HomeMy WebLinkAbout2016-07-05 Monitoring Reports Civil Engineering Land Surveying Environmental Consulting 1-andscape Architecture
HANCOCK
20107
November 30, 2016
Mr. Dan Leary NOV
Osgood Solar, LLC
857 Turnpike Street, Suite 233
North Andover, MA 01845
RE: Osgood Solar Project
1600 Osgood Street,Assessors Map 34, Parcel 1.7
North.Andover, MA 01845
Construction Inspection Summary for September/October/November 2016
North Andover Planning Department
Dear Mr. Leary:
Hancock Associates (HA) have completed construction inspection services for the
Osgood Solar.Project for the period beginning at end of September through and including
the month of November 2016. Hancock performed these services as an independent
construction monitor hired by Osgood Solar, LLC for the benefit of the "Town of North
Andover- in conformance with the requirements of the Planning Board Decision dated
July 5, 2016..
Scope of Inspection
Hancock Associates performed the following:
-1. observed completed installation of erosion controls;
-2. compared installed items with approved plans and specifications (no deviations to
report this period);
-3. prepared field reports for each inspection noting progress, extent of work, and any
evidence of siltation/erosion;
-4. discussed schedule with construction representative;
-5. prepared this summary letter of inspections for this period and provided copy of same
to the North Andover Planning Department.
Inspections were performed by a Massachusetts Professional Civil Engineer.
DANVERS OFFICE MARLBOROUGH OFFICE
185 Centre Street,Danvers,MA 01923 315 Elm Street, Marlborough,MA 01752
Phone: (978)777-30501{ax:(978)774-7816 Phone:(508)460-1111 Fax: (508)460-1121
www.hancockassociates.cotn
HANCOCK
ASSOCIAIT'S
Plan Reference
"Osgood Solar, LLC, Solar Development 1600 Osgood Street(Route 125) (Assessors
Map 34 Lot 17)Application for Plan Approval,North Andover, Massachusetts (19
Sheets)"prepared by Meridian Associates, dated May 6, 2016 and last revised on June
16, 2016.
Town of North Andover Planning Board Notice of Decision—Site PlanReview—dated
July 5, 2016.
"Plot Plan of Land Located in North Andover, Massachusetts, Osgood Landing, 1600
Osgood Street(Route 125)"prepared by Meridian Associates and dated October 5, 2016.
"Sketch Plan"prepared by Meridian Associates with no date showing relocation of
proposed fence on west side of building,
Summary
All work conformed to the approved plans and specifications, and in particular:
-1. erosion controls were installed approximately as shown on the approved plans;
-2, solar arrays, permanent/temporary fencing was installed approximately as shown on
the approved plans;
-3. no work was begun on the New England Tractor Trailer locus as shown on the
approved plans.
-4. contractor reported on.2016-11-28 that work will continue for at least two weeks.
All inspection reports and accompanying photos are attached for your use and records.
If you have any questions or comments, please contact me at 508-460-1111 or email me
at rchrusciel L0iancockassociatcs.corn,
Very truly yours,
HANCOCK ASSOCIATES
Z,-
Robert A. Chrusciel, P.E.
Senior Project Manager
RAC/rac
cc: Jean Enright, North Andover Planning Dept.; J. Peznola, E. Cullen, Hancock Assoc.
Encl.: Hancock Assoc. Inspection Reports for September/October/November 2016
Page 2 of 2
HAL r C O C K Construction Inspection Re ort# 1
ASSOCIATES
Date 9-28-2016
Mon Tues Weds Thurs Fri Sat I Sun
x
Project: Osgood Solar LLC Weather sun cloudy overcast Rain snow
x
Project#20107 Temperature To 32 32-50 50-70 70-85 ssover
x
Client: Osgood Solar LLC Wind still Moderate High Report No.
x
Contractor: Osgood Solar LLC Humidity cry Moderate Humid
x
Project Manager: Robert Chrusciel
Average Field Force
Name of Contractor Non-manual Manual Remarks
Dan Leary 1 15
Visitors
Time Name Representing Remarks
10:30-11:15 Edward Cullen Osgood Solar See below
Equipment on site:
Crane,fork lift, street sweeper
Construction Activities:
Installation of ground solar panels in solar field on North side of building and installation of solar field on roof. Erosion control
and temporary fencing already in place,solar panel installation and some permanent fencing has recently begun. No evidence
of siltation or erosion of surfaces,
By: Edward Cullen, PE MA Civil 51819 Title: Project Engineer
Reviewed by: Robert A.Chrusciel PE MA Civil 28779 Title: Project Manager
1 of 2
Construction.Ins ecdoli Report# 1
ASSOCIATES
CB within solar field Straw wattle at perimeter of solar field
I
V
j
Straw wattle at entrance to solar field Straw wattle at perimeter of solar field
I rd( r,Y
2of2
HANCOCK Construction Inspection Report#2
ASSOCIATES
Date 10-28-2016
Mon Tues Weds Thurs Fri Sat Sun
x
Project: Osgood Solar LLC Weather sun Cloudy overcast Rain snow
x
Project#20107 Temperature To 32 32-50 50-70 70-85 85-over
x
Client: Osgood Solar LLC Wind still Moderate High Report No.
x 2
Contractor: Osgood Solar LLC Humidity Cary Moderate Humid
x
Project Manager: Robert Chrusciel
Average Field Force
Name of Contractor Non-manual Manual Remarks
Dan Leary 0 0 Rainy day
Visitors
Time Name Representing Remarks
10:30-11:15 Edward Cullen Osgood Solar See below
Equipment on site:
fork lift
Construction Activities:
No activity due to rain
Solar field North of building is nearly complete.
Work has begun on second solar field Western of building erosion control and temporary fencing already in place. Some
permanent fencing has been installed.
No evidence of siltation or erosion of surfaces after 2.8 inch storm on October 21.
By: Edward Cullen PE MA Civil 51819 Title: Project Engineer
Reviewed by: Robert A. Chrusciel, PE MA Civil 28779 Title: Project Manager
1 of 2
HANCOCK
Construction Inspection Report#2
ASSOCIATES
Straw wattle along perimeter of parking area
�Grrrl o%�i �
�, ��✓�;fill/!/i/ �W, ;��« %�
Construction activity within solar field
x >. r „rf ari�i19ulr YO ao 19 r��
fP F U
yra rr
r
v r air it h r
IlJP�ri�r�yw ������ Pal'"""""�y��i!•�i(�ifi°1+�r�"G.u" J�///1��� Jlr ' �t !r`;r%%1�r�/k��///1 ';
/�a✓Il"III(YI�� D'Yl�i W' // ,//G G/filmy M,�'"w✓r r mri!/;v r�N"IN,.
2of2
H11 r C O C K Construction Inspection Report#3
ASSOCIATES
Date 11-4-2016
Mon Tues Weds Thurs Fri Sat Sun
x
Project: Osgood Solar LLC Weather Sun Cloudy Overcast Rain Snow
x
Project#20107 Temperature To 32 32-50 50-70 70-85 85over
x
Client: Osgood Solar LLC Wind still Moderate High Repot No.
x 3
Contractor: Osgood Solar LLC Humidity Cry Moderate Humid
x
Project Manager. Robert Chtusciel _.._
Average Field Force
Name of Contractor Non-manual Manual Remarks
Dan Leary 1 8
Visitors
Time Name Representing Remarks
10:30-11:15 Edward Cullen Osgood Solar See below
Equipment on site.-
fork lift
Construction Activities:
Northern field complete with permanent fencing.
Continued installation of solar field West of building.
No signs of siltation or erosion of surfaces.
By: Edward Cullen, PE MA Civil 51819 Title: Project Engineer
Reviewed by: Robert A. Chrusciel, PE MA Civil 28779 Title: Project Manager
1 of 2
HANCOCK
Construction Inspection Report#3
ASSOCIATES
Temporary fencing along perimeter of western solar field Silt sack on CB outside of western solar field
Straw wattle at discharge point for northern field Silt sack and permanent fencing of for northern field
�' " f� �"" mmuluuuuuuuuuumu uu�� ,
2of2
HAr C O C K Construction Inspection Report#4
ASSOCIATES
Date 11-14-2016
Mon Tues Weds I Thurs Fri Sat Sun
x 11
Project: Osgood Solar LLC Weather Sun Cloudy Overcast Rain snow
x
Project#20107 Temperature To 32 32-50 50-70 70-85 a5-over
x
Client: Osgood Solar LLC Wind Still Moderate High Report No.
x 4
Contractor: Osgood Solar LLC Humidity Dry Moderate Humid
x
Project Manager: Robert Chrusciel
Average Field Force
Name of Contractor Non-manual Manual Remarks
Dan Leary 1 8
Visitors
Time Name Representing Remarks
10:30-11:15 Edward Cullen Osgood Solar See below
Equipment on site:
fork lift
Construction Activities:
Installation of solar panels in western solar field nearly complete. Continued installation of permanent fencing around western
solar field.
No evidence of siltation or erosion of surfaces.
By: Edward Cullen, PE MA Civil 51819 Title: Project Engineer
Reviewed by: Robert A.Chrusciel, PE MA Civil 28779 Title: Project Manager
1 of 2
HANCOCK
Construction lns ecti Ile at•t#4
ASSOCIATES
Western solar field and installation of permanent fencing
l/��+�' Y �l��z ✓hye w��� %f�F /lr// � r�
� n�u r � mP ///?l�/� e �/ ✓61 fP
a' � r w"�^ �� u✓ � �i�% a r y
Material stored near Western solar field
n �
..wwwwWM /
y l
V
2of2
HANCOCK Construction Inspection Report#s
ASSOCIATES
Date 11-21-2016
Man Tues I Weds I Thurs I Fri Sat Sun
x
Project: Osgood Solar LLC Weather San Cloudy Overcast Rain snow
x
Project#20107 Temperature To32 3250 50-70 70-85 85-0ver
x
Client: Osgood Solar LLC Wind still Moderate High Report No.
x 5
Contractor: Osgood Solar LLC Humidity Dry Moderate Hued
x
Project Manager: Robert Chrusciel
Average Field Force
Name of Contractor Non-manual Manual Remarks
Dan Leary 1 8
Visitors
Time Name Representing Remarks
10:45-11:30 Edward Cullen Osgood Solar See below
i
Equipment on site:
fork lift
i
Construction Activities:
I
i
i
Continued installation of roof solar panels and installation of permanent fence around westem solar field almost complete.
i
Trench drain referenced in Planning Board decision was repaired and cleaned(see photo).
i
No evidence of siltation or erosion of surfaces.
By: Edward Cullen, PE MA Civil 51819 __ Title: Protect Engineer
Reviewed by: Robert A.Chrusciel, PE MA Civil 28779 Title: Project Manager
r
[i
€. 1 of 2
HANCOCK
Construction Ins ection.Report#5
ASSOCIATES
Trench drain after repair and cleaning adjacent to northern solar field
KY
rr i
r
/
`;�j/;j�%%')'�° ' '� "y•a'a day ����i� r
/r
y Az
i
/
Installation of permanent fencing for western solar field
www;w'wMrvy f w
p 4
I
2of2
HACOCK Construction Ins ectio»t Report#6
ASSOCIATES
Date 11-28-2015
Mon Tues Weds Thurs Fri Sat Sun
x
Project: Osgood Solar LLC Weather Sun Cloudy Overcast Bain Snow
x
Project#20107 Temperature To 32 32-60 soap 70-85 ss-over
x
Client: Osgood Solar LLC Wind Still Moderate High Report No.
X 6
Contractor: Osgood Solar LLC Humidity Dry Moderate Humid
x
Project Manager: Robert Chrusciel
Average Field Force
Name of Contractor Non-manual Manual Remarks
Dan Leary 1 8
Visitors
Time Name Representing Remarks
i 12:45-1:30 Edward Cullen Osgood Solar See below
4
E
kqt Equipment on site:
k
Crane
Construction Activities:
Continued installation of roof solar panels and installation of wiring in west field.
Permanent fence for western field almost complete.
No evidence of siltation or erosion of surfaces.
By: Edward Cullen, PE MA Civil 51819 Title: Project Engineer
Reviewed by: Robert A.Chrusciel PE MA Civil 28779 Title: Project Manager
i of 2
Construction Inspection Report#6
ASSOCIATES
Trash storage in west solar field and installation of roof panels
Installation of permanent fencing for west solar field
M iJ yOf.G
2of2