HomeMy WebLinkAbout1991-06-04 Correspondence 1 KAREN H.P.NELSON Town of 120 Main Street, 01845
Director
(508) 682-6483
NORTH ANDOVER
BUILDING ".. . 11
CONSERVATION g AC 4U DIVISION OF
HEALTH
PLANNING PLANNING & COMMUNITY DEVELOPMENT
May 13, 1993
Mr. Donald George, P.E.
Executive Director
Greater Lawrence sanitary District
240 Charles Street
North Andover Ma 01845
Dear Mr. George:
The North Andover Division of Planning and community
Development is ready to move forward at this time to discuss the
gift of land from the Sanitary District to the Town of North
Andover as part of our Boat Ramp Project. We would appreciate your
placing this matter on the next available agenda.
Thank you very much for your consideration.
Sincerely,
"e-14 co
Richard P. Doucette,
Conservation Administrator
Town of North Andover
CC James Gordon, Town Manager
Karen Nelson, Division Director
William Dolan, Fire Chief
Kimball Chase Inc.
Kii..L.
y
Januaryk 31, 1991
Mr. Steven C. Davis 261 Essex Street
Massachusetts Environmental Protection Agency LawrenceMassachusetts.
Executive Office of Environmental Affairs 018Q
EOEA/ MEPA Unit
100 Cambridge Street, lath Floor
Boston, Massachusetts 0=02
RE; North Andover Boat Lanmh
KCCI Project No.94-3631.01
Dear Mr. Davis:
I correspond as the duly authorized agent for the Town of North Andover, Massachusetts
with respect to the boat launch project currently under design for the Conservation Office.
The project has undergone revisions to the original 1988 design and application with a..
significant reduction in the impact to the sites' resource areas. I have enclosed a copy of
the revised plans for your review.
In addition, we have received our Order of Conditions from the Conservation Commission
of which a copy is enclosed. Application to other State and Federal regulatory agencies
having jurisdiction over this project are also currently under way.
Based on the plans submitted by Kimball Chase Company to your office in 1988 for the
boat launch, your office made a determination at that time that the project did not meet
the MEPA review thresholds and no ENF was required. (See Attached)
The purpose of this letter is to request that your office review the attached plans and
information and mare a determination as to the jurisdiction of the MEPA requirements for
the proposed redesign.
Should you require further information, please call me at your convenience. Thank you for
your time and cooperation.
Sincerely yours,
7MS.
C MPANY, INC.
ro s,
Division Manager
cc: Richard Doucette,
Conservation Administrator
Portsmouth, NH • Concord, NH Bath, ME Salem, NH Lawrence, MA
T
�
(�xecrcli'r e elc$ a ( nuc- Jdla d
900 am�xirc'pe yo iw,ee
MICHAEL S. ouKAKIS February 25 , 1988 '•
GOVERNOR �
JAMES S. HOYTE '
SECRETARY
Ms . Rebecca J. Clough, oje .. Nana er
Kimball Chase
53 Stiles Road, Suite 202
Salem, NH 03079
Re: Merrimack River Boat Launch North Andover MA
Dear Ms . Clough:
Thank you for your request of. February 1, 1988 , for- an
opinion as to the status of the above referenced project under
the provisions of the Massachusetts Environmental Policy Act and
its regulations . Based. on the information therein, it is the
opinion of the Secretary, pursuant to 301 CMR 11.03 (3) , that the
project as described does not meet the MEPA. r_eview thresholds at
301. CMR 11.25 , 26 , and 27 . Therefore , no Environmental
Notification Form need be filed and Commonwealth agencies are
free to act.
It is possible that a future requirement for a Superseding
Order of Conditions under the Wetland Protection Act Regulations
could lead to modification of this ruling. Should that become
the case, please notify me at the above address .
Sincerely,
Steven C. Davis
Assistant Secretary
Environmental Impact Review
SCD/sd
Y
r M6? Y
WILLIAM F.WELD February 12 , 1991
GOVERNOR
ARGEO PAUL CELLUCC► (617)727-9800
LIEUTENANT GOVERNOR
SUSAN F.TIERNEY
SECRETARY
Mark S. Gross
Kimball Chase
261 Essex Street
Lawrence, MA 01840.
Re: Request for Opinion; North Andover Boat Launch
Dear Mr-. Gross:
You have requested the opinion of the Secretary regarding
the applicability of the Massachusetts Environmental Policy Act
and its regulations to the proposed North Andover Boat Launch.
You have indicated that the project is somewhat changed from
the project originally reviewed by the Director Steven Davis in
1988. 1 have reviewed the plans you enclosed and the Order of
Conditions of the Conservation Commission.
Based on the information you have provided, it is the
opinion of the Secretary that no MEPA thresholds are exceeded by
this project. No Environmental Notification Form need be filed,
and Commonwealth agencies are free to act.
Sincerely,
Janet G. McCabe
Assistant Secretary
Environmental Impact Review
cc: John Simpson.
JGM/jgm
100% RECYCLED PAPER
DEPARTMENT OF ENVIRONMENTAL PROTECTION
DIVISION OF WETLANDS AND WATERWAYS REGULATION
WATERWAYS REGULATION PROGRAM
WATERWAYS LICENSE APPLICATION
DREDGING ADDENDUM
WATERWAYS FILE N0.
DESCRIPTION OF DREDGING PROJECT The construction of the boat ramp
will involve dredging of material below the MLW elevation to accommodate
— --- -- .-structural fi1.1 for-the concrete walls LNmnp and precast- plank:
PURPOSE OF DREDGING For placement of structural fill material for
su2port of the boat ramp components .
VOLUME OF MATERIAL TO BE DREDGED 61 C.Y.
METHOD OF DREDGING Clamshell
DISPOSAL METHOD AND SPBCIFIC LOCATION
Dre 'e material to be disposed of on-site.
(PLEASE INCLUDE SEPARATE DISPOSAL SITE LOCATION MAP.)
NAME OF APPLICANT Town of Ngrth e .
SIGNATURE OF APPLICANT
DATE
PLEASE TYPE OR CLEARLY PRINT ALL INFORMATION
Eff 10/4/90 -1g-
DEPARTMENT OF ENVIRONMENTAL PROTECTION
DIVISION OF WETLANDS AND WATERWAYS REGULATIONQ
WATERWAYS REGULATION PROGRAM
MUNICIPAL ZONING CERTIFICATION
APPLICATION FORM .3
WATERWAYS FILE NO.
NAME OF APPLICANT Town
PROJECT STREET ADDRESS
CITY/TOWN Nggth Andnvnr,• Massachusetts
WATERWAY
DESCRIPTION OF PROPOSED USE OR CHANGE IN USE construction of a
boat launching facility into the Merrimack River
(to be completed by Municipal Clerk or Appropriate Municipal ,Of'icial)
I HEREBY CERTIFY THAT THE PROJECT DESCRIBED ABOVE AND MORE FULLY
DETAILEa IN THE APPLICANT' S WATERWAYS LICENSE APPLICATION AND PLANS IS
NOT IN VIOLATION OF LOCAL ZONING ORDINANCES AND BYLAWS.
SIGNATURE OF MUNICIPAL OFFICIAL t
TITLE Conservation Administrator & Town PlanerC.�
CM/TOWN OF NORTH ANDOVER, MASSACHUSETTS
DATE January 21, 1991
PLEASE TYPE OR CLEARLY PRINT ALL INFOR*SATIOT�'
Etz 10/4/90 -19-
1
DEPARTMENT OF ENVIRONMENTAL PROTECTION
DIVISION OF WETLANDS AND WATERWAYS REGULATION
WATERWAYS REGULATION PROGRAM
MUNICIPAL PLANNING BOARD NOTIFICATION
APPLICATION FORM 4
WATERWAYS FILE NO.
NAME OF APPLICANT TOWN OF NORTH ANDOVER
PROJECT STREET ADDRESS Riverview Street
CITY/TOWN North Andover, Massachusetts
WATERWAY Merrimack River
(to be completed by Municipal Clark or Appropriate Municipal
Official)
I HEREBY CERTIFY THAT A COPY OF THE COMPLETED WATERWAYS LICENSE
APPLICATION AND PLANS DESCRIBED ABOVE WAS SUBMITTED BY THE
APPLICANT TO THE MUNICIPAL PLANNING BOARD ON _ Jan. 29, 1991
6
D TE
SIGNATURE OF MUNICIPAL OFFICIAL
-- --- TITLE Town Planner
CITY/TOWN OF North Andover
DATE January 29 1991
PLEASE TYPE OR CLEARLY PRINT ALL INFORMATION
NOTICE TO APPLICANT:
THIS FORM MUST BE SUBMITTED ALONG WITH THE ORIGINAL APPLICATION
MATERIALS, IF THE FORM CANNOT BE EXECUTED BY THE APPROPRIATE
MUNICIPAL OFFICIAL AT THE TIME OF DELIVERY, THE APPLICANT SHOULD
WAIT UNTIL HE RECEIVES THE EXECUTED FORM BEFORE SUBMITTING THE
COMPLETED APPLICATION PACKAGE TO DEP.
Eff 14/4/90 -20-
Kimball
February 14, 1991 Chase
Massachusetts Department of Environmental Protection 261 Essex Street
Lawrence
Waterways Regulation Program Massachusetts
One Winter Street, 8th Floor 01840
Boston, Massachusetts 02108
RE: North Andover Boat Launch
KCCI Project No. 90-3631.01
Dear Reviewer:
On behalf of the Conservation Office for the Town of North Andover, Kimball Chase as
duly authorized agent, is submitting the attached completed application and supporting
documents for the Chapter 91 Waterways License pursuant to 310 CMR 9.00. An
application was previously submitted in April of 1988, but as a result of design changes, did
not proceed forward. The attached application and plans reflect those proposed design
changes and the completed application and supporting documentation consist of the
following documents:
• Basic application Form 1, with supporting documentation.
• Application Forms 2, 3 & 4.
• Set of plans in accordance with Section 6 "Mylar Plan Specifications" of the
Chapter 91 requirements.
• Copy of the Order of Conditions issued for this project.
• Copy of letter and supporting documentation to MEPA requesting
jurisdictional applicability for the project.
The enclosed application and materials have been prepared and submitted in accordance
with the requirements of the Chapter 91 License Application procedures and is completed
as submitted. If you should have any questions or require further information as a result
of your review of the attached materials, please contact me at (508)687-7701 at your
convenience.
Sincerely ours,
KI L CIHA MPANY, INC.
Irk S. Gross, P.E.
ivision Manager
cc: Mr Richard Doucette, Conservation Administrator
Portsmouth, NH • Concord, NH • Bath, ME # Salem, NH • Lawrence, MA