HomeMy WebLinkAbout2016-04-05 Construction Phasing 1661 & 1665 GPR TKZ LLC
4 High Street, Suite 201
North Andover, MA 01845
978-852-4002
tzeke@comcast.net
May 10, 2016
Jean Enright,Acting Town Planner
North Andover Planning Department, and
Jennifer Hughes, Conservation Administrator
North Andover Conservation Department
1600 Osgood Street
North Andover, MA 01845
Re: 1661 & 1665 Great Pond Road Construction Schedule
Hi Jean and Jennifer,
Pursuant to the decisions of record regarding these adjacent lots, below is the proposed
construction schedule.
May 2016: install erosion controls, prepare stone cleaning access pad beside 1665 driveway;
excavate 1661 foundation
June 2016: construct 1661 foundation, backfill/grade/stabilize
July 2016: demolish 1665 residence, re-establish retaining walls and regrade for new residence;
begin framing 1661; install utilities and driveway 1661, stabilize disturbed areas
August 2016: construct 1665 foundation, backfill/grade/stabilize, begin 1665 framing
September 2016: stabilize all disturbed site areas
October 2016: complete construction 1661
November 2016: complete construction 1665; cleanup.
Let me know of any questions or concerns.