OPERATION AND MAINTENANCE PROGRAM
for
EXISTING STORMVW'ATER MANAGEMENT SYSTEM
Located at
1600 OSGOOD STREET
NORTH ANDOVER, MASSACHUSETTS
Applicant:
Osgood Solar, LLC
1600 Osgood Street
North Andover, Massachusetts 01845
Prepared by:
Meridian Associates, Inc.
500 Cummings Center, Suite 5950
Beverly, Massachusetts 01915
(978) 299-0447
June 27, 2016
Project Name: Osgood Solar, LLC Solar Development
Owner Name: Ozzy Properties, Inc.
1500 Osgood Street
North Andover, Massachusetts Q 1845
Party Responsible for {Maintenance: Ozzy Properties, Inc.
Long-Term Inspection and Maintenance Measures
Erosion Control
Eroded sediments can adversely affect the performance of the stormwater
management system. Eroding or barren areas should be immediately re--vegetated.
Inspection and Maintenance of Catch Basins
The catch basins shall be inspected once per year and at the end of the foliage and
snow removal seasons, and if necessary, any maintenance shall be performed so
that it functions as designed. The basins shall be cleaned once per year, or when
sediment in the bottom of the sump reaches 1/ the depth from the bottom of the
invert of the lowest pipe in the basin. Inlet and outlet
outlet pipes should be checked for
clogging.
Debris and Litter Removal
Trash may collect in the BMP's, potentially causing clogging of the facilities. All
debris and litter shall be removed when necessary, and after each storm event.
Sediment and debris collected from vacuuming and/or sweeping should be disposed
of at a permitted waste disposal facility. Avoid disposing of this material on site,
where it could be washed into the proposed subsurface infiltration systems.
Parking Lot Sweeping
Upgradient portions of the northern solar array shall be swept annually in the early
Spring (Exhibit A). Sweeping shall be conducted with a high efficiency vacuum or
regenerative air sweeper rather than a mechanical broom sweeper.
V I!q!gxa
. 4
to �� ■ �� AA��\�A�\���� ��V ` A\� A V v � � vA
f�
STORMWATER MANAGEMENT
AFTER CONSTRUCTION
INSPECTION SCHEDULE AND EVALUATION CHECKLIST
PROJECT LOCATION: 1600 Osgood St, North Andover MA WEATHER:
Inspection Required Inspection Fallow-up
Date Inspector .Area Inspected Frequency if,BMP Comments Recommendation Inspection Required
(yes/no)
Catch basins 14nnually and-4fter
Major Storm Events
(1) Refer to the Massachusetts Stormwater Handbook, Volume Two: Stormwater Technical Handbook (February 2008) for
recommendations regarding frequency for inspection and maintenance of specific BMP's.
(2) Inspections to be conducted by a qualified professional such as an environmental scientist or civil engineer.
Limited or no use of sodium chloride salts, fertilizers or pesticides recommended.
Other notes: (Include deviations from: Con. Comm. Order of Conditions, PB Approval, Construction Sequence and Approved Plan)
Stormwater Control Manager:
..........................