii n ���� tit c e ; j ti,`� �� i� i y� �'¢� ate a� v��2 =' .. „-� it�'u a t �xz k�^�e �� r .� � � � � � o IM ROL w ,. _.. OW ra r s M r r n sky.. m . E*w � � I �rli � " Y A 4'J", �G Ila z � „ a w - nr= I I vY, f ,�` =x �y� �` � $��, �� .. �n„ . ti, w .. � � �. ,5s �,.. �� { �, �. -� � �,r y N �, � � ��� r � ,�� ��� M d �,_ , _�. . �r r �� F n ��,. w, - .... ,� .: �, z-,s �� � `� � , � # .- � � � � r�� 4 & v �..... -s .„ ' .... ..r ,.. �_.u,,.. _ --.'.. ..�,.. t e w. r 3 S '�` � � � w..�m. .r �,,i r � , w w r x w. _, y � ,. /` �� M v.. .ri % ,.v=/r�.� ... .v u � ..r.,�''"."fie° �. m 'n �; M � � � .�.„ 1 .. � 5' �: � � y«, s t „/- u v ti � N ` y4 ��' : 5 pY K. I x ... �-n o � � �. e: ,Y, r. �` t „r .. �.. .,. r " 5 v 4... a: y l � Sw �. ', ..y ,'v" r, Y � �._ e i crn �.C ,, ��. � w.. _t.. „u„� r. � - .,., ,; „R, `ft Yw .b c < ✓.,d p � , Y a s r x � �.. � '�� � � �r,�� � �, Y, =r t .. m -'n.„ .,, :. r ..c i...... y Y .. �... n � �,; � �h fix„ �r w r a 2 SL ,u Max 01 1h� � ry a- � i r � s i x r <r S 6 k µ f rr�^�2 r c r L Sullivan Engineering Group, LLC Civil Engineers&Land Development Consultants Weekly Monitoring Report Week of November 20th, 2017 384 Osgood Street, North Andover (DPW ildig) DEP File No.: 242-1681 Monitor: John(Jack) D. Sullivan, III P.E. Date of Inspection: November 21, 2017 @ 3:30 pm Weather: 57 degrees/clear DEP Sign: Up & Visible from street Order of Conditions recorded: Yes Construction Schedule: On-file Wetland flagging: Present in field Erosion Control: Installed in correct location Emergency Erosion Control: Yes additional haybales available Bond: Town Project (n/a) Field Notes: - Erosion control in good shape - All disturbed areas have been loamed; but have not been hydroseeded - Site superintendent said hydroseed, with tackifer, to be completed any day. - Walks are being formed; no concrete work yet - No signs of site erosion - Site Photos: Five (5) PO Box 2004 Woburn, MA 01888 (781) 854-8644 e-mail:jacksu1153@comcast.net 4 r � a �n P a n. a. m U F.v Mirv+ Y fg a..51 i I IN l IY � r�1 t i<; Y: f r t�Y 8 t��}t t 1 S '° i {`' ly s1'3' r ;•z }t.'�Yi+{'iz �i;k�t*;siiczZattt41r..t\ttt t�' 7�``�1��{�mf jz't}}}'���_ 7� �}�,y st t'�tt�`{}{il��.�3 t,lz. �S„<t. ti €'ht, tt iSit �'•iS�� rl����t i z t: tt'fii z#k t{ t� � 'lt��S t..t ,. _t.t_ { +�t2 �t�ax},.{ i;-t1'd 4 i et ttat t;•t \ s �t z�} �t n ��tr- t F�414 �4� ,°Ys,.r{ FC^ '(� ''•, �t� � �.,, rs�{,rt;°���,�) i ��i�t +�.° {� }a�tt� '�t•2:��Gn�#i��`�z�i�?;{4?�ksatz i-`k' �. p� t` U�>"t{ .tied z }i "�'z + t,s s,;e•t t,,, r n r Ktr t R 4 i' &`,t ,? R �k4t; f��t fl }.. t anti r;t iv�hz sa ttt t Ai i e. + �yY � - e 1 ! r= �a k d �u h i €1 rn � s EFYF s 4 P 4V1 V�1:S Judi �i t V/ Sullivan Engineering Group, LLC Civil Engineers&Land Development Consultants ekly Monitoring Report W elk of November 13th, 2017 384 Os Street, North Andover (DPW Building) DEP File No.: 242-1681 Monitor: John(Jack)D. Sullivan, III P.E. Date of Inspection: November 14, 2017 @ 3:00 pm Weather: 42 degrees/overcast DEP Sign: Up &Visible from street Order of Conditions recorded: Yes Construction Schedule: On-file Wetland flagging: Present in field Erosion Control: Installed in correct location Emergency Erosion Control: Yes additional haybales available Bond: Town Project(n/a) Field Notes: - Erosion control in good shape - Loamed areas have not been hydroseeded yet - No signs of site erosion - Appeared that most of the work taking place is inside the building - Site Photos: Four(4) PO Box 2004 Woburn, MA 01888 (781) 854-8644 e-mail:jacksu1153@comcast.net ��� � ¢ { >�: I i4d�i �py'?9;t�4 a, it �� �a 4 yf �� � � ` � ��_. M y �. �. w�w_;_N,n_sr-�' �. � � ;..� �� �_ �.� :. W��. � �� �_, �� �. s �� y ;' —. �. � , :� � ,. �. 5 2 rv, 3� K 'AJ m �� `/ �; Sn „� �� r` r �t,�1}� �' k ; t4 i 3 lr t ;� � kt ` fi3 ��lt 4s�#,fey, ;,l �� /' s 4 } 4ii �� �? g "E ck, E�'4 ,,,�y Ap ,�' Y 'S4 � � , —� ���,n. � 'r� i i fi &�(� t 8i� � 1 {k I 1, � S: I j�' � {. t4 �ti ,� r S' 4 A};�\ ��1� 2�3?s �y��z am 2P ` �k�\lY�l}? s t ii��k{;4 j r , �htlr t ��' ll`��r��y j� ti+�s������1�� . {�j �'�tz�'t� � ��}���t�14&;���y;��2s?tt lv:���� ��a.�� t,.ltir` �� �s,. te" ��� { �� �ti�� �: �. �. �'. aix,,.. s.�� �„, 4 0 wt 'i �,. .k A Ykh V iln 4 w $gk 9} ' . . l ?�t �a tz z V { P, 9 zaJ �ry i t� � I . N I ny fl t ✓�7 ��4,�, i 1 j f j I� "'I!.. 'III IIIIII I I. IIY i° Iliul�l�u i �I 11' C'W ! 1 i '„fir`-�-`" "�✓,:-„�, III I �I II I rt�I I !I III �l ? y v 1 t Sullivan Engineering Group, LLC Civil Engineers&Land Development Consultants dry Monitoring Report W. of November 612017 384 Osgood St , North Andover (][)PW Building) DEP File No.: 242-1681 Monitor: John(Jack) D. Suan,III P.E. Date of Inspection: November 6, 201 11:00 am Weather: 60 degrees/overe DEP Sign: Up &Visible from street Order of Conditions recorded: Yes Construction Schedule: On-file Wetland flagging: Present in field Erosion Control: Installed in correct location Emergency Erosion Control: Yes—additional haybales available Bond: Town Project(n/a) Field Notes: - Silt Sacs in catchbasins were cleaned of silt/debris buildup - Some rip-rap placed at outlet of drain pipe to brook in the rear; additional some rip-rap placed on exposed soil bank for stabilization over winter conditions. - Conducted site walk with Town officials and site superintendent on 11/6 to discuss site conditions prior to onset of winter. - Loam being placed and graded in front of site - Loam to be finished this week and to be hydroseeded. - Erosion control in good conditions; deficient sections of the mulch sock identified in the last report have been fixed(new mulch sock installed) - Site Photos: Five (5) PO Box 2004 Woburn, MA 01888 (781) 854-8644 e-mail:jacksu1153@comeast.net A �,;�.. � , z � � ���+ � � hry ��" .:` ':' �' � � �` �,�a 't ����' ,; r,s � a 4Y ` ' r �'. "� , { � � � � �- �-� � � � �� � y. �.�, Y ... � �.1„��a n i' e F.. law l # Yl ;t' twi 4 i„ 1 Kk 74, 4 Y{} t Ftv Y#'' 15 IN ON ain ' t 4t tt Al 51 aS 4 n r � Y} u �t �mog, x f T t �x x x+ 4 s 4 r V_j ,'tS v=1,.k,6 l a• } � {, ,.<3u , :. .,' <t'• .cx }x s e t.. ,.{,. x.. ?.., �'�, .. � c 4 n•<„n�,. .,,.,.,...,��., xx.t��,J�,�,}fxc'rt��tt } �,� n. x? tt x•y.x. .<d ,u. � ;x �< �x.r=$�, {i. .y: .:.,, 4 � �\x � � ', � ;. � �.,t � t T s. <{xtt`�?£ ,U, '�{�� '{rt {.�11'»�'�' e., Pk .,:t�ls1"h�sy„''s4=. ;:¢ �,u�.o <4 ,,• x,r �Y��,, t �, .� � �,'n< I }t�i �•. ,, x n f s�x' � � � �,; 'a� txttx try� # } }y 7 t 4 Utz ,1 t a ,.c ,�t x` a�x {"��+" ;,;' ��': :.:;;•. a ,>��,'tt`S �e w, - �, t v, x 1 C'xk t, s,> a ', � '� l� t try: 4t�} 4x$�C SS��$'ik}�. '.,.a •cm, .; < @ ff� � lit � t d �>�. t ! x t F 4 «„�t S t { 1x J ;off' t �' •} t 1 �} � t � 1 a a a, �. . � �� r lh a t� � • a ,c � a n v � R}1 Z Y 11 1 l F= , 5 11 ,x 3� a m a t3 } e; l a� r t - r: �'Y N I I t n f x ��I h 1 w ory� P V�n!III %/ y3 arse 5" F. YYYY L yy M� � I ry , p v Sullivan Engineering Group, LLC Civil Engineers&Land Development Consultants Weekly Monitoring Report Week of October 30th, 2017 384 Osgood Street, North Andover (DPW Building) DEP File No.: 242-1681 Monitor: John(Jack)D. Sullivan, III P.E. Date of Inspection: November 2, 2017 @ 10:00 am Weather: 65 degrees/clear DEP Sign: Up &Visible from street Order of Conditions recorded: Yes Construction Schedule: On-file Wetland flagging: Present in field Erosion Control: Installed in correct location Emergency Erosion Control: Yes additional haybales available Bond: Town Project(n/a) Field Notes: - Had a 0.91"rain event on 10/29 and a 0.34"rain event on 10/30 - Met with site superintendent to discuss some house keeping issues including cleaning all silt sacs in the catchbasins (see Photo#6); replacing some mulch sock in the front that is rotting out(see Photo #7); the need to rip-rap an exposed slope over the new drain pipe out to the brook(see Photo#3) - Site held up well to heavy rains earlier in the week - Site is still being graded and loamed - I was told site will be hydroseeded; I told the superintendent that if seed does not germinate they will need to apply haymulch for winter conditions. - Majority of erosion control in good condition. - Site Photos: Seven(7) PO Box 2004 Woburn, MA 01888 (781) 854-8644 e-mail:jacksu1153@comcast.net �=:� nn -;.� ., � i ,,: .. f _' e._,,, .. �. v �� ., _- s r r �v s Est a Ft 1 .. � 4 1 n= E F s 4 � i d k a a 3 � x i'z tkf � a as a � r� ',i' ...� �' ��� tilu ,y+y fa t �� y c� �� �tt`� � t y ,�: ,r.:,._, ±•.t� f } r _ r r c 4; kM�i t raj C t z n \i f rr ; t �y . tFvx ,t } x . ft{ 17j } s h�tr 1 � � r ' €f �s 2 r r F „ r 3 x y w n. w vN 9 r c u v a u u., t � m s M „K � � r t M MI jai LIN ------------ z P £ IN, M00m, 0 y. _ .. y„. ll y e v. r d, „ F r � , w „ 5. r, E: d .max z l 0 i Sullivan Engineering Group, LLC Civil Engineers&Land Development Consultants Weekly Monitoring Report Week of October 23r , 2017 384 Osgood Street, North Andover (DPW ilding) DEP File No.: 242-1681 Monitor: John(Jack)D. Sullivan,III P.E. Date of Inspection: October 25, 2017 @ 2:00 pm Weather: 65 degrees/rain DEP Sign: Up &Visible from street Order of Conditions recorded: Yes Construction Schedule: On-file Wetland flagging: Present in field Erosion Control: Installed in correct location Emergency Erosion Control: Yes additional haybales available Bond: Town Project (n/a) Field Notes: - Erosion controls barriers in good condition - Inspection took place during 0.88"rain event - No signs of site erosion - Spoke with project supervisor and site will be loamed/seeded by early next week; informed site supervisor that if grass does not germinate that haymulch would need to be spread over disturbed areas for winter conditions. - Site drainage working properly Site Photos: Five (5) PO Box 2004 Woburn, MA 01888 (781) 854-8644 e-mail:jacksu1153@comcast.net p Y t v r r, r '4 1 w vY i rd u _ a. �a s. ddJJ i � sa �t � tar t �. a `� s twt IR� 2 kO � t t } �f t e A '+ 6 r t" a Ms t # a c ONE ARN will JL t f M g t t u i } a 6 y 1 x AN �F i P y r �a x� a t i y{ rt ViQ �y 4 h� 2 i it`s t� 1�r e v { ¢ S r ut x p S b„ <7 k 4 �� e 1rt ,� "�; �. ��' �� °° r ���� �F .��pp � ��� � r��� C $$��� � � f .fix- j � �v�v� F '' ��'� .� �. p', ��,� � � �" � tt �� � � � � �� � � � � � �. ��k n .� .. ��� -� �� ��_ _.� � u �„ �- � "�,' �r���, S ��'.. -� � �- 6 / Sullivan Engineering Group, LLC Civil Engineers&Land Development Consultants Weekly Monitoring Report Week of October 16th, 2017 384 Osgood Street, North Andover (DPW Building) DEP File No.: 242-1681 Monitor: John(Jack)D. Sullivan, III P.E. Date of Inspection: October 16, 2017 @ 2:00 pm Weather: 55 degrees/clear DEP Sign: Up &Visible from street Order of Conditions recorded: Yes Construction Schedule: On-file Wetland flagging: Present in field Erosion Control: Installed in correct location Emergency Erosion Control: Yes additional haybales available Bond: Town Project(n/a) Field Notes: - Erosion controls barriers in good condition - Finish pavement has been installed in rear lot - Loam being installed in front of property; area being finished graded - No signs of site erosion; site is stable Site Photos: Six (6) PO Box 2004 Woburn, MA 01888 (781) 854-8644 e-mail:jacksu1153@comcast.net Ott: q 4�a ilk } A} SYf 4` .z „ t 4 4= 3 e1� 1 til p. L. 4 is It z,�t�h 1i t A, !y ksua r; � ffi t S tt, A. i >n �t �!,� �� s . �� ;, �' y;, z ,t � ��� t �t �st�:,`�4`,�`� � ..tty`� ti} �Yy}�;��j�i � a, ,, ygt r' li �i ,i' �'.., �t#. l.. iSp. �i 5 � �:t.,, �1 �� A e,r t Y e S [- � `€ a u �"' n � ,i$y� n j � ,� �'� 8 rz �, � t t �; � i � �, `€t� 4 t�tit i y �i ��� ,, ,� b§b i.tti �t�)£t r �� .. Zi�� .�.,r ',,,;, 3 �� ��, ,�� t� '�l 1 ' s� - 3 - 5 i s�Y � 1 � � � � sx '� � � � i 1� �`.� \. i�� { d� � .� � y 2(� { tt � t �t y� � t h + ,i �,. ti is �{�1���;� �t���t �� � � ,t �D r;� ,�� '. t 21 i 3s 5 � tt � fi u� ;�,� �.xa�w.�._�._, 'w,���a: .S.�,.:��.�.a.. ,.y,,..�.,.� ,.,,...��,�,li �t�. a� .�`` � � � �a..0,� � ,� .:��,.Z�zs'..���<. .,. ��,�, t t , 41 v X;. t*; 3 1 Fs t M � b t 2 If F+ � i rF X tt ri k4% B j i �l t ' p } p 77 S l��, ��4 �.k; f s, i. �k� d g >�'; '� { ' �� � ,a` $ �,� n r ._; `� emu, �." ,.. M1�, � }nl�y' . 3 fir` is�t�. } t 1 j a� 4 1 �� t� � fit., } 1'� � V, {� 2 ( t��e i, x� �� ���, ,Vti ii ,t �}��� yy It t���tY� ( �;• tt g 8 1'� §`t�;t�r ..,,. f�r 1 ,,. � �t � p U' � �5� �; i rk � n �i t ��S i � s ��' ¢'� f, r s� �� �s ,t` � � } i�tia� �s 3 { � , `���� i .�t '}sta3�� s ' �� �>�� ���a ,. �fi, �, ��lYl��s��� � �� P �� `k Ft.'�� j t 5 i st���..k��� � �. �Y. �� � t�'( uti��y� �ifs� ��tt ��}; ;� r � �a �„��, kr` �� t � 2�k ����`4 a }�' t � ��;-� '� � �� �� r� . ti tits� i� �� z $ �'��a}� r c���s� ��� }�tty �1u� y t� �t '�,f 3 � .y v "M ��3�V�,�3�k} ��i`�'2� �tb����4 � � \�g 1 i # �;�c`�i ';7 �a?t is it � sc �t bi:.4 A�'� f�� j�� t �' k ����`{��11`�j'`a��i i� ��� 1�7}Ja l�r4kxs. a �, M 1 , k,. ��r 7 me w y 3 mz �e r 1� uq> r � t � } S } �y }Y A fit �t 4 l \ i Sullivan Engineering Group, LLC Civil Engineers&Land Development Consultants Weekly Monitoring Report Week of October 9th, 2017 384 Osgood Street, forth Andover (DPW uilding) DEP File No.: 242-1681 Monitor: John (Jack)D. Sullivan, III P.E. Date of Inspection: October 9, 2017 @ 5:00 pm Weather: 75 degrees/rain DEP Sign: Up &Visible from street Order of Conditions recorded: Yes Construction Schedule: On-file Wetland flagging:ng: Present in field Erosion Control: Installed in correct location Emergency Erosion Control: Yes additional haybales available Bond: Town Project(n/a) Field Notes: - Erosion controls barriers in good condition - 0.37"rain event - No signs of site erosion - The majority of the vertical granite curbing has been installed in front parking lot Site Photos: Six (6) PO Box 2004 Woburn, MA 01888 (781) 854-8644 e-mail:jacksu1153@comcast.net tt III t;,'j �...,�, , � #���, 4b�t i g ��i f �{ ��i�, I n°„� t � . }fit 1 if�� �.} S ,�ts�t,� �° � �� i� �� � � ��t� �. ��4� �-�t= hi,�- �, ;; pp ,,, '� i5 r r �� t t�, t. sir � � 'u Y i�s, e �ti 1 �se�� e � u 4l1\ F��4tyj\}#�1 S e 4 i � �1 yy t � J l}}F^ kl # y} f S 3 _ 1Al f soli i �£j ��� �,�. 1 f2 s Yz �4•f'' q i �,1 �'� fit` }t��� � III�� 3 ��' tea, t�, +� 1 a � �i#"�, a .. � � � rr : v w � � 4 t jt �, �¢fl. � �> s it+ r�zv�`; }' .,' . � Y� �. f, , ti, E'g i., t � , 2 i t Ft 1 1 t } t it} 4 }b nxt t 1 S'•; '��,� tx s zz� �j tt{��� � n s,� �., � :I� \ 7tr�;z l lz� ���}z t t � � Z�i lt..'. �l .;•,�tt�� � t 3t t z�A€��A,, ' a Z , Z trx y �t3 ``piktlrtftailt c �t t�i• �t e �t a i � r� I y1 t la ) _,:,. _. 4 �, � � � � � 4 „`� � � r � E w �. �� < r „. __ E,�� � ,� �.` ,� �..;T- :. h,,,. � ,�, :, .... _� .., ;� r �ilf Ili V � i �, r s; t i �i � t s�,. f�( �irii.°N�1� (Y r y I M I� � � a1'�'I � i � �GY w . � � �_ �� 4 F i y 4 � a � +. w��� v. ` # d$ uS3�� <', f "Sv.. � 9 � � y r � �� �a rl� ,t a r it ��. � 4 � aS �#i��`1+�t ���a�, � ca "�� ���p� z i � �„ ����{ ��. ���y� a �� ,s<.,� ��� " t�� �d S' t ..� ,�'�:, � �r �. �, ,; �� r� �D� � .f � L�r�t ��st� 1,��y �' `� €s? � � �. ,� ����. v ,. ti`c �,t SS@@yy��, ''��f:�s t�RZ 3�� kv'��'� ,S�, a�= �� � �� �� �it .`- ��}.., t *.1 i �y�}l�t � a y� A t 'i r�a, 1� ', a k � $ �xk� �� 5 } f�,3�� .. Flu{d�'�� 3 �,�4 {R �`l t �$.,. it � 2 k. t 4 a� 1 y �, � ti: .,,c tF �a .., 1. ,� ,�,:r ,s �*" }�f i >` i�,,, �l {t, } 5 t } q�� � { } 4�d� F j its- Q � ��1 F i l .� � k�t tl t s ��y., r 2<i' i t e t t „ � za �; r ?,a .�4t � t� ='t � � �� �� ��, Sullivan Engineering Group, LLC Civil Engineers&Land Development Consultants Weekly Monitoring Report Week of October 2nd1 2017 384 Osgood Street, North Andover (DPW Building) DEP File No.: 242-1681 Monitor: John (Jack) D. Sullivan, III P.E. Date of Inspection: October 4, 2017 @ 4:00 pm Weather: 75 degrees/clear DEP Sign: Up &Visible from street Order of Conditions recorded: Yes Construction Schedule: On-file Wetland Ragging: Present in field Erosion Control: Installed in correct location Emergency Erosion Control: Yes additional haybales available Bond: Town Project(n/a) Field Notes: - Erosion controls barriers in good condition - No signs of site erosion - Shoulders off of paved surfaces have been rough graded - Granite curbing delivered to site and set to be installed Site Photos: Five (5) PO Box 2004 Woburn, MA 01888 (781) 854-8644 e-mail:jacksu1153@comcast.net M w. v w F „. „ r �g V ti. k 50 it m a ; x -°^ " ls- IS �- x ,. y w = � 'NO 11. Al Jr,ENO= n �x i \ �4 r i ' k t q Alk, t y d Y t < w r 4 1,. Z A$� 1 I 1 } I i e k� 9 „ „y £ i r z� �r t F i t F I r a 2 t t t:. uA ,, t ifoI , n. a tAt t N t S= t w � + y, m a n i Sullivan Engineering Group, LLC Cvll Engineers&Land Development Consultants Weekly Monitoring Report Week of September 25th, 2017 384 Osgood Street, North Andover (DPW Building) DEP File No.: 242-1681 Monitor: John (Jack)D. Sullivan, III P.E. Date of Inspection: September 26, 2017 @ 4:00 pm Weather: 84 degrees/clear DEP Sign: Up &Visible from street Order of Conditions recorded: Yes Construction Schedule: On-file Wetland flagging: Present in field Erosion Control: Installed in correct location Emergency Erosion Control: Yes additional haybales available Bond: Town Project (n/a) Field Notes: - Erosion controls barriers in good condition - No signs of site erosion - Front and rear lots have been paved(binder pavement) - Drainage structures at finished grade; catchbasins have silt sacs Site Photos: Five (5) PO Box 2004 Woburn, MA 01888 (781) 854-8644 e-mail:J'acksu1153@comcast.net I 01 kh 5 \g� 40? ' �f < 4, M1 �t z�T if4 9t21 i .1 i t✓ fit: i I i air \ � \: �\ .. ������� \ �������� �/�« ������\ :��\ ) ; � ^ � < :��\ � \ : � 2< / . � « � �\ t. « y �� : � ® ?\. « w : ° d � y mdd © © \ .� . � �,� : v .y � > .� :\y:© � - > i y ��� \ _ �: z � �° ����� : �\� \\�\ i 5 � � � \ 2 < �« 2 ��� <« � < © © S . y �.d < �<�m. : ». ƒ � .������>\ . � � ���\ \ . f� 2 m m .. AVII - 4 w „ r t t ti. t INN t t{}t q 35 f1 f 3 I- 4 s a a ' >?gAll ,4 a< maur - � u E' WY, 3sI ` t , o te. a 1 t V . 9 u f x .. u x, t� p 1 i & t t' t a ry t i i t, t psi t r t o t E F t F ti �tl , 1 4 y o A iww pto Sullivan Engineering Group, LLC Civil Engineers&Land Development Consultants Weekly Monitoring Report Week of September 18th5 2017 384 Osgood Street, North Andover (DPW Building) DEP File No.: 242-1681 Monitor: John(Jack) D. Sullivan, III P.E. Date of Inspection: September 19, 2017 @ 5:00 pm Weather: 64 degrees/light rain DEP Sign: Up &Visible from street Order of Conditions recorded: Yes Construction Schedule: On-file Wetland flagging: Present in field Erosion Control: Installed in correct location Emergency Erosion Control: Yes—additional haybales available Bond: Town Project(n/a) Field Notes: - Erosion controls barriers in good condition - Rear of property is prepared for paving - Front of site is being prepared for paving; manholes raised to finish grade - Catchbasins at front of site have filter fabric installed; grates still above rough site grade; ultimately silt sacs will be needed and will talk with site superintendent. - No signs of site erosion - Rear of property in good shape. Site Photos: Five (5) PO Box 2004 Woburn, MA 01888 (781) 854-8644 e-mail:jacksu1153@comcast.net z� , z 4 t. J' } } stills, ¢ A r i 1�r fk, i< "t<t t}fLl Q } t tb `ti l 1�t�1 i 4 is ��t a f 1� ... 7 ti. J t dj rz 4} a„ x«i P ,< . <. i ,x i �y A' y \ ^: . § . � . : �� . . , , , . . . ����> � : : 2\ �a , 2\ , > � > : � . � . � � ' >: � s � ! »< ` \\ � , ° � ® . d - i . � » \ ? . � � . � ^ � < . � \ . � . � � . : \ � \ �� ^ , \ � . ` : . . ® \ . � . ` � ° ^ ` » : . . �® » . } � � > � »l � \\ � < , s ? r : . . . , r . . . � � x. \ : : y , � � � \ � `>� : �\/ \ : . � » : . � . > « \ \ / \ � . � � � \ ~ � » � , � \ /� \ \ � \ »� < . & . ` � \ + ® . � � , < «< > , � : � ` >\ y � ° � � �\ : y \ } E , . ; a = � 2 : : � © : : . » �d��(� ° � . . �/% » \ ' � �©; : � �� ` ` ± . ` : . . 2` � 2 » a . . . \ . < � . {f? t, 1 z rs 4 '4 tt1 t1 tt, t l 1� t}��t t xti. y) t P E x r� z i� t� pp i z t t zi r'xn , =x a ls dt� t i x f ,,, Y r.. t � tw } s� �?f M Y �t 2� Sullivan Engineering Group, LLC Civil Engineers&Land Development Consultants Weekly Monitoring Report Week of September 11th, 2017 384 Osgood Street, forth Andover (DPW Building) DEP File No.: 242-1681 Monitor: John (Jack)D. Sullivan, III P.E. Date of Inspection: September 12, 2017 @ 4:00 pm Weather: 78 degrees/clear DEP Sign: Up &Visible from street Order of Conditions recorded: Yes Construction Schedule: On-file Wetland flagging: Present in field Erosion Control: Installed in correct location Emergency Erosion Control: Yes additional haybales available Bond: Town Project(n/a) Field Notes: - Erosion controls barriers in good condition - Rear of property is prepared for paving - Front of site is being prepared for paving (base material being installed/compacted) - No signs of site erosion - Rear of site is cleaned up nicely; awaiting pavement application; all structures set to finished grade Site Photos: Five (5) PO Box 2004 Woburn, MA 01888 (781) 854-8644 e-mail:jacksu1153@comcast.net y z" r a w p� tt t r , 1 a z r e� € n 4 a 4 V'd', t va •. '< >, yt,y t �� "i""}r` �s da, s s #k a»s a t,. ,vP„ {<...r} "�. � m}"" t r �<�;r� �P, " � ,,. wr 'w ��t` "� ya �} w +PS w W ai,➢ � s,� �v`' tr, Rk,m �.��_.R� ^ t r,�„r ", 4 l, e.wdm to " 1 it .#,re:lyt t jS., �w„p;''" � � a �t '+� � wc>=a Zz'�.:>• tl�`4 x'z'" ,w�<"` � � ,,{a ,ry P� m ,r..'kr iP'�y,. t '��",s, era, ,o •.. ,m ta ,= [ y of r u a 3 °; �t`�1?;s} �•�` v 1 �t � PU {t�7�<�`�7`kry54 t}}Au� � a,,aa,,.z �; , e i } s r> ! a w €:x y 's,.>"?_'. §tu w k s m r Y w r� a Wvp �U y , r 3e f v a, r s M xu r x x` r �r ter,. '9 r a s , ti s r, 1,4 4 f �Y 1 f y } a � 4 : Y is I f S s tt r t � 'td� {et�2 c � •. et l td r ti r �� tri a4is � 1}. ��z�'� •k"�i ��a. tF t SS rs�t ti tt }i �f� 4 z t..•, ek x { t1� y� z � y 4 i { cl},r, y y �• o a u � trs v .n r � r r t i a r A � F � ti w s. v: z 7, d, 1 " 0 hp a 1 ` c z- wg 6. f. V_ a y . �. x " x v Sullivan Engineering Group, LLC Civil Engineers&Land Development Consultants Weekly Monitoring Report Week of September 4t', 2017 384 Osgood Street, North Andover (DPWBuilding) DEP File No.: 242-1681 Monitor: John(Jack) D. Sullivan, III P.E. Date of Inspection: September 8, 2017 @ 1:00 pm Weather: 74 degrees/clear DEP Sign: Up &Visible from street Order of Conditions recorded: Yes Construction Schedule: On-file Wetland flagging: Present in field Erosion Control: Installed in correct location Emergency Erosion Control: Yes additional haybales available Bond: Town Project(n/a) Field Notes: - Erosion controls barriers in good condition - Silt Sacs have been installed in all newly installed catchbasins at rear of site (see photos) - Drainage castings have been raised to finish grade at front of site - Site will be finished graded soon for pavement installation - On 9/6 there was 1.7" of rain - On 9/7 there was 1.0" of rain; inspection took place on 9/8. No signs of erosion or drainage issues. Site Photos: Eight(8) PO Box 2004 Woburn, MA 01888 (781) 854-8644 e-mail:jacksu1153@comcast.net u � � M w Al .,-= :_ - �, 4 ME # ^ 5 �v $ Z r/ p ` .'"ram r'a "� qpola m'� s ` 3-7 9; T, A -tie iq Jot' s AA - e g ty AT i ' , SA kk lok -< P, _ r ". n ol Al � dz � .,,R. .� � P �, �yY�tit '• � 7 r e I y y r - , moll- 44 f f, fIN w, - uPAIL - MOM st �� r a,r fx s _ y IN r 4 . 77 o r t a rr � tryi LOT _.. pOCR � x r ' rw r a Ar . .`< s sit, ` t } t F~ 1tit 01 1 6 s Y43 't ; 1tJ t 1 � t t t t }'1,ii ..t> Z�' rF j " , V I, t.r f. 2"k� '�< s j�`r{�l};��ryt}��F t } xtt ,•em � !1 �{I a 3 '�"` t,."<x 3 t, fht ,s fs Jq > y tf kF r z t" . tts }, }� f•Y Yr t t1VtVJ+t �" in S''ttS tft}t f t 4 s i %1' t �J t i t i ,}tt f l u •< /t�\t14\3tYtt S1 F:x i 3;" i } 2ry }jts,2Y21}tlt�tsy t�t$tt21 y tt t " _ , t,; J;JFYlY+ JkYt t, IX ky e L txl4=rtt v{'tom t};: t 11�4} x}1U51 u41 Ytt t5 .1 x, 7 } rt _t�J,, }ll,.( l £d J3tsdi{S{iY+Yt 11 J 1t }i z 413 tf f}}ttx Yt Y ` k. { �S �, {ti }rr€Yr YtY J J{2 t4 , {`i 4t4k,2}`}it t Sxsly x t 1 j f 'Ni tt V s i14}2{ sttr'S�t t\t>ft �.1� r`�Y c JY o } i s t s ) 1 t. {t S,'j} t }{L' i tS It ttp Oil tfY ks D} { S S i c t IF i "� xAo f, aza }` t} ti �r tt J Y w r t vtY� ��} x <.: i Ilk" Rk t x f' }ttf ,y }tftf2� s rv, i"y f` s 4 Ni" d <` f MEN WPOVYW ........... L: INS .............................. .......... .......... sm was -0, ,�........�11� nffi 'M ak" ---------------------- .... . 71, "goof .. ........."I VW oil _,"'Awn A V,A "Ns M ;............ . .. ................. �Fx 1 All '70 MR, UP, AM onto �yw d talt "M, Ps #Y,?�:. - ."-•e�Ct t ' :>.'� , '.. _�,: $a'slg "°d� 99� �:N '�' ^*5 ;';(�; t, 4?g,,i 4 l 7 tit! i' at F u ik i S It ills N d � < y 1`fi,;,,74. I4 t �`ti t sd`�, to �emt ,; ba �`�t yplx`k'� �i`,i�S?•',.,,ts ��` � �»`,�� } 'F� .'t! mxl��k } s _ a N tsts ti , „ t � s a k� t tt k=k5 ;sti ' 46 r`Y ! ME k n a ! t ,7 { �a 4. f i t �vl:: Y� I� }Y, k r• r. e r c f^ I'III tJ 1 r-� gIIIV I r- i r r� x 12 y a I'll MY ly w. -� u a r r ,,'rr-rim` . -' Ap 16 ', m, aP MAR, nag W_. WWI ;Illy; 7 'ten '`^ aVal ram, n � 1-5 jut � r �r :All 'sr n .,, , Y Y t h x>$ s t tc��4 ��i,��1',j`'.:'• rft'fi i ��t 2 ., ',� ,��,. � r s �s,. � i �� � g. e t iz e[ t sS r t; a � t m Yt ti n r t { Zo u. ,10 3 i z �' �. .� � �" +F'�x �,`�ae�}t��r j�ue' 1 Ya ,,a .; i* ,•, tt •Y t I� c a t 9 � i m , k i AF l £k Ott, r y `�P'�ahla. 1 tiC r., m t E, +4 t v +. F M 4 4 t t t f, r t i r t � a t a Mg C � ".�%101 f IM pw AM r r � r e + e t ^2 h ii a w+ {}a qg\t ,rirr + � t r Lag { { ., } £ + zt 6. V 3.�za S 1, L r r t to ��i .?` �A 1., ,.3 '+ .a.. + 1 zXt'x. ( ` [ i a �`` °�>} ..:� t �. � ?.i� � g� �'ki :'lr,' lea.' + d � f}`� ��B�' 'it1 Al l n r F .+ t, £ r i ,�s�n tlr ,��' +4`ir�. t3l ti. ,n t Ij�$S'�l,,a <�;'.; a, a. s! �, �,�? £?a,, ' � c•�t+�1' ::;; ;. +d� lk .. n sr ., a"�^11 r. jSaa b Ott . }} t .. w w .�; 9 Sullivan Engineering Group, LLC Civil Engineers&Land Development Consultants Weekly Monitoring Report Week of August 28, 2017 384 Osgood Street, North Andover (DPW Building) DEP File No.: 242-1681 Monitor: John(Jack) D. Sullivan, III P.E. Date of Inspection: September 1, 2017 @ 11:00 am Weather: 74 degrees/clear DEP Sign: Up &Visible from street Order of Conditions recorded: Yes Construction Schedule: On-file Wetland flagging: Present in field Erosion Control: Installed in correct location Emergency Erosion Control: Yes additional haybales available Bond: Town Project(n/a) Field Notes: - Erosion controls barriers in good condition - Contractor has installed filter fabric as temporary protection to newly installed catchbasin grates; I spoke with contractor and these will be traded out for silt sacs next week - Drainage castings being raised to finish grade at front of site - Site will be finished graded soon for pavement installation Site Photos: Seven (7) PO Box 2004 Woburn, MA 01888 (781) 854-8644 e-mail:jacksu1153@comcast.net n x M u r� tF w. u v t i'" a= xa k r � �r a } , Y r r v—� s w. " r5 i may. M " r Y w " w r ` r �r r " r� t ry .o r � , m��F r �v " r w w. M �r r.. 7 7 a 77 i I i� �. ..; ,, tt to 5'Y f St( IN, Ys 5 i Q' f Ilk 4 Ct v § t 4 r "i}�4Pt�91tt� , 4 t� C t4c �t i `3�4�4tty � S' F 4 = t t £ y s t t J� tt t t } .tzi��1 fit}tit . { t \ £ y tAtF {tl Nilar $ } a tt3 a �,::., i „t' 1kit, � .F , f'•ta#;x x{ ))sty t(bzt G 1iu'sl t. 5`:a}F;t. 1tdU,�„ axal . A 1¢ 1 ,{x at x@try Isttlf r t E "TWA ,2? ' �4� � st 7t� It 3, tf x § u WNW?i t tt{ sy'4x' h ma's t t < tx�l;1 t t 'tt ,, man t t t�g $. i ,00 9 Y S % �h A�sy'�' x, .A ,,, it a j�S, ;t.,v 4r Ass"", � ��, _. �_! r �� �`�� `� `_°t'••` tv �� �{t � ;� ,� �»ix: si�`��.i'�§fit��„� tt #V>;� At, Anon- Wow t t sh? { Son I— , \ �t ;c st 1 i VA �i i a3 x`,�rtt S y m. 9 Xo ytS t xaF tt, _ •, Our �,., t s � x s 1xz tp�01 _ '. t,, v t t bxtx�yllirC �lx 'th\ It 0 out <: tSloxs ;, x t? T' l >ti .. r ------------- SA r A. . . -77 K,' OF am"mm" ck AMP OWN 06, Rol .._ s P" , am a ��� . ,�- .- , u r n rv, F t,z.� i h t�t�'` s�ut"T.'k� $.�t '~` �" 1t��' � it� 1� z� �� �;� tialstY�{ ��i '� ��� n }a,'a ...,. 1a t � x t1� t a ?Z h is t �� � a .' a {�� l � .> �a s�tst�St t � Cia ��' { .ta� c i st �{ S Sly s k f }rs��tl l� t}� j ;r�r s i� s a F U:� l kl t o � t o is �s a J, a -� �#;� a Kt' s{ {z7�{i s sf} ��{{ {s�gt as ��:: s �'}� �uk �r ��ss s�1 1{ � � a � ? .{t �s:� `; t i. { � s 4, t �s "�. 3;Sa�� y ,l t ,y.; { � '�i � � �{ } g� i ai t t to a i'f � tf 't �tt s { Gt t� a i s� � S t t# �!t .;�i a t e �a �Y y�, N � � �f� ,'a 'tit, sr;��s ,�,t�, 7 � ,3. �s � h 3>� s�.,,: t� �i� a` 6.. �{„r �`;, ti a''' t,',� t��'� ict�t{,C,a. �'1t�{� ,t 'it<� a �{ � s a`{`a' t �� f" t ,�44 � ,>4 t`t w t } SS t��,t ��a lat � - � [ t l' }t t t t�yt`: Y ?�s�?. s � +' s d � 3 '' ?+ �� t� ��� � ) t may; � � �'" I^'c��3, t i t+S 3y � '�� � t g � a�t � tf �� � 1 � r k s t > a { t� t't t,,t3 rt � t� �Y a��t,_ �'�i s Y `'•`t�s s,s >a � E 3t f# �{ � A � � s3 'S i ,. a ,, v t� " t � � t ,`( 4 t, 3 �� � � 4y�t � s r � f p t y� G �� � `� _ 2 � 3�t*� t 4f �, �� � �� iY r { 6�� ,} �' " �.{l 1{fti �. � ktt` � '� � # t� t t� t t .� � a �, tt a �t � i# i � {,. � � � a } tt�, t j f # � e x e 1 �y, �`^° S � to � ,t a��` t.r, s '} ff££ ,; �� t� �`} � Fi' . K � 1* � 1 ��i�:r�11 1'�s � i :tt, Gs� i t: � � t i Iu � § � 'Si 1 1 \ N. �'-�` tea '. {�`� �.,: � }t ' � �, t{ k��� xi ti.� � ._9 k ti f �tt 7t;� t,t � a< �t� F�X' C �t t '° �s r � � < tt�, s t 1a� ;. � t � r�s k � r��" t a�� Y i t i e �� ',> sa �:a �e � t� 1`r ; s,,.,; s 'i �`� �� L` tiE ��'�tea e .. 'a ,�. sr � 4� f a, a. r� ij?' a .' �;;1 a � 7`: (f# � r ��Y by � � i�, �, R ippp 1 5 j( ��I�'� ��� C t � ) I \ �'Y '� ,,,. q� ti.,�tt� �, ,� } ��'�a�2ktit��3 i f ��l�t�tt t t s{1 {�{�21�i\�}�t �t�i��}t��iF i} � \7 tv> t{Di)bq't a fi�'Y t ti a s s � � s eslti �.�' � s �a�tuti�„�.t �tv.s. t.,a�a�u� ;��s� Sullivan Engineering Group, LLC Civil Engineers&Land Development Consultants Weekly Monitoring Report Week of August 21, 2017 384 Osgood Street, North Andover (DPW Building) DEP File No.: 242-1681 Monitor: John(Jack) D. Sullivan, III P.E. Date of Inspection: August 25, 2017 @ 6:00 pm Weather: 74 degrees/clear DEP Sign: Up &Visible from street Order of Conditions recorded: Yes Construction Schedule: On-file Wetland flagging: Present in field Erosion Control: Installed in correct location Emergency Erosion Control: Yes additional haybales available Bond: Town Project(n/a) Field Notes: - Erosion controls barriers in good condition - Contractor has begun to fine grade rear of site for future paving - Silt Sacs not installed yet on new catchbasin grates...going to talk to contractor on Monday to do so; no evidence of any silt/soil entering basins. - No signs of erosion or silt migration; site is relatively stable Site Photos: Five (5) PO Box 2004 Woburn, MA 01888 (781) 854-8644 e-mail:jacksu1153@comcast.net ;��� �u Y v. 4� �. � pr � `� �Fl� .. �, �>> � � yY,, p �,- ,, 4�� !t., l { § �`� fi „� �, �!�� n �4 � �, �, ,., c s �y " ; �: a r ,.�a 4 . ���..� �"� ��. �, � .' ��� ��. h, �m eit° � � ,. ��s. �i �'.` ,. t� s ,'� :� �' �J �� ss � � �.a <.� � 4� � ,:, o- a,. y" 3. z r � ,z°ra ( � �„ �'��� �. � "` ,�., a,� .__ �: �.. 7 s t U$ } to 13 } �'t. i a .« � � 3{ A �,z ;�# ��£ a x`i�., u,� �'^. � � x xa„ ��'�' �� { s s a t t�, a� ,4�`h; "� a a ��? r k�,�j� `���� � ; �� tz, i 7 f'� �� J{�k, �, n�' t �� �. �} �' ��� °� ,�':: it m�, r c c l c c s x br dd r,� Sullivan Engineering Group, LLC Civil Engineers&Land Development Consultants Weekly Monitoring Report Week of August 14, 2017 384 Osgood Street, North Andover (DPW Building) DEP File No.: 242-1681 Monitor: John(Jack)D. Sullivan, III P.E. Date of Inspection: August 16, 2017 @ 8:00 a.m. Weather: 74 degrees/clear DEP Sign: Up & Visible from street Order of Conditions recorded: Yes Construction Schedule: On-file Wetland flagging: Present in field Erosion Control: Installed in correct location Emergency Erosion Control: Yes additional haybales available Bond: Town Project(n/a) Field Notes: - Spoke to site contractor; told him to install silt sacs at NEW catchbasin locations at rear of property prior to finish/fine grading. Existing grates are presently higher than surrounding site grade so there is no chance of siltation of the basins. - Contractor to begin finish grading over next week or two at rear of site (by the new salt shed); pavement to follow fine grading - Drainage work(catchbasin installation) to begin out towards Osgood Street in upcoming weeks - Erosion control in good condition; no signs of silt buildup at barrier - Relatively dry weather week Site Photos: Seven (7) PO Box 2004 Woburn, MA 01888 (781) 854-8644 e-mail:jacksu1153@comeast.net � � a nalT al V ab �s ✓s my No w f , `• -` .- �6 um ol f ,. �., , .: ., .a✓ .• , r - ` A LOKI WA r OW � a .. � y rW 511, 0*1 Aa Ski". � 23 yy y w - N=.. VF �` wR r, a a x >� �� ��; �� � ; ��' Y� �- S �,8, �` Pfti. _ Y r M,i � � �r'�l �-�? ,�. < i. �',�j e y t ��, .. ;�Y � ,,. . ,A €., _v. ;a "� a a y ,;,. ���; Y� � �� r „., �;; � ,�- ,k x e i �M�-'`1 it �; /. � ���� a�> i �, ^'r �,�ai "� r � � �� t ,: �, u r, s 1 .. r Y t r, ft 6 ? �k 5 v tftt ,. fit`i i„ I R° � t t �'� S Y } 1 f S� �{� � � Sx� , � , ��s� F ��1� S{is Yea7::.,�t ' t"R.sa" t" r`a1,\�;,£_,3, ��n,Y,1t;�:t 3:r :.`J',,•x t?{t ),"�:''�4'}l'l3l �"shx All, 01 x" . a } s:. .t•:, a£.: fi r{ a s' S Y 7, s .,,. ,r::<�` Sx ,x,,, ;%; If''�t .u� ,! •, a' .s x,, .�`„_ ..: ;. $ � A !s=t .ry s�`:, t'M4 ' tYt`% {~j' INV tk '�xtr,yf, � l tl,{•#_` r? s> rat ti����rff$$<v s 2`,,'mit�k Z= �yet, s �.=�;r�3�e 1 s rF#. ,} i }�.t.;t. ,`,i��"�u �": r ,". � tx,Y :'sY��. k � #. #r i 2 `; .�`S �.. `Y ,P;,r'�t "� o,;# .t.. ,•' Y'� t i, :,, r,; "'� �{ Yt::ut:� ;a �`4` m. a{ x � �t: I { �" a i n �#i ititl tYl\t`4) RUMP x ;, l fir 3t t o t i� s{lVol AT '. i 1 Sn st rA Ya ; i Aw fax td- in t k r: a! a; t a�iXar; �tttt t '{t, (t i r ,x, �sa . .tis, ,;r, " : �t 4 i ,, r� R i .. � � ,a. { rn ;� �7 L r l� a, r`t�' t e Y :.:;y ;y •: „< ,'. Y' „, s "t lit 4 it§ � �} �pl l '��#t.�. -) #� fit `t '# t{ ,ry ilr �., $ It �,rtzV: fit.•ttk� v ",;• t ewn a :rJt .. P t I =<it3�11�.�". �t.a� ";t` "l, }iNJ' `�''' d i � t�` N 9 $sat }rot: 1 Via!rr '14sar fii i 3 a 6 X4 rr tit}i#�4_ MAW a� ,� �i'�d `gym�•�e n a$s � ; ��,�{a v{E :# �"1 � �i t4; d �srp .' { a I a t ,c # } 't,�, ARE i� r) x.ry, s.��,,gg r'1�"' }s<," �. � nott��•> 1 s i�a .`: r r is ,'�, = -u ;•,4,y s `,k t a { a" to a ( x3 i{Yk5 e .x s.: yc s. ., .. „xi s� "fits`R, NIL e';12t i$,. r� �rt,:rw' �r � II� � � =:,tin§ A��3"`+ �4f t, t ` ,u�?'Y Y�i tak< :fi};,�•� �t k �;a,.+� v" ?t Nzr, . s 't; k, r°;" ^r r)' r IV- ,' ,�¢ =C T}J' 3 xxn+ ,.c. .,t�.>• Y':, � S i] ,t;tr. � s� S t yy ,r <ari ss. t� tY t ,i� k~< �•# :{ � r=` .fr� s '•!'t A, n*t t ,.1, c ,==,a �'�i�, 't i r sitV1,7 1, ,. '. �,�wt5' t�Yu,�.. a�... �Y�v�., �_�_ ,3tbN ,_ n,, a,_. , t Y:"..,:, ,.�- �,>�, . . f .a..� „ ". s�` >atif t. n �T A .s r 7 ,r ._- �.: „.�< a .rd ry u, - TOY W w P;; ` a - = zso of ._ Al"IM MA r, K Y yA of a I_ . 01, Of Min T .-.: ow ti i 1; 5 " rv; r tiz h ?� -„ MAO ..' oz sp 7 .,, WaVwon my Q rWRY W ' o A 77. ; r A c l 4. n t t.a , tr N � ems^-✓ c .0 �i µ w r N r u 'F -c €r r ,A Sullivan Engineering Group, LLC Civil Engineers,&Land Development Consultants Weekly Monitoring Report Week of August 7, 2017 384 Osgood Street, North Andover (DPW Building) DEP File No.: 242-1681 Monitor: John(Jack)D. Sullivan, III P.E. Date of Inspection: August 11, 2017 @ 5:00 pm Weather: 70 degrees/clear DEP Sign: Up &Visible from street Order of Conditions recorded: Yes Construction Schedule: On-file Wetland flagging: Present in field Erosion Control: Installed in correct location Emergency Erosion Control: Yes additional haybales available Bond: Town Project(n/a) Field Notes: - Steel frame/roof in place on salt shed - Erosion control in good condition; no signs of silt buildup at barrier - Relatively dry weather week - Finished grading not completed around drainage infrastructure at rear of site. Site Photos: Six (6) PO Box 2004 Woburn, MA 01888 (781) 854-8644 e-mail:jacksu1153@comcast.net jl� _ F aft r r r���¢, �-� ��� ,��; e �.� 1+''+ ri"� � i ie �:� �,; ��� r� S�"b�; I I Y �)f, 4�i, S ~�i� �f i ,�� 11 9y � y 4�� � �' w r � . �� -� >r � : � . ��>:w. �, .�=w-,: - � N1 ✓ � r „a'� r „� � �� v 1 7 t 3, SSUM tAt 1 mIrl r1 Sti LEA §r ti �', Y �ite 1 b it tr tit r t l t P 1 1 I 1 q cat tI 1, 1' �. t - i ; � i I, �� y ��£}F�4 1�tS F�F� t �e� ��{� � �,�^` <� ���� ���� � �� 4 3 A �. " w Y T.� �3 i a 1 r, s }tt) tk f n t tt 1 ih t� t r- fi 'tt 4 t z tty ' y k tt ' ait�c t `✓& tit �L� `� ti TIRE; it} 1 1 t \t E t t a u, t � „�t,>' :'t �'4`,?�'��rz t{t�i��,l`, �r �7 k� z jF��� t� r t~• tt{ aid �;� { ,t< � � �"# kr j }t �i z y 54 t s t � � t t t 7 t t���.Btd t, i.• ,, t a � .,a. 9.p1 _ t '2; � ���_ �t y� .t �' �� 1,1 .a� `t.;�l t 4vtz t t, r a��gg a Sullivan Engineering Group, LLC Civil Engineers&Land Development Consultants Weekly Monitoring Report Week of July 31, 2017 384 Osgood Street, North Andover (DPW Building) DEP File No.: 242-1681 Monitor: John(Jack) D. Sullivan, III P.E. Date of Inspection: August 5, 2017 @ 10:00 am Weather: 70 degrees/overcast DEP Sign: Up & Visible from street Order of Conditions recorded: Yes Construction Schedule: On-file Wetland flagging: Present in field Erosion Control: Installed in correct location Emergency Erosion Control: Yes additional haybales available Bond: Town Project(n/a) Field Notes: - Steel framing being installed on salt shed building - Very dry week; rain/thunderstorms forecasted for today - No site work taking place at front of site; front of site in good shape (clean) - Finished grading not completed around recently installed drainage structures - Erosion control barriers in good condition. Site Photos: Six (6) PO Box 2004 Woburn, MA 01888 (781) 854-8644 e-mail:jacksu1153@comcast.net tj4 U tsr 4 t kk 4 l } q„ i ti4�� t 4M1f i £, 31 i41. 4 4 yt AK��i y:. t, k t t 4 44' �13 ti r � s r3� tit i j kil t 11ktQ A N s t sY�k�4 1 k t ��! II � i ,�. ,�� Sullivan Engineering Group, LLC Civil Engineers & Land Development Consultants Weekly Monitoring Report Week of July 24, 2017 384 Osgood Street, North Andover (DPW Building) DEP File No.: 242-1681 Monitor: John (Jack) D. Sullivan, III P.E. Date of Inspection: July 28, 2017 @ 10:00 am Weather: 70 degrees/clear DEP Sign: Up & Visible from street Order of Conditions recorded: Yes Construction Schedule: Wetland flagging: Erosion Control: Emergency Erosion Control: Bond: Field Notes: On -file Present in field Installed in correct location Yes additional haybales available Town Project (n/a) - Gravel spread and rough graded for access driveway in area on new salt shed - Drainage work completed in the rear of the facility; some backfilling required - No site work taking place at front of the site; only work on the building exterior/interior - Erosion control barriers in good condition. Site Photos: Seven (7) PO Box 2004 Woburn, MA 01888 (781) 854-8644 e-mail: j'acksu1153@comcast.net Sullivan Engineering Group, LLC 0vrl Engineers & Land Development Consultants Weekly Monitoring Report Week of July 17, 2017 384 Osgood Street, North Andover (DPW Building) DEP File No.: 242-1681 Monitor: John (Jack) D. Sullivan, III P.E. Date of Inspection: July 23, 2017 @ 11:00 am Weather: 85 degrees/clear DEP Sign: Order of Conditions recorded: Construction Schedule: Wetland flagging:. Erosion Control: Emergency Erosion Control: I: • • Field Notes: Up & Visible from street Yes On -file Present in field Installed in correct location Yes additional haybales available Town Project (n/a) - Very dry weather week - Replacement mulch sock installed near stormceptor installation (see Photo #2) - The soil stockpile at the rear of the site has been removed - One soil stockpile at front of site has been removed; one remaining small stockpile - Erosion control barriers in good condition. - Drainage infrastructure installed at rear of site, contractor to provide grate protection upon rough grade Site Photos: Five (5) PO Box 2004 Woburn, MA 01888 (781) 854-8644 e-mail: jacksu1153C&comcast.net � w�. :�z /\r 3�� :� «�2�:\. ~q��<»^ ©� : - `� � � \ y � � z � «2� \�� w&» - . ®��<� -: �x .�.<�� , . . �� � .. ,� . �: ,>: � > ..��/ ���� ��y�/ . �,. . . . . . .� , .. .::,,. ... � � �� � d �� � � _v© « oAff, -n -0 X O (D OD C-) co w cs� b r� PO 01 co co Qo cs, w c 0, 0 D v. � cn o CD m D O CG - 0 = D (a o < CD 0 CD o :3 Q 3 rt L CD � > co m (n w v (on o O C- c a N O v w :a D C- m m c m n c c0 CUD cn O m O < (D m c0 O < V O D CD M C �O On = (C �cnm Ox O N < , Om(0 o CD m 0o cD w co �. r r 0 CD -0 O Zr D (D C2 �. O c CS (D m (Q cn r' (D (D (n 0- C: v m 6 m L Q 3 m D c r* Cn m � = m cn_0 m m c-> (D cn (D — CD m CD CD QC CL (D O �(D X_ CD (n (D O (D 3 O CD O m n (n (D (n CD (D 0- cn (D C 0 O cy (D m C) CD 0- v � o m m < -6 3 tD (D w: (n cn m _ CD :30 = co C < (D cr A —=c� �0E;� 0. C: r«G)CD G :3 zrD c X m C Cn �� cc N zr m T c ncn 0 i CL CD"-' c ®. < : cn O CD m3 0 m-wcn n 3^: (Q `D Q O ((DD ' < 0 < V 00 v:�� .p C3CD O �m � N mop O vv O Q O U) V � I CD m e (_ cD n CD W CD cc @ N o CD n m O (D 3 CD m � Cm O O V ;o (D S 6 O (D r�F C) O m (n O Q m CD 3 CD A x O n. O S �t1 m L 3 = O n :3" s= C O < N N CD O CD 3 J v -4 O Cb V (� (b D w O 0 0 :3 -n C- N) ti 7.7 Cl) cn 0 3 cz 3 p cc 0 m 3 w o c 0-n i �mm T zvo D lw 0 @ 3 x o o v v a� CDc� tD ?7 W I 4D @ :3- :zv �. D v O v -n ° v .,,j_ o cno 0 CD p O= MM 71@ D D w =oQ'Q c� � CO Du o aiOd p v rt O O @ @ v O P, CJt p < v 1 C4 m v fCp : � O v W @ 4�1 C) @ v n @ < _ U5 O i O < o D zs (Do v (D 3 w :3 i W � < M CQ a n v o < c � v (D _ cz. o 6 � a o 3 v C:Y CL { (D b O 3 v w oO v QCD cn v :3 w o A ) v CD v aC O n � ' C O v � � c < O O < @ v 3 v v o 6 < O CD v 3 v ca O _v v n C v 23 _n v n X, N C. ^^W \mil 0 O 3 0 v N V L @ v m n C' cQ' 0 v CL O @ 3 v co o v ;uC a• -P, (D n N n 0)O o :7 W v . 3 a D X CD 0" CD n n a) a. v 3 n O a s v 3 Q) O v O S. O G CD N M O v \ / / / \ / CD/ "m \ / / E / Ilia* Now m :3 \ 0 \ « \ / \ 6 ® \ 6 / / \ \ �_ \ _� \ CD / CD ƒ o / ; k s 8 \ « \ m a T / m � \ p C m_ � � \ 2 5' 3 E \ \_ / o / / O \ 7 / � \ Sullivan Engineering Group, LLC Civil Engineers & Land Development Consultants Weekly Monitoring Report Week of July 10, 2017 384 Osgood Street, North Andover (DPW Building) DEP File No.: 242-1681 Monitor: John (Jack) D. Sullivan, III P.E. Date of Inspection: July 12, 2017 @ 6:30 pm Weather: 70 degrees/light rain DEP Sign: Up & Visible from street Order of Conditions recorded: Yes Construction Schedule: Wetland flagging: Erosion Control: Emergency Erosion Control: Field Notes: On -file Present in field Installed in correct location Yes additional haybales available Town Project (n/a) - Large stormceptor unit at rear of property has been installed. - The soil piles at the front of the site are still onsite. - The larger soil stockpile to the rear of the property is still onsite - Inspection took place over 0.2" rain event; no signs of erosion - Erosion control barriers in good condition. - Water service and hydrant installed off of Wayne Street need front addition Site Photos: Seven (7) PO Box 2004 Woburn, MA 01888 (781) 854-8644 e-mail: jacksu1153@comcast.net Emmons 1 I o Sullivan Engineering Group, LLC Civil Engineers & Land Development Consultants Weekly Monitoring Report Week of July 3, 2017 384 Osgood Street, North Andover 1 Building) DEP File No.: 242-1681 Monitor: John (Jack) D. Sullivan, III P.E. Date of Inspection: July 7, 2017 @ 10:30 am Weather: 70 degrees/light rain DEP Sign: Up & Visible from street Order of Conditions recorded: Construction Schedule: Wetland flagging_ Erosion Control: Emergency Erosion Control: Field Notes: Yes On -file Present in field Installed in correct location Yes additional haybales available Town Project (n/a) - Large stormceptor unit is almost finished being installed (see photo of installed manhole) - The soil piles at the front of the site are slated to be removed within the next two weeks. They are still covered with plastic (mostly) with no signs of soil migration. - The larger pile to the rear of the property does not have a time table for removal as of this report. - No signs of site erosion during a relatively dry week. - Erosion control barriers in good condition. - In area of stormceptor installation at rear of site there is a need for new silt sock to be installed. Contractor has ordered some and will install on Monday. The silt fence is still intact and some crushed stone placed in area where silt sock will be installed as an additional measure of interim protection. Site Photos: Nine (9) PO Box 2004 Woburn, MA 01888 (781) 854-8644 e-mail: jacksu1153@comcast.net Sullivan Engineering Group, LLC Civil Eng lneeis & Land Development Consultants Weekly'I 1 g Report Week of 384 Osgood e•t, North Andover (DPW Building) DEP File No.: 242-1681 Monitor: John (Jack) D. Sullivan, III P.E. Date of Inspection: June 28, 2017 @ 9:00 am Weather: 65 degrees/clear DEP Sign: Order of Conditions recorded: Construction Schedule: Wetland flagging: Erosion Control: Emergency Erosion Control: :. • Field Notes: Up & Visible from street Yes On -file Present in field Installed in correct location Yes additional haybales available Town Project (n/a) - Large stormceptor unit to be installed this week. Area at rear of site partially excavated for installation (see photo) - The soil piles at the front of the site are slated to be removed within the next two weeks. - The larger pile to the rear of the property does not have a time table for removal as of this report. - No signs of site erosion after some heavy flash rain events late yesterday afternoon - Erosion control barriers in good condition. Site Photos: Six (6) PO Box 2004 Woburn, MA 01888 (781) 854-8644 e-mail: jacksu1153@comcast.net m Sullivan Engineering Group, LLC Civil Engineers & Land Development Consultants ITeekly Monitoring Report Week of June 19, 384 Osgood Street,1 Andover (DPW Buildin] DEP File No.: 242-1681 Monitor: John (Jack) D. Sullivan, III P.E. Date of Inspection: June 20, 2017 @ 7:00 pm Weather: 70 degrees/clear DEP Sign: Up & Visible from street Order of Conditions recorded: Construction Schedule: Wetland flagging: Erosion Control: Emergency Erosion Control: :� Field Notes: Yes On -file Present in field Installed in correct location Yes additional haybales available Town Project (n/a) - Drainage infrastructure installation starting at rear of site (see photo of double grated catchbasin). - The soil stockpiled (spoils) next to the double grated catchbasin will be removed or used to backflll immediately. - No signs of site erosion - Erosion control barriers in good condition. - Two soil piles in front of site (with tarp covering) has been tested and has contamination; still onsite; Town working to have piles removed - Large soil pile in rear of site has been tested and consultant is trying to determine the most cost effective way to remove this pile from the property. Site Photos: Six (6) PO Box 2004 Woburn, MA 01888 (781) 854-8644 e-mail: jacksu1153@comcast.net Sullivan Engineering Group, LLC Civil Engineers S Land Development Consultants Weekly1 iReport Week of June 12,2017 84 Osgood Street1 11 Building) DEP File No.: 242-1681 Monitor: John (Jack) D. Sullivan, III P.E. Date of Inspection: June 15, 2017 @ 2:00 pm Weather: 70 degrees/clear DEP Sign: Order of Conditions recorded: Construction Schedule: Wetland flagging: Erosion Control: Emergency Erosion Control: :• . Field Notes: Up & Visible from street Yes On -file Present in field Installed in correct location Yes additional haybales available Town Project (n/a) - This week was relatively a dry weather week. - No signs of site erosion - Erosion control barriers in good condition. - Concrete foundation walls in place at old salt shed location - Two soil piles in front of site (with tarp covering) has been tested and has contamination; still onsite; Town still working to have piles removed - Large soil pile in rear of site has been tested and has contamination. Town is working on obtaining pricing to remove. - Precast drainage structures have been delivered to site for rear drainage work Site Photos: Six (6) PO Box 2004 Woburn, MA 01888 (781) 854-8644 e-mail: jacksu1153@comcast.net Ad Sullivan Engineering Group, LLC Civil Engineers & Land Development Consultants Weekly Monitoring Report Week of June 5, 2017 384 Osgood Street, NorthAndover Building) DEP File No.: 242-1681 Monitor: John (Jack) D. Sullivan, III P.E. Date of Inspection: June 6, 2017 @ 5:00 pm Weather: 50 degrees/heavy rain DEP Sign: Up & Visible from street Order of Conditions recorded: Construction Schedule: Wetland flagging: Erosion Control: Emergency Erosion Control: :• • Field Notes: Yes On -file Present in field Installed in correct location Yes additional haybales available Town Project (n/a) Site inspection took place following 0.74" rain event on 6/5 and during a forecasted rain of 0.56" on Tuesday (6/6) - No signs of site erosion - Erosion control barriers in good condition. - Site is well drained in front; some ponding of water in rear area by old salt shed (see site photo) - Foundation walls under construction at old salt shed location - Soil pile in front of site (with tarp covering) has been tested and may have contamination; still onsite (see site photo) - Large soil pile in rear of site is being tested and may have some contamination; additional testing to be completed Site Photos: Seven (7) PO Box 2004 Woburn, MA 01888 (781) 854-8644 e-mail: jacksu1153@omcast.net tea. k ^. s Sullivan Engineering Group, LLC Civil Engineers & Land Development Consultants Weeklyp Week of May 29th, 2017 384 Osgood Street, North Andover (DPW Building) DEP File No.: 242-1681 Monitor: John (Jack) D. Sullivan, III P.E. Date of Inspection: June 2, 2017 @ 9:00 am Weather: 60 degrees/clear DEP Sign: Order of Conditions recorded: Construction Schedule: Wetland flagging: Erosion Control: Emergency Erosion Control: GM I Field Notes: Up & Visible from street Yes On -file Present in field Installed in correct location Yes additional haybales available Town Project (n/a) - Drainage infrastructure completed installed at front of site; additional drainage work to be completed in the rear - No signs of site erosion - Erosion control barriers in good condition. - Site is well drained - Foundation walls being formed and some sections poured in area of old salt shed - Soil pile in front of site (with tarp covering) has been tested and may have contamination - Large soil pile in rear of site is being tested and may have some contamination; additional testing to be completed Site Photos: Seven (7) PO Box 2004 Woburn, MA 01888 (781) 854-8644 e-mail: jacksu1153@comeast.net Sullivan Engineering Group, LLC Civil Engineers & Land Development Consultants Weekly Monitoring Report Week of 1` 384 Osgood Street, North Andover (DPW Buildin] DEP File No.: 242-1681 Monitor: John (Jack) D. Sullivan, III P.E. Date of Inspection: May 23, 2017@ 5:00 pm Weather: 50 degrees/overcast DEP Sign: Order of Conditions recorded: Construction Schedule: Wetland flagging: Erosion Control: Emergency Erosion Control: Field Notes: Up & Visible from street Yes On -file Present in field Installed in correct location Yes additional haybales available Town Project (n/a) - Site inspection took place after a 0.27" rain event on monday (5/22) - No signs of site erosion - Erosion control barriers in good condition. - Site is well drained - Footing being formed and poured in area of old salt/sand shed - Front of site in area of DPW addition site was in good shape; clean Site Photos: Six (6) PO Box 2004 Woburn, MA 01888 (781) 854-8644 e-mail: jacksu1153@comcast.net WMI'llml � / m .� \. � � � � ».� a� °� \ / � � \�� ^ \ � � � � � / \ \� ,� � � a x ��;�. ,� y � � . \� .\ \ / � .� � ar�a . _ y y: \�� " > w .w . � . :\\��,\ »��.2�»� � � � �°<,� , a,g < ..� � w �w .�«.� »° \� � � � � . v� « ��� �\- a Sullivan Engineering Group, LLC Civil Engineers & Land Development Consultants Weekly Monitoring Report Week of May 15thq 217 384 Osgood Street, North Andover Building) DEP File No.: 242-1681 Monitor: John (Jack) D. Sullivan, III P.E. Date of Inspection: May 15, 2017@ 9:00 am Weather: 50 degrees/light rain Up & Visible from street DEP Sign: Order of Conditions recorded: Yes Construction Schedule: On -file Present in field Wet_ l_ and flagging: Installed in correct location Erosion Control: in Control: Yes additional haybales available Emer enc Eroso Town Project (n/a) Bond: Field Notes: Site inspection took place after a 0.97" rain event throughout #2 shows an ex. �avat on area at existing - Drainage infrastructure installation still underway art of the excavation) structure location for connection. Dirt spoils are not stockpiled, but p drainage - No signs of site erosion Erosion control barriers in good condition. ' s which had been stockpiled out front of the DPW bstallation work n removed. Soils pile this week. Site was cleaned up in the front to be ready for the drainage and oaring - Footings were not formed at the rear of the site yet, but are planned for forming P Site Photos: Six (6) 854-8644 e-mail: jacksull53@comcast.net PO Box 2004 Woburn, MA 01888 ( 781 ) w � OWMI-na""', � . 9 � ` � � f ����� - .� � �� � � � : : :. . . - yam, � � \: : .�� .. \� \ :,> .�«� 9 �,��</���.w K I Sullivan Engineering Group, LLC Civil Engineers & Land Development Consultants Weekly )4onitoring Report Week of May i .. AndoverBuilding) ��; � �111 1 DEP File No.: 242-1681 Monitor: John (Jack) D. Sullivan, III P.E. Date of Inspection: May 11, 2017@ 11:00 am Weather: 55 degrees/clear Up & Visible from street DES Order of Conditions recorded: Yes Construction Schedule: On -file Present in field Wetland flagging: Installed in correct location Erosion Control: Emer Yenc i Erosion Control: Yes additional haybales available Town Project (n/a) Bond: Field Notes: tructure being installed in the front of the site. It did not appear with the excavation for Drainage mfras ture that dewatering would be necessary. the first drainage struc stockpiles in the front of the site will be moved to the rear of the site over the next few days The soilP per the site supervisor of the old sand/salt shed the future footing (which isetrreenchhedt week the footing will be d filled with crushed one In the area rain over the week has been covered with plastic for upcoming formed and poured The DPW addition will be installing the roof shortly No signs of site erosion Erosion control barriers in good condition. Site Photos: Four (4) PO 88 (781) 854-8644 e-mail: jacksu1153@comcast.net Box 2004 Woburn, MA 018 � � � � � � � d ?\ Z\ . � � � � : � � � � \?;� . �»���� � :�:�<. .. » »� � a� � � � ?� ? w ,.,� a� .� � � � . .. . »<.� � � � � � �� � � . - . w w . :.� � a� � > � «ate «. «: . . : .� � ,. .: � � y: :. �.:\� � � \�� y�� �� � � M-' . a ffi: :vn y © x y... . . : Sullivan Engineering Group, LLC Civil Engineers & Land Development Consultants Weekly1 1 r Report Week of May Ist, 2017 384 Osgood Street, North Andover (DPW Buildin DEP File No.: 242-1681 Monitor: John (Jack) D. Sullivan, III P.E. Date of Inspection: May 2, 2017@ 3:30 pm Weather: 45 degrees/light rain DEP Sign: Up & Visible from street Order of Conditions recorded: Yes Construction Schedule: On -file Wetland flagging: Present in field Erosion Control: Emergency Erosion Control: Field Notes: Installed in correct location Yes additional haybales available Town Project (n/a) - 8" Water Main being installed - Footing which has been excavated in former location of salt/sand storage shed is being evaluated by geotechnical engineer for stability - 700-800 yds of materials in excavation in the rear of the property has been removed from the site - Site has been cleaned up substantially from last weeks inspection - Drainage manholes to be delivered this week - Concrete pile which had been stockpiled by flagpole has been removed - Remaining soil piles in front will be removed or used as backfill for drainage work - No signs of site erosion; siltation control in good shape Site Photos: Five (5) PO Box 2004 Woburn, MA 01888 (781) 854-8644 e-mail: jacksu1153@comcast.net �" �� ��'�'k�~ ,, , � s n �� � ��. Sullivan Engineering Group, LLC Civil Egineers & Land Development Consultants WeeklyoReport Week of April 24th, 2017 384 Osgood Street, North Andover (DPW Buildin] DEP File No.: 242-1681 Monitor: John (Jack) D. Sullivan, III P.E. Date of Inspection: April 25, 2017@ 4:30 pm Weather: 45 degrees/heavy rain DEP Sign: Order of Conditions recorded: Construction Schedule: Wetland flagging: Erosion Control: Emergency Erosion Control: CM Field Notes: Up & Visible from street Yes On -file Present in field Installed in correct location Yes additional haybales available Town Project (n/a) - Soil stockpiles still onsite and covered; I did not see superintendent onsite to discuss removal date - Excavation for new foundation in area of old salt/sand shed underway; crushed stone installed along a portion of where future footing will be formed/poured - Steel roof installed on DPW addition - No signs of site erosion - Inspection took place during anticipated rainfall of 1 1/2". Site handling rain well with no signs of erosion or silt migration. Site Photos: Seven (7) PO Box 2004 Woburn, MA 01888 (781) 854-8644 e-mail: jacksu1153@comcast.net r _- �� �� �. Sullivan Engineering Group, LLC Civil Engineers & Land Development Consultants Weekly Monitoring Report Week of April 84 Osgood ..t, North • 1 1 Buildin] DEP File No.: 242-1681 Monitor: John (Jack) D. Sullivan, III P.E. Date of Inspection: April 18, 2017@ 2:30 pm Weather: 50 degrees/clear DEP Sign: Order of Conditions recorded: Construction Schedule: Wetland flagging: Erosion Control: Emergency Erosion Control: = Field Notes: Up & Visible from street Yes On -file Present in field Installed in correct location Yes additional haybales available Town Project (n/a) - Soil stockpiles still onsite and covered; In speaking with superintendent the stockpiles may be removed this Friday (4/21); once contaminated piles are removed any additional piles will be relocated. - Erosion control had been repaired from previous report - The salt/sand storage shed at the rear of the DPW building has been demolished - Steel roof installed on DPW addition - No signs of site erosion Site Photos: Four (4) PO Box 2004 Woburn, MA 01888 (781) 854-8644 e-mail: jacksu1153@comcast.net �\ y � � � � � � � � \- �� � � � � � � : . � � _�� �� � � - 2� ������. . . ,>. �:�© ..2\\»�\�� 22.���} Sullivan Engineering Group, LLC Civil Engineers & Land Development Consultants Weekly Week of April 10th, 2017 84 Osgood DEP File No.: 242-1681 Monitor: John (Jack) D. Sullivan, III P.E. Date of Inspection: April 11, 2017@ 5:30 pm Weather: 80 degrees/clear DEP Sign: Up & Visible from street Order of Conditions recorded: Yes Construction Schedule: On -file Wetland flagging: Present in field Erosion Control: Installed in correct location Emergency Erosion Control: Yes —additional haybales available Bond: Town Project (n/a) Field Notes: Soil stockpiles still onsite and covered; Soils were scheduled to be removed on 4/14, but additional testing required prior to transport/delivery. Therefore 4/14 date has been voided. - Some areas of the erosion control need repair. The areas were pointed out and will be corrected this week. No immediate risk. - A crushed stone and haybale check dam was installed (see Photo 3) at the site entrance off of Osgood Street. This check dam system is upgradient of existing erosion control - The concrete floor for the new building has been poured and finished - Drainage catchbasin structures have been delivered to the site Site Photos: Four (4) PO Box 2004 Woburn, MA 01888 (781) 854-8644 e-mail: jacksu1153@comcast.net Sullivan Engineering Group, LLC Civil Engineers & Land Development Consultants 'IT eekly Monitoring Report Week of April 84 Osgood Street, North Andover 1Buildin) DEP File No.: 242-1681 Monitor: John (Jack) D. Sullivan, III P.E. Date of Inspection: April 4, 2017@ 4:30 pm Weather: 38 degrees/raining DEP Sign: Up & Visible from street Order of Conditions recorded: Construction Schedule: Wetland flagging: Erosion Control: Emergency Erosion Control: Field Notes: Yes On -file Present in field Installed in correct location Yes —additional haybales available Town Project (n/a) - Inspection took place during 1/2 inch rain event - Soil stockpiles still onsite and covered - Wood pallets have been removed (previously stockpiled near erosion control) - There was a bobcat and a crushed stone stockpile parked near erosion control; no workers onsite at time of inspection; I will talk with superintendent to either use crushed stone immediately or relocate. - Erosion control is in good condition; - Site was somewhat muddy but no silt/mud transport - Appeared majority of utility work under the future building slab has been completed. Site Photos: Four (4) PO Box 2004 Woburn, MA 01888 (781) 854-8644 e-mail: jacksu1153@comcast.net MIL IN f - w x v Sullivan Engineering Group, LLC Civil Engineers & Land Development Consultants WeeklyoReport Week of March 27, 2017 384 Osgood Street, North Andover (DPW Buildin DEP File No.: 242-1681 Monitor: John (Jack) D. Sullivan, III P.E. Date of Inspection: March 28, 2017@ 5:30 pm Weather: 38 degrees/raining DEP Sign: Up & Visible from street Order of Conditions recorded: Yes Construction Schedule: On -file Wetland flagging: Present in field Erosion Control: Emergency Erosion Control: :• • Field Notes: Installed in correct location Yes additional haybales available Town Project (n/a) 0.6" rain event on Monday (1/27); 0.4" rain event today (Tuesday) - Soil stockpiles still onsite; based on conversation with Asst. Town Manager the earliest the piles can be removed is the first week in April; Town is attempting to get multiple quotes due to high cost. - Wood pallets are stacked (15 +/- pallets high) by erosion control still onsite and are to be disposed of. - Erosion control is in good condition; - Site is draining well with no signs of soil migration; Site Photos: Five (5) PO Box 2004 Woburn, MA 01888 (781) 854-8644 e-mail: jacksu1153@comcast.net Sullivan Engineering Group, LLC Civil Engineers & Land Development Consultants W •• ._RkMonitoring Report Week of March 20, 2017 384 Osgood Street, North Andover (DPW Building) DEP File No.: 242-1681 Monitor: John (Jack) D. Sullivan, III P.E. Date of Inspection: March 24, 2017@ 11:30 am Weather: 38 degrees/overcast DEP Sign: Order of Conditions recorded: Construction Schedule: Wetland flagging: Erosion Control: Emergency Erosion Control: :• • Field Notes: Up & Visible from street Yes On -file Present in field Installed in correct location Yes additional haybales available Town Project (n/a) - Soil stockpiles still onsite; based on conversation with Asst. Town Manager the earliest the piles can be removed is the first week in April; Town is attempting to get multiple quotes due to high cost. - Wood pallets are stacked (15 +/- pallets high) by erosion control still onsite and are to be disposed of. - Installation of water pipe (DICL) being installed (see Photo #4) - Erosion control is in good condition; - No signs of any silt or soil carryover to Wayne Road from construction entrance. Site Photos: Four (4) PO Box 2004 Woburn, MA 01888 (781) 854-8644 e-mail: jacksu1153@comcast.net ��� �� �. -�w -�� x-<,. , w �, r v: Sullivan Engineering Group, LLC Civii Engineers & Land Development Consultants Weekly Monitoring Report Week of March 13,2017 384 Osgood Street, North Andover (DPW Buildin DEP File No.: 242-1681 Monitor: John (Jack) D. Sullivan, III P.E. Date of Inspection: March 13, 2017@ 9:30 pm Weather: 28 degrees/clear DEP Sign: Up & Visible from street Order of Conditions recorded: Yes Construction Schedule: On -file Wetland flagging_ Present in field Erosion Control: Installed in correct location Emergency Erosion Control: Yes additional haybales available Bond: Town Project (n/a) Field Notes: - Soil stockpiles still onsite and were re -blanketed; contractor placed some clean crushed stone on the top of the tarps to hold them in -place ed on Tuesday (3/14) - Site inspection took place before l8high) by er m expecton of still onsit and are to be disposed of. - Wood pallets are stacked ( pallet - Erosion control is in good condition; - No signs of any silt or soil carryover to Wayne Road from construction entrance. Site Photos: Four (4) PO Box 2004 Woburn, MA 01888 (781) 854-8644 e-mail: jacksu1153@comcast.net >» ^� `~ �� S« . .....� 9� � m � x � « 6 \ a Sullivan Engineering Group, LLC Civil Engineers & Land Development Consultants Weekly Monitoring Report Week of March F i Osgood Street,1 Andover 1 (DPW Buildin] DEP File No.: 242-1681 Monitor: John (Jack) D. Sullivan, III P.E. Date of Inspection: March 7, 2017@ 2:30 pm Weather: 37 degrees/light rain DEP Sign: Order of Conditions recorded: Construction Schedule: Wetland flagging Erosion Control: Emergency Erosion Control: :• • Field Notes: Up & Visible from street Yes On -file Present in field Installed in correct location Yes additional haybales available Town Project (n/a) - Soil stockpiles still onsite; I spoke to site supervisor to re -blanket the piles since some soil is showing; the piles will be re -blanketed by thursday - Steel arrived on Monday and is being erected - Excavation equipment has been removed from the buffer zone - Wood pallets are stacked (15 +/- pallets high) by erosion control and will be disposed of this week - Erosion control is in good condition; - Contractor has done a good job this week cleaning up site for the steel delivery Site Photos: Four (4) PO Box 2004 Woburn, MA 01888 (781) 854-8644 e-mail: jacksu1153@comcast.net r y�ii ,.._u� Sullivan Engineering Group, LLC Civil Engineers & Land Development Consultants Weekly1 p g Report Week of Feb. 384 Osgood Street, North Andover (DPW Building) DEP File No.: 242-1681 Monitor: John (Jack) D. Sullivan, III P.E. Date of Inspection: February 28, 2017@ 3:30 pm Weather: 52 degrees/clear DEP Sign: Up & Visible from street Order of Conditions recorded: Yes Construction Schedule: On -file Wetland flagging Present in field Erosion Control: Emergency Erosion Control: C• . Field Notes: Installed in correct location Yes additional haybales available Town Project (n/a) - Soil stockpiles still onsite; I had contractor "re- blanket" the piles - Steel is due onsite next week - All snow is melted; site is well drained - Spoke with site supervisor about relocating excavation equipment outside the buffer zone - Erosion control is in good condition; Site Photos: Four (4) PO Box 2004 Woburn, MA 01888 (781) 854-8644 e-mail: jacksu1153@comcast.net Sullivan Engineering Group, LLC Civil Engineers & Land Development Consultants Weekly1 1, g Report Week of Feb. 20,2017 384 Osgood Street, North Andover (DPW Building) DEP File No.: 242-1681 Monitor: John (Jack) D. Sullivan, III P.E. Date of Inspection: February 21, 2017@ 3:30 pm Weather: 45 degrees/clear DEP Sign: Up & Visible from street Order of Conditions recorded: Yes Construction Schedule: On -file Wetland flagging: Present in field Erosion Control: Emergency Erosion Control: l- . Field Notes: Installed in correct location Yes additional haybales available Town Project (n/a) - Soil stockpiles still onsite, but covered with tarps - Masonry work for elevator shaft completed - Steel for the building is delayed; not onsite - Snow melt taking place this week; site draining well; no erosion - Erosion control is in good condition; Site Photos: Four (4) PO Box 2004 Woburn, MA 01888 (781) 854-8644 e-mail: jacksu1153@comcast.net �,r m:� w- M -�� I. .AM Sullivan Engineering Group, LLC Civil Engineers & Land Development Consultants Weekly1 1, r Report Week of •b . 13,2017 4 Osgood ••t, North Andover1 in DEP File No.: 242-1681 Monitor: John (Jack) D. Sullivan, III P.E. Date of Inspection: February 15, 2017@ 11:00 a.m. Weather: 35 degrees/overcast DEP Sign: Order of Conditions recorded: Construction Schedule: Wetland flagging: Erosion Control: Emergency Erosion Control: Field Notes: Up & Visible from street Yes On -file Present in field Installed in correct location Yes additional haybales available Town Project (n/a) - Soil stockpiles still onsite, but covered with tarps and snow cover - Masonry work for elevator shaft almost completed - Steel for the building is running 2-3 weeks out (delayed) - Some siding work is required on existing building that may start next week - Major snow events took place 2/9 + 2/12 (each storm dropped 8"-12" snow) - Erosion control is in good condition; - No work taking place today; masons to finish elevator shaft work tomorrow Site Photos: Three (3) PO Box 2004 Woburn, MA 01888 (781) 854-8644 e-mail: jacksu1153@comcast.net . : �� � � � \ � /\{\:� j �,� /\ .. y.. - >� � ��� «® . : : �� z, + © .2�» % � . 2 y � � } .� � � : . xw:� �r y� �: z � : � � \1�� � � \ »� \� �� m� � . � « « 4 \,. . � � >� - m� « « © �� d� � . \� \ ��° �� � � � Sullivan Engineering Group, LLC Civil Engineers & Land Development Consultants Weekly Monitoring Report Week of Feb. 6, 2017 384 OsgoodStreet, North Andover (DPW Building) DEP File No.: 242-1681 Monitor: John (Jack) D. Sullivan, III P.E. Date of Inspection: February 9, 2017@ 8:00 a.m. Weather: 30 degrees/light snow DEP Sign: Order of Conditions recorded: Construction Schedule: Wetland flagging. Erosion Control: Emergency Erosion Control: Bond: Field Notes: Up & Visible from street Yes On -file Present in field Installed in correct location Yes additional haybales available Town Project (n/a) - Soil stockpiles still onsite, but covered with tarps - Masonry work for elevator shaft almost completed - Inspection took place just prior to major snow event (14"-18" snowfall forecasted for 2/9) - Erosion control is in good condition; no signs of silt migration or build-up at barrier - No work taking place today; site is closed Site Photos: Five (5) PO Box 2004 Woburn, MA 01888 (781) 854-8644 e-mail: jacksul153(c�comcast.net A Trtr?.� `� _ =1 General Information Project Name: Muffin Realty Trust — 351 Willow Street DEP Fite No.: MA DEP #242-1639 Location: North Andover, MA Date of inspection: February 10, 2017 Start/End Time: 11:30 AM -11:55 AM Inspector's Name(s): Will Schkuta Inspector's Tifle(s): Environmental Inspector Inspector's Contact Information The Morin -Cameron Group, Inc. 66 Elm Street Danvers, MA 01923 978-777-8586 Describe present phase of construction Solid waste disposal room construction Type of Inspection: 0 Regular 0 Pre -storm event 0 During storm event 0 Post -storm event Weather Information Has it rained since the last inspection? 0 Yes 0 No Precipitation Amount Measured at Lawrence Airport between February 3 — February 9 = 0.37 inches Weather at time of this inspection? 19% Clear Do you suspect that discharges may have occurred since the Last inspection? 0 Yes 0 No Are there any discharges at the time of inspection? 0 Yes 0 No Site-specific_BMPs BMP Installed Date for corrective BMP Description and Operating Corrective Action Needed action/responsible Properly? person Silt Fence/Silt Sock, Silt 0 Yes 0 No N/A N/A Sack Overall Site Issues AMP/Activity Implemented? Maintained? Corrective Action Date for corrective action/responsible Needed person Are all slopes and disturbed areas not actively being Z Yes 0 No 0 Yes 0 No N/A N/A worked property stabilized? Are natural resource areas (e.g., streams, wetlands, mature trees, etc.) protected ED Yes 0 No 0 Yes 0 No N/A N/A with barriers or similar BMPs? Are perimeter controls and sediment barriers adequately installed (keyed 0 Yes 0 No Z Yes 0 No N/A N/A into substrate) and maintained? Is there evidence of sediment being tracked into 0 Yes 23 No 0 Yes 0 No N/A NIA the street? Is trash/titter from work areas collected and placed Z Yes 0 No 0 Yes 0 No N/A N/A in covered dumpsters? Are vehicle and equipment fueling, cleaning, and maintenance areas free of 0 Yes 0 No Z Yes 0 No N/A N/A spills, leaks, or any other deleterious material? Certification statement: The undersigned has inspected the site and has informed the site contractor of responsibilities for repairing and maintaining the erosion control system. Print name: WILL Z,1AKtXT,,A Signature: Date: February 10, 2017 Sullivan Engineering Group, LLC Civil Engineers & Land Development Consultants Weekly Monitoring oReport Week of Jan 30th, 2017 384 Osgood Street, North Andover (DPW Buildin] DEP File No.: 242-1681 Monitor: John (Jack) D. Sullivan, III P.E. Date of Inspection: January 30, 2017 @ 3:30 p.m. Weather: 30 degrees/clear DEP Sign: Order of Conditions recorded: Construction Schedule: Wetland flagging: Erosion Control: Emergency Erosion Control: I: me Field Notes: Up & Visible from street Yes On -file Present in field Installed in correct location Yes —additional haybales available Town Project (n/a) - Remaining soil stockpiles onsite have been covered with plastic tarps (see site photo 3+4) - Foundation is fully backfilled - Masonry work starting on building - No dewatering activity taking place - Erosion control is in good condition; no signs of silt migration or build-up at barrier - No signs of mud or silt carryover to Wayne Street; rip -rap construction entrance working well (see Site photo # 1) Site Photos: Four (4) PO Box 2004 Woburn, MA 01888 (781) 854-8644 e-mail: jacksu1153@comcast.net m Sullivan Engineering Group, LLC Civil Engineers & Land Development Consultants Weekly1 g Report Week of I' 84 Osgood Street,NorthAndover 1 Buildin] DEP File No.: 242-1681 Monitor: John (Jack) D. Sullivan, III P.E. Date of Inspection: January 24, 2017 @ 1:00 P.M. Weather: 35 degrees/rain DEP Sign: Order of Conditions recorded: Construction Schedule: Wetland flagging: Erosion Control: Emergency Erosion Control: G• . Field Notes: Up & Visible from street Yes On -file Present in field Installed in correct location Yes —additional haybales available Town Project (n/a) - Inspection took place during heavy rainfall overnight and into today (> 1" rainfall total) - Foundation is fully backfilled; previous soil stockpile areas that were tested and suitable for backfill purposes have been used. The remaining soil stockpile area near the erosion control barrier needs to be disposed of off -site and based on conversation with the site supervisor today that should happen over the next week. - Site held up well to heavy rains - Propane tank delivered to site today - No dewatering activity taking place - Erosion control is in good condition; no signs of silt migration or build-up at barrier - No signs of mud or silt carryover to Wayne Street; rip -rap construction entrance working well Site Photos: Four (4) PO Box 2004 Woburn, MA 01888 (781) 854-8644 e-mail: jacksu1153@comcast.net w . :a v , y� « ?� •� \ .. � +. � � > Sullivan Engineering Group, LLC Clvll Engineers & Land Development Consultants Weekly1 1 g Report Week of Jan 16th, 2017 84 Osgood Street, NorthAndover 1 Buildin!' N DEP File No.: 242-1681 ' N Monitor: John (Jack) D. Sullivan, III P.E. ;_ u Date of Inspection: January 18, 2017 @ 12:00 p.m. e Ll Weather: 35 degrees/rain u DEP Sign. Up & Visible from street Order of Conditions recorded: Construction Schedule: Wetland flagging: Erosion Control: Emergency Erosion Control: I:• I Field Notes: Yes On -file Present in field Installed in correct location Yes additional haybales available Town Project (n/a) - Foundation walls are all poured, forms stripped and portions are backfilled - It appears soil stockpiles onsite are being used to backfill foundation; some additional backfilling is required, but it appears some of the soil will need to be removed from the site; Site supervisor was not onsite during inspection to ask if piles were going to be removed. Last week I was told they would be removed if not needed for backfill. - No dewatering activity taking place - Erosion control is in good condition; no signs of silt migration or build-up at barrier - No signs of mud or silt carryover to Wayne Street; rip -rap construction entrance working well Site Photos: Five (5) PO Box 2004 Woburn, MA 01888 (781) 854-8644 e-mail: jacksu03la comcast.net � \ » r Sullivan Engineering Group, LLC Civil Engineers & Land Development Consultants Weekly Monitoring Report Week of 384 Osgood Street� North Andover (DPW Building) DEP File No.: 242-1681 Monitor: John (Jack) D. Sullivan, III P.E. Date of Inspection: January 12, 2017 @ 1:00 P.M. Weather: 55 degrees/clear DEP Sign: Up & Visible from street Order of Conditions recorded: Yes Construction Schedule: On -file Wetl_ a@fla_ in Present in field Erosion Control: Installed in correct location Emergency Erosion Control: Yes additional haybales available Bond: Town Project (n/a) Field Notes: - Foundation footings are all poured; portion of frost walls have been poured and forms removed - Remaining foundation walls are formed o Sae supervset to isor poured onsite and on was told the y or soil can be used for Soil stockpiles are still m place; spoke backfill of the foundation and that by the middle of foundation will be backfill or exclessa hfrom this material. He is aware that these stockpiles need to be removed as the site - No dewatering activity taking place Erosion control is in good condition - No signs of site erosion (including soil stocicpiles)a encouraging lraging due to snow melt this week and some rain (0.14" on Tuesday 1/10 + 0.10 on Wednesday ) well - No signs of mud or silt carryover to Wayne Street; Osgood Stpconstrtion entrance reet from snow melt and �aini on tues/wed - Some pondmOsg g water on driveway apron off of Site Photos: Four (4) PO Box 2004 Woburn, MA 01888 (781) 854-8644 e-mail: jacksu1153@comcast.net ft ��,� gin.; �� �; � ,, �.:' �_ ��,; � �� ���-�.. �.. � �� � . �� � �. �� $; o�_ , . ��� -- '�, ,�� �-� n n'�a ,, 4 ��.� �� �;, �, .� ��,� ��> �. DEP File No. Monitor: Date of Inspection: Weather: DEP Sign: Sullivan Engineering Group, LLC Civil Engineers & Land Development Consultants Weekly Monitoring Report Week 1 d 12017 84 Osgood Street, North• 1 i Building) 242-1681 John (Jack) D. Sullivan, III P.E. January 5, 2017 @ 1:00 p.m. 30 degrees/clear Order of Conditions recorded: Construction Schedule: Wetland flagging_ Erosion Control: Emergency Erosion Control: �4 Field Notes: Up & Visible from street Yes On -file Present in field Installed in correct location Yes additional haybales available Town Project (n/a) - Foundation footings are being poured; frost walls being formed (see photos 2+3) - Contractor utilizing construction blankets over excavated foundation areas for frost protection - Soil stockpiles still onsite and have been tested for contaminants; awaiting report to see if soil can be used to backfill foundation OR if material will need to be treated as contaminated as disposed off -site in accordance with federal requirements. - Spoke with contractor and told portion of foundation walls to be poured on Friday (1/6) and the remainder of walls to be poured next week - No dewatering activity - Erosion control is in good condition - No signs of site erosion (including soil stockpiles) - No signs of mud or silt carryover to Wayne Street; rip -rap construction entrance working well (see photo # 1) Site Photos: Four (4) PO Box 2004 Woburn, MA 01888 (781) 854-8644 e-mail: jacksu1153@comcast.net Sullivan Engineering Group, LLC Civil Engineers & Land Development Consultants WeeklyReport Week of Dec. 384 Osgood Street, North Andover (DPW Buildin] DEP File No.: 242-1681 Monitor: John (Jack) D. Sullivan, III P.E. Date of Inspection: December 28, 2016 @ 1:00 p.m. Weather: 35 degrees/clear DEP Sign: Order of Conditions recorded: Construction Schedule: Wetland flagging: Erosion Control: Emergency Erosion Control: Ise Field Notes: Up & Visible from street Yes On -file Present in field Installed in correct location Yes additional haybales available Town Project (n/a) - Foundation footings are being prepared (crushed stone placed & wood forms being set) - Contractor utilizing construction blankets over excavated foundation areas for frost protection - Temporary soil stockpile areas due to foundation excavation consistent with construction practices - No dewatering activity - Erosion control is in good condition - No signs of site erosion - No signs of mud or silt carryover to Wayne Street; rip -rap construction entrance working well Site Photos: - Four (4) PO Box 2004 Woburn, MA 01888 (781) 854-8644 e-mail: jacksu1153@comeast.net .M1 `". Sullivan Engineering Group, LLC Cavil Engineers & Land Development Consultants Weekly Monitoring Report Week of Dec. 19th 2016 84 Osgood Street,1 • 11 Buildin] DEP File No.: 242-1681 Monitor: John (Jack) D. Sullivan, III P.E. Date of Inspection: December 21, 2016 @ 10:30 a.m. Weather: 29 degrees/clear DEP Sign: Up & Visible from street Order of Conditions recorded: Yes Construction Schedule: Wetland flagging: Erosion Control: Emergency Erosion Control: :e . Field Notes: On -file Present in field Installed in correct location Yes additional haybales available Town Project (n/a) - Foundation excavation work underway - Ground is frozen; blankets placed in areas for excavation - No dewatering activity - Erosion control is in good condition - No signs of site erosion Site Photos: - Four (4) PO Box 2004 Woburn, MA 01888 (781) 854-8644 e-mail: jacksu1153@comcast.net Sullivan Engineering Group, LLC Civil Engineers & Land Development Consultants 17ee._R,?TlonitoringReport Week of Dec.th 6 384 Osgood Street, North Andover (DPW Building) DEP File No.: 242-1681 Monitor: John (Jack) D. Sullivan, III P.E. Date of Inspection: December 15, 2016 @ 2:30 p.m. Weather: 24 degrees/clear/windy DEP Signn: Up & Visible from street Order of Conditions recorded: Yes Construction Schedule: Wetland flagging: Erosion Control: Emergency Erosion Control: Field Notes: On -file Present in field Installed in correct location Yes additional haybales available Town Project (n/a) - Temporary rip -rap construction entrance installed off of Wayne Street - Pile rig onsite; pile installation underway - Construction trailer is onsite - Porta Potti's onsite - Foundation work to begin next week - Erosion control is in good condition - No signs of site erosion Site Photos: - Six (6) PO Box 2004 Woburn, MA 01888 (781) 854-8644 e-mail: jacksu1153@comcast.net d , � � . . � \ \� � � �� � � � \. .. ��\ ���» � ,. �� w�.���a �. r >»a : � < « .� : »� � a � � : : � � : :xs ©�� « \.� � \ �� « ? «\2 � � : . � � ,«r �� /�« � 2 xm�2 \ ƒ� <� $� :ate � »+} . � . . : � � � ©m . v � > � . « � : : . >� y�� 3 ©«��, « ��� � y Sullivan Engineering Group, LLC Civil Engineers & Land Development Consultants Weeklyo. or Report 384 Osgood Street, North Andover (DPW Buildin] DEP File No.: 242-1681 Monitor: John (Jack) D. Sullivan, III P.E. Date of Inspection: December 9, 2016 @ 10:30 a.m. Weather: 34 degrees/clear DEP Sign: Order of Conditions recorded: Construction Schedule: Wetland flagging: Erosion Control: Emergency Erosion Control: :M Field Notes: Up & Visible from street Yes On -file Present in field Installed in correct location Yes additional haybales available Town Project (n/a) - First inspection of site - DEP File number is posted on construction fence and visible from Osgood Street (photo attached) - Erosion control is in -place and in good condition - Portion of pavement area in front of building has been removed - Surveyor marring pile locations; rig to come in next week to start pile installation for foundation Site Photos: - Five (5) PO Box 2004 Woburn, MA 01888 (781) 854-8644 e-mail: jacksu1153@comcast.net