HomeMy WebLinkAbout- Permits #NACC #284 - 19 COMMONWEALTH AVENUE 9/8/2021
CONSERVATION DEPARTMENT
Community & Economic Development Division
Maximo Guerrero
1404 Basswood Circle
North Andover, MA 01845 September 9, 2021
19 Commonwealth Avenue, North Andover
New Deck Construction
Conservation Conditions of Approval, NACC #284
Pursuant to section 4.4.2 (A) of the North Andover Wetlands Protection Regulations,
Maximo Guerrero, on behalf of the homeowner Betzabet Ascencio, filed for a small project for
work proposed at 19 Commonwealth Avenue, North Andover. The work involves installation of a
new approximately 170 square foot deck with stairs. The deck will be supported by a combination of
five (5) 12" wide x 4" deep footings & attached to the corner of the house by lag bolts. Proposed
work is located within the 200-foot Riverfront Area to the Shawsheen River, approximately 126- feet
from the bordering vegetated wetland to the Shawsheen River.
During the September 8, 2021 public meeting, the North Andover Conservation Commission
(NACC) found this project to qualify as a Small Project Permit and voted unanimously to approve
this projeA
The project is approved only as it relates to the Conservation Commission and any and all other
approvals should be obtained by the applicant/homeowner.
** The applicant, homeowner and their contractors are advised that NO other work on the property
is allowed under this permit. The NACC has jurisdiction over all of the wetlands and associated
100-Foot buffer zones and 200 Riverfront Area to the Shawsheen River on site and any work
that involves ground disturbance or changing the current conditions in these areas will require
permitting with the NACC. This includes, but are not limited to, house additions, pools, patios,
decks, sheds, fences, garden beds, landscaping and bridge installation, tree or
vegetation cutting/pruning. These activities shall be held to the current standards under the Bylaw
and WPA. but not limited to
All work shall conform to the following plans and conditions:
RECORD DOCUMENTS: Small Project Filing Including:
Application Checklist,
Plan Set Entitled Proposed Deck 19 Commonwealth Avenue,
drawn by Gilberto Jimenez & Mayky Sanchez, GJ Design
Group, LLC, dated July 12, 2021
19 Commonwealth Avenue Small Project Permit Approval Category A New Deck Construction
Page 1 of 2
Plot Plan (Proposed New Deck) prepared by Design Group,
LLC
GIS Aerial Map with measurement to wetland
The following conditions are hereby mandated:
CONDITIONS:
1. Prior to work commencing, a pre-construction meeting with the Conservation Department
shall be scheduled.
2. All excavated soils shall be taken off site.
3. A site visit with Conservation Department shall be scheduled once the project is complete to
verify compliance.
4. This permit shall expire one year from the date of issuance.
Should you have any question or comments regarding the contents of this letter, please do not
hesitate to contact the undersigned at 978.688.9530. Thank you for your anticipated cooperation
with this matter.
Respectfully,
NORTH ANDOVER CONSERVATION DEPARTMENT
Amy R. Maxner
Conservation Administrator
19 Commonwealth Avenue Small Project Permit Approval Category A New Deck Construction
Page 2 of 2