HomeMy WebLinkAbout2017-6-6 Monitoring Report 2 10/16/2017 Town of North Andover Mail-Fwd:Weekly Inspection Report-Wheelabrator Ash House Project-October 12 NORTHANDOVER Massachusetts Bonnie V1/olstromer<bwolstromer@northandoverma.gov> Fwd: Weekly Inspection Report - Wheelabrator Ash House Project - October 12 1 message Jean Enright <jen rig ht@northandoverma.gov> Fri, Oct 13, 2017 at 1:57 PM To: Bonnie Wolstromer<bwolstromer@northandoverma.gov> Bonnie, Please print and put in the Wheelabrator project file. Thank you Jean ---------- Forwarded message---------- From: Tim Jones <tjones@techenv.corn> Date: Fri, Oct 13, 2017 at 12:11 PM Subject: Weekly Inspection Report-Wheelabrator Ash House Project-October 12 To: Jean Enright<jonright@ north andoverma,gov>, Brian LaGrasse <blagrasse@northandoverma,gov> Good Afternoon Jean and Brian, Please see the attached weekly inspection report and photo log. No issues to note. Project is going according to expectations/schedule. The existing concrete foundation rebuild and footing installation is complete for the main ash house (Phase 1). Site is undergoing finish housekeeping in preparation for the heavy crane install and new concrete panel delivery. These activities are beginning today and they will be installing panels starting next week. Big progress should be obvious in next week's report! Please let me know if you have any questions. Have a great weekend, Tim Tim Jones, PMP https://mail.google.com/mail/ca/u/O/?ui=2&ik=a2debacbl a&jsver=BNKYfl ymS-O.en.&view=pt&search=inbox&th=15fl 6e2c4c34d7b8&siml=15fl6e2c4c34d7b8 113 10116/2017 Town m North Andover Ma -rwu:vvaoNyInspection Report mme*lauotor Ash House Project Octouer12 Associate TECH ENVIRONMENTAL Focused Knowledge. Real Solutions 383 Wyman Street, Suite 2Q5 Waltham, MAO2451 (0) 781,890.2220X32 (C) 8D2279.941@ Fax: 781.880,945i donem@TeohEnv.00m www.TeohEnv.00m _ Sincerely, Jean Enright Planning Director Town uf North Andover 110 Main Street North Andover, MA 01845 Phone 97&68&9533 hupa:Vmai|e000|e.00m/mai|/ca/u/0/vui=2aix=a2uo»anuluuVuvo=BwxYf1vma-u.on.uv|*w=pt&searco=inuoxum=15n6o2c4c34u7u8usim|~15f16o2r*u34u7u8 2B FOCUSED KNOWLEDGE. REAL SOLUTIONS. SITE INSPECTION MEMORANDUM To: Town of North Andover—Planning&Health Departments From: Tim Jones Date: October 13, 2017 Subject: Weekly Site Inspection Report—Wheelabrator Ash House Reconstruction Ref 1949:1 Tech Environmental, Inc. (Tech) is providing this weekly site inspection report for the Wheelabrator North Andover Ash House Replacement project. The observations below and attached photos represent the activities observed during the inspection on October 12.. 2017. General Project Progress Developments: Met with Wheelabrator team to conduct weekly inspection of Ash House project. This week's inspection was self-guided and included check-ins with Tom Penna, Project Manager and contractor R.H. White following the inspection. Work in progress noted during the inspection (**Phase 1 main ash house demolition complete): 1) regular truck loadout of ash was ongoing during the inspection; 2) staging and preparation for new concrete panel installation; 3) finish housekeeping from concrete wall refurb work. 1. Construction Phase—Phase I: Concrete wall rebuild and structural footing preparation for new building is completed, forms are stripped and structure being staged for concrete panel install. Heavy crane install scheduled to start 10113, concrete panels arrive 10/16. 2. Construction Schedule — Project is on accelerated schedule. Existing foundation wall has been refurbished and new building construction to commence week of 10/16. 3. Nuisance Conditions —No nuisance conditions noted, ash loadout containment functioning as designed and no material track-out from ash house facility. No fugitive emissions. Site housekeeping in excellent condition. Conditions were sunny and dry. 4. Areas of Non-Compliance — No areas of non-compliance noted, ash house air scrubber in operation and no fugitive emissions were observed from ash transfer. 5. Corrective Actions — None required, housekeeping in excellent condition and support materials are staged in good order. 6. Dust Mitil4ation —Ash conveyance and truck loadout was in operation, scrubber in service. New partition seal intact,Ash loadout area confined. 7. Material Stockpiling —Staged materials currently on site within defined construction zone: 1) dumpster for construction debris; 2) concrete/steel building erection staging equipment and supports. 8. Erosion Control—No erodible material piles on site or exposed earth, new gravel crane pad has been installed and compacted, housekeeping in excellent condition. 9. Scrubber In/Out of Service—Ash loadout in progress and scrubber operational. 10. Next Major Activity — New ash house construction planned to begin week of October 16, crane installation and building panel delivery/staging in progress. Address: 303 Wyman Street,Suite 2951 Waltham,MA 02451 1 Phone:781-890-2220 1 Fax:781-890-9451 1 Website:www.techenv.com Wheelabrator North Andover—Site Inspection Photos 10/12/2017 77 No y h t r 1 � I f c, rts...e _r.. ,- �,,.s,.u„ ;...�._.«.,W.:,,. .�.v-�,,....�.,w ra,,,.r,....� ,a...,..�.:.,s.x..,. .�..v_a............._...a..,....,.... :,.....,..,..,......,.. ..,.,�...�...,.... w,.,e...,..,�,�..w .,,.�..,e..�.,..,.._.,,.�.�..,..,.,m.a,,�... .�r.....,.....A,�.,_____�__m� Site Inspection Photos (cont.) r t r rt r 1 T i U u�. r r fir: Site Inspection Photos (cont.) lY NO v F 3 ��. r...-� p, r rG...,,-�^. "; _,.^:�"cam ✓ .:r r . r r x G r w � y `��� _ ,_ �,--� :,� �`.�""r :,,�� �..:✓� fir.� �-s- µ Site Inspection Photos (cont.) T r d s x. x k { i e r �s w: TeCH FOCUSED KNOWLEDGE. REAL SOLUTIONS. SITE INSPECTION MEMORANDUM To: Town of North Andover—Planning& Health Departments From: Tim Jones Date: September 29, 2017 Subject: Weekly Site Inspection Report—Wheelabrator Ash House Reconstruction Ref 1949 Tech Environmental, Inc. (Tech) is providing this weekly site inspection report for the Wheelabrator North Andover Ash House Replacement project. The observations below and attached photos represent the activities observed during the inspection on September 27, 2017. General Project Progress Developments: Met with Wheelabrator team to conduct weekly inspection of Ash House project. This week's inspection was self-guided and included check-ins with Gary Collette, Plant Manager, Tom Penna, Project Manager and contractor R.H. White following the inspection. Work in progress noted during the inspection (**Phase 1 main ash house demolition complete): 1) regular truck loadout of ash was ongoing during the inspection; 2) existing concrete wall refurbishment work in-progress (forming, scarifying and pouring); 3) footings form work in-progress. 1. Construction Phase—Phase I: Concrete wall rebuild and structural footing preparation for new concrete panel building. Concrete pouring has commenced on walls and wall cap. 2. Construction Schedule — Project is on accelerated schedule. Concrete wall pouring has been initiated and new wall panels will begin to arrive for October installation. 3. Nuisance Conditions —No nuisance conditions noted, ash loadout containment functioning as designed and no material track-out from ash house facility. No fugitive emissions. Site housekeeping in good condition. Conditions were sunny and dry. 4. Areas of Non-Compliance — No areas of non-compliance noted, ash house air scrubber in operation and no fugitive emissions were observed from ash transfer. S. Corrective Actions —None required, housekeeping on NW corner of job site and material stockpile covers have been addressed. 6. Dust Mitigation —Ash conveyance and truck loadout was in operation, scrubber in service. New partition seal intact,Ash loadout area confined. 7. Material Stockpiling — Materials and stockpiles currently on site within defined construction zone: 1) crushed stone at clarifier pad; 2) sand at clarifier pad; 3) sub-slab fill material; 4) dumpster for construction debris and slab cuts; 5) new lumber, staging and concrete forming materials.— UNCHANGED from prior report. 8. Erosion Control — Covered sand and stone stockpiles covered/intact, sock boom in place around catch basin, footing spoils covered, housekeeping in good condition. 9. Scrubber In/Out of Service—Ash loadout in progress and scrubber operational. 10. Next Major Activity — Continuing with existing concrete wall refurbishment/rebuild and footing work, concrete pouring initiated. New ash house construction planned to begin in mid-October. Address: 303 Wyman Street,Suite 295 1 Waltham,MA 02451 1 Phone:781-890-2220 1 Fax:781-890-9451 1 Website:www.techenv.com Wheelabrator North Andover—Site Inspection Photos 09/27/2017 w f x G f r / c,- ? }, 7 t i F x � h g' dP® f .....�.....,».,.,,..,�«,«._.««....a.,�..,at«..«....a,.,.-.y..�.,�,.�..................P..�...,..,.,..e�,...".,,..,_:..»..�..,.:...a.a....�. ......._....,..m..�...«..,....:........a,. ...,.n...��.....,., ..".Wm�."..,.,m.............�..v»..«.� .". ..,....w«....mc..ww-,.........,........ Site Inspection Photos (cunt.) 'a �a a ;A i i „g b y 9 vl� Site Inspection Photos (cont,) ke, �1 1 I i I, I I iu r r I it lii I Ilil V III I III III II � II I 'I 41 I I I it I I y it uY y � i 7 , f Site Inspection Photos (cont.) �r I i � F I� Ali G, �3 r s ✓ ,ate a a } a9�ls. a� �;rW Site Inspection Photos (cunt.) r Yr D arc � s k I F �s r Il��f I j I j I r-e ! �yl I k Y � a 3 3' sc I I fl I� �x FOCUSEO KNOWLEOGE. REAL SOLUTIONS. SITE INSPECTION MEMORANDUM To: Town of North Andover—Planning& Health Departments From: Tim Jones Date: September 22, 2017 Subject: Weekly Site Inspection Report—Wheelabrator Ash House Reconstruction Ref 1949 Tech Environmental, Inc. (Tech) is providing this weekly site inspection report for the Wheelabrator North Andover Ash House Replacement project. The observations below and attached photos represent the activities observed during the inspection on September 219 2 17. General Project Progress Developments: Met with Wheelabrator team to conduct weekly inspection of Ash House project. This week's inspection was self-guided following check-in with Gary Collette, Plant Manager. Checked-in with lead job contractor R.H. White and Wheelabrator site team following the inspection. Work in progress noted during the inspection (**Phase I main ash house demolition complete): 1) regular truck loadout of ash was ongoing during the inspection; 2) existing concrete wall refurbishment work in-progress (forming and scarifying for pour prep); 3) footings form work in-progress. 1. Construction Phase — Phase I: Existing concrete wall rebuild and structural footing preparation ongoing for late September concrete pour schedule. 2. Construction Schedule — Project is on schedule with goal to accelerate tasks and complete entire project by end of calendar year. 3. Nuisance Conditions —No nuisance conditions noted, ash loadout containment functioning as designed and no material track-out from ash house facility. No fugitive emissions. Site housekeeping in good condition. Conditions were sunny, dry and breezy. 4. Areas of Non-Compliance — No areas of non-compliance noted, ash house air scrubber in operation and no fugitive emissions were observed from ash transfer. 5. Corrective Actions — Improve housekeeping on NW corner of job site, refresh cover on material stockpiles, combine and/or remove if material no longer planned for use. 6. Dust Mitigation —Ash conveyance and truck loadout was in operation, scrubber in service. New partition seal intact, Ash loadout area confined. 7. Material StockpilinI4 — Materials and stockpiles currently on site within defined construction zone: 1) crushed stone at clarifier pad; 2) sand at clarifier pad; 3) sub-slab fill material; 4) dumpster for construction debris and slab cuts; 5) new lumber, staging and concrete forming materials.— UNCHANGED from prior report. 8. Erosion Control — Covered sand and stone stockpiles covered/intact, sock boom in place around catch basin, new footing spoils covered (refresh), housekeeping in good condition. 9. Scrubber In/Out of Service—Ash loadout in progress and scrubber operational. 10. Next Major Activity — Continuing with existing concrete wall refurbishment/rebuild and footing work ahead of concrete pour scheduled for the week of 9/25. Address: 303 Wyman Street,Suite 295 1 Waltham, MA 02451 1 Phone:781-890-2220 1 Fax:781-890-9451 1 Website:www.techenv.com 7' a ..., �� - MINE. Site Inspection Photos (cont.) I � Ihb�VII 11 i r Yt r VV i i T I(- �m ra �111 i � M `¢yam{ + 17 iYEigy�Ya. Y^. f 13, ICI �9� Site Inspection Photos (cunt,) M. w' ° x era �• �, �. 4€ i r ' � f ' r rs I I� € y,€ �r i �g� Site Inspection Photos (cont.) u ,<r r a ; e e v r l f t �4 r� a P s Y cgq �i Site Inspection Photos (coat.) F � VV ' r s ' tl k R MA f a FOCUSED KNOWLEDGE. REAL SOLUTIONS. SITE INSPECTION MEMORANDUM To: Town of North Andover—Planning& Health Departments From: Tim Jones Date: September 15, 2017 Subject: Weekly Site Inspection Report—Wheelabrator Ash House Reconstruction Ref 1949 Tech Environmental, Inc. (Tech) is providing this weekly site inspection report for the Wheelabrator North Andover Ash House Replacement project. The observations below and attached photos represent the activities observed during the inspection on Septe fiber 1,3 22 17. General Project Progress Developments: Met with Wheelabrator team to conduct weekly inspection of Ash House project. This week's inspection was self-guided following check-in with Gary Collette, Plant Manager. Checked-in with lead job contractor R.H. White and Kevin Beauregard, Plant EH&S Manager during inspection. Work in progress noted during the inspection (**Phase I main ash house demolition complete): 1) regular truck loadout of ash was ongoing during the inspection; 2) existing concrete wall refurbishment work in-progress (staging installation, aged concrete hammering/chipping); 3) footing excavation work in-progress (slab cutting, hammering, subsurface material excavation). 1. Construction Phase — Phase I: V phase of main ash house demo is complete, existing concrete base wall rebuild and new structure footing preparation in-progress. 2. Construction Schedule — Project is on schedule with goal to accelerate tasks and complete entire project by end of calendar year. 3. Nuisance Conditions —No nuisance conditions noted, ash loadout containment functioning as designed and no material track-out from ash house facility. No fugitive emissions. Site housekeeping in excellent condition. 4. Areas of Non-Compliance — No areas of non-compliance noted, ash house air scrubber in operation and no fugitive emissions were observed. S. Corrective Actions—None required. Conditions were dry and sunny. 6. Dust Mitigation —Ash conveyance and truck loadout was in operation, scrubber in service. New partition seal intact,Ash loadout area confined. 7. Material Stockpiling — Materials and stockpiles currently on site within defined construction zone: 1) crushed stone at clarifier pad; 2) sand at clarifier pad; 3) sub-slab fill material; 4) dumpster for construction debris and slab cuts; 5) new lumber, staging and concrete forming materials. 8. Erosion Control — Covered sand and stone stockpiles covered/intact, sock boom in place around catch basin, new footing spoils covered, housekeeping in excellent condition. 9. Scrubber In/Out of Service—Ash loadout in progress and scrubber operational. 10. Next Major Activity — Continuing with existing concrete wall refurbishment/rebuild and footing work ahead of concrete pour scheduled for the week of 9/25. Address: 303 Wyman Street,Suite 295 1 Waltham, MA 02451 1 Phone:781-890-2220 1 Fax:781-890-9451 1 Website:www.techenv.com eelabrator North Andover—Site Inspection Photos 09/1 /2017 l i f _t Y 1y Sri i t �X 2- w f i �- fl aF �L 1 w ye m Site Inspection Photos (cont.) v r 4 I ..r i V v i �T. k - _ J i II I I 'I ICI q+ICI I� iI�II V�Ilill I I�i. IV 'fill I I i'Yli i I I I li it III Y I III h II Site Inspection Photos (cunt.) ff k >r - J 4 I u v�e y I I it lil I �r r�I y f�l ry I 1I' pv I f a s rE �� 6 I ' fSf P .o Allows- � � s t r Site Inspection Photos (cont.) III�I � z x, q f S � 3 i S 1 � c a r � f f J 5� t " sy� I FOCUSED KNOWLEDGE. REAL SOLUTIONS. SITE INSPECTION MEMORANDUM To: Town of North Andover—Planning&Health Departments From: Tim Jones Date: September 8, 2017 Subject: Weekly Site Inspection Report—Wheelabrator Ash House Reconstruction Ref 1949 Tech Environmental, Inc. (Tech) is providing this weekly site inspection report for the Wheelabrator North Andover Ash House Replacement project. The observations below and attached photos represent the activities observed during the inspection on September 06, 2017. General Project Progress Developments: Met with Wheelabrator team to conduct weekly inspection of Ash House project. This week's inspection was self-guided following check-in with Gary Collette, Plant Manager, and Kevin Beauregard, Plant EH&S Manager. Work in progress noted during the inspection (**Phase I main ash house demolition complete): 1) regular truck loadout of ash was ongoing during the inspection; 2) existing concrete wall refurbishment work in-progress (staging installation, aged concrete hammering/chipping); 3) footing excavation work in-progress (slab cutting, hammering, subsurface material excavation). 1. Construction Phase — Phase I: 11t phase of main ash house demo is complete, existing concrete base wall rebuild and new structure footing preparation in-progress. 2. Construction Schedule — Project is on schedule with goal to accelerate tasks and complete entire project by end of calendar year. Extended work hours have been granted. Next major milestone is foundation and footing pour work on/about the week of 9/25. 3. Nuisance Conditions —No nuisance conditions noted, ash loadout containment functioning as designed and no material track-out from ash house facility. No fugitive emissions. Site housekeeping in excellent condition. 4. Areas of Non-Compliance — No areas of non-compliance noted, ash house air scrubber in operation and no fugitive emissions were observed. 5. Corrective Actions — None required: previously requested sock boom has been placed around catch basin in former clarifier pad area. Conditions were dry with rain in forecast. 6. Dust Mitigation —Ash conveyance and truck loadout was in operation, scrubber in service. New partition seal intact,Ash loadout area confined. 7. Material Stockpiling — Materials and stockpiles currently on site within defined construction zone: 1) crushed stone at clarifier pad; 2) sand at clarifier pad; 3) sub-slab fill material; 4) dumpster for construction debris; 5) new lumber, staging and concrete forming materials. 8. Erosion Control — Covered sand and stone stockpiles covered/intact, sock boom in place around catch basin, new footing spoils covered,housekeeping in excellent condition. 9. Scrubber In/Out of Service—Ash loadout in progress and scrubber operational. 10. Next Major Activity — Continuing with existing concrete wall refurbishment/rebuild and footing work ahead of concrete pour scheduled for the week of 9/25. Address: 303 Wyman Street,Suite 295 1 Waltham,MA 02451 1 Phone:781-890-2220 1 Fax:781-890-9451 1 Website:www.techenv.com heelabrator North Andover— Site Inspection Photos 09/06/2017 l 3 3 W� i I Site Inspection Photos (coot.) x r � ,r E w r g t W � 1 Fi ys y F w � Site Inspection Photos (cunt.) — ` � � t w w o -. .1..��'`. T a v t Site Inspection Photos (cont.) W l }xl x� n + a � re A r. t � r 3M1L's —= r I11 �.Y Site Inspection Photos (cunt.) 'I III � I r � " 4 Liy yr, ; 3 tlp t'CF �t Site Inspection Photos (cost.) � k y r r u r � V I `rk d h Y ti•. VIu I � kY I"11 w° y S FOCUSED KNOWLEDGE. REAL SOLUTIONS. SITE INSPECTION MEMORANDUM To: Town of North Andover—Planning& Health Departments From: Tim Jones Date: September 1, 2017 Subject: Weekly Site Inspection Report—Wheelabrator Ash House Reconstruction Ref 1949 Tech Environmental, Inc. (Tech) is providing this weekly site inspection report for the Wheelabrator North Andover Ash House Replacement project. The observations below and attached photos represent the activities observed during the inspection on August 31, 20 L. General Project Progress Developments: This week's inspection was self-guided following a meeting with Wheelabrator site management team, Board of Health and Director of Public Health. Work in progress noted during the inspection: 1) regular truck loadout of ash was ongoing during the inspection; 2) Phase 1 ash house demolition complete and all steel and building materials removed from site; 3) existing concrete wall refurbishment work initiated (staging installation); 4) footing excavation work initiated(slab cut and subsurface material excavation). 1. Construction Phase — Phase I: lst phase of main ash house demo is complete and existing concrete base wall rebuild in progress. 2. Construction Schedule — Existing main ash house building demolition complete, all demolition materials have been removed from site. Existing wall is being staged to begin concrete forming/drilling and new structural footings excavation in progress. 3. Nuisance Conditions —No nuisance conditions noted, ash loadout containment functioning as designed and no material track-out from ash house facility. No fugitive emissions. Site housekeeping in excellent condition. 4. Areas of Non-Compliance — No areas of non-compliance noted, ash house air scrubber in operation and no fugitive emissions were observed. 5. Corrective Actions — None required: previously requested sock boom has been placed around catch basin in former clarifier pad area. Conditions were dry. 6. Dust Mitigation —Ash conveyance and truck loadout was in operation, scrubber in service. New partition seal intact,Ash loadout area confined. 7. Material Stockpiling —Materials and stockpiles currently on site: 1) crushed stone at clarifier pad; 2) sand at clarifier pad; 3) sub-slab fill material - will all be covered by Friday 9/1; 4) dumpsters and plastic sheeting have been picked up and removed; 5) new lumber, staging and concrete forming materials on site and staged within clarifier pad area. 8. Erosion Control — Covered sand and stone stockpiles covered/intact, sock boom in place around catch basin, new footing spoils to be covered, housekeeping in excellent condition. 9. Scrubber In/Out of Service—Ash loadout in progress and scrubber operational. 10. Next Major Activity — Continue with existing concrete wall refurbishment/rebuild and footing work. Address: 303 Wyman Street,Suite 295 1 Waltham, MA 02451 1 Phone:781-890-2220 1 Fax:781-890-9451 1 Website:www.techenv.com c h Yr" � a ✓ f � err l � _ 6 r - Z.—.a. i g _ ta s r P, T^ L� r � 4 .. ~ M 21 �v - r Site Inspection Photos (cont.) m Y t � . 8 � r y T.s t! r, i i r n. —+ i Site Inspection Photos (cunt.) S { 4 17. f �I �p 5 4 �q d u� r "s 4 k�[ tl yv � II 3 i i f 9 i r ' Site Inspection Photos (cont.) r s F r 4 , r 4 �r Y rr Site Inspection Photos (cont.) Y" rt K k y „fi f f , s b a� f � yr, — 9S� u "ter F &s Site Inspection Photos (cont.) µ , i, e I Ys,dz�k k'��•i'�y lilt a r i I i � r i �p. f t� L t _ 4 t TEKH FOCUSED KNOWLEDGE. REAL SOLUTIONS, SITE INSPECTION MEMORANDUM To: Town of North Andover—Planning&Health Departments From: Tim Jones Date: August 25, 2017 Subject: Weekly Site Inspection Report—Wheelabrator Ash House Reconstruction Ref 1949 Tech Environmental, Inc. (Tech) is providing this weekly site inspection report for the Wheelabrator North Andover Ash House Replacement project. The observations below and attached photos represent the activities observed during the inspection on August 24, 2017. General Project Progress Developments: Met with Wheelabrator team to conduct weekly inspection of Ash House project. This week's inspection was self-guided following check-in with Gary Collette, Plant Manager. Work in progress noted during the inspection: 1) regular truck loadout of ash was ongoing during the inspection; 2)major ash house roof and building demo in progress. 1. Construction Phase—Phase 1 2. Construction Schedule — Existing ash house building demolition ongoing with all building roof and wall cladding removed and most of the steel framing taken down. Steel super structure being cut and dismantled in pieces with crane and lift assist. 3. Nuisance Conditions —No nuisance conditions noted, ash loadout containment functioning as designed and no material track-out from ash house facility. No fugitive emissions. 4. Areas of Non-Compliance — No areas of non-compliance noted, ash house air scrubber in operation and no fugitive emissions were observed. 5. Corrective Actions — Requested a sock boom be placed around the catch basin in the former clarifier pad for added protection from rain events and construction wet down. 6. Dust Mitil4ation —Ash conveyance and truck loadout was in operation, scrubber in service. New partition wall installed and sealed for demo phasing work. Ash loadout area confined. As noted in photos, plastic sheeting is skirting the demolition zone to capture any ash and debris resulting from building demolition activity. 7. Material Stockpiling — As previously noted, two covered material stockpiles currently on site: 1) crushed stone at clarifier pad; 2) sand at clarifier pad. All of the demolished steel framework is lowered onto floor of ash house for further cutting to disposal size. Piles of steel beams are kept within the walls of the ash house where debris is confined and swept up for dumpster disposal. 8. Erosion Control— Covered sand and stone stockpiles covered/intact and a sock boom to be placed around the solitary catch basin for added inlet protection from work activities. 9. Scrubber In/Out of Service—Ash loadout in progress and scrubber operational. 10. Next Major Activity — Continue with steel frame demolition phase of main ash house building, demo steel material hauling offsite to begin week of 8/28. Existing concrete wall refurbishment and forming work slated to begin once all steel demo complete. Address: 303 Wyman Street,Suite 295 1 Waltham,MA 02451 1 Phone:781-890-2220 1 Fax:781-890-9451 1 Website:www.techenv.com Wheelabrator North Andover— Site Inspection Photos 08/24/2017 ,�,, ,fir-'�� ✓ �".r-.�' r � <--�"K '��^-G.��, �. c " ,�„' �. �,-.✓..-.-'--'f-'mac. ..:-`�'�-.,� �,, c ,F � uy F t j�F t�rr M , I�{�� �I e ff k S l f l w � i x yII 1 d lit l i III{ i LI{ rl(rl ! I g,. U( M ,ern ti r Site Inspection Photos (coot.) v. 9 z;. f i 3 I ail i t l ✓ l r 't S It �� 1 G Site Inspection Photos (cont.) ,� .,cam u' r'� •-`- r r r r i r r r r r r: ru � r f r r tj l 6' a I I r ",ram. rr r �n 3 IIII Site Inspection Photos (cont.) y y s ,µ ham_ q; 7 T uaeYl 4 i l^ 4 � r 3 pry i Y Site Inspection Photos (cont.) f f l l f e / F t � J � k n r � x � a a z _ r, TrN �,Y I r �r 3 pill v er= oil € r i r� i` a J a p tdtr-�•'•, 'rf� 8/25/2017 Town of North Andover Mail-Weekly Inspection Report-Wheelabrator Ash House Project-August 24 NORTH ANDOVER Massachusetts Rebecca Oldham <roldham@northandoverma.gov> Weekly Inspection Report - Wheelabrator Ash House Project - August 24 1 message Tim Jones <tjones@techenv.com> Fri, Aug 25, 2017 at 7:33 AM To: Rebecca Oldham <roldham@northandoverma.gov>, Brian LaGrasse <blagrasse@northandoverma.gov> Good Moring Rebecca and Brian, Please see the attached weekly inspection report and photo log. Project is going according to expectations/schedule with initial phase of main ash house demolition winding down. No compliance or nuisance condition issues observed and site management practices are up to spec. Gary let me know they have communicated to the Planning Dept. that they are planning to accelerate their schedule to complete the project by the end of the calendar year. In addition, they had asked and been granted some extended work hours to support that goal. A project schedule update is in the works. Please let me know if you have any questions. Have a great weekend, Tim Tim Jones, PMP Associate TECH ENVIRONMENTAL Focused Knowledge, Real Solutions 303 Wyman Street, Suite 295 Waltham, MA 02451 (0) 781.890.2220 X32 (C) 802,279,9418 Fax: 781.890.9451 tjones@TechEnv.com w,vw.TechEnv.com https://mail.goog le.corn/ma il/u/0/?ui=2&ik=ab4f3cb798&jsver=xueMu_41 Keg.en.&view=pt&search=inbox&th=15a192afd357236f&siml=15e192afd357236f 1/2 8/25/2017 Town of North Andover Mail-Weekly Inspection Report-Wheelabrator Ash House Project-August 24 WNA_Sitelnspection Repo rt_08242017.pdf 4049K https://mail.google.com/mail/u/0/?ui=2&ik=ab4f3cb798&jsver=xueMu 4lKeg.en.&view=pt&search=inbox&th=15e192afd357236f&siml=15e192afd357236f 2/2 TeCH FOEUSEO KNO1n1LEOGE, REAL SOLUTIONS, SITE INSPECTION MEMORANDUM To: Town of North Andover—Planning& Health Departments From: Tim Jones Date: August 18, 2017 Subject: Weekly Site Inspection Report—Wheelabrator Ash House Reconstruction Ref 1949 Tech Environmental, Inc. (Tech) is providing this weekly site inspection report for the Wheelabrator North Andover Ash House Replacement project. The observations below and attached photos represent the activities observed during the inspection on Lt-ut ::st 17,2017. General Project Progress Developments: Met with Wheelabrator team to conduct weekly inspection of Ash House project. This week's inspection was self-guided following check-in with Gary Collette, Plant Manager, and Kevin Beauregard, Plant EH&S Manager. Work in progress noted during the inspection: 1) regular truck loadout of ash was ongoing during the inspection; 2)major ash house roof and building demo in progress. 1. Construction Phase—Phase I 2. Construction Schedule — Existing ash house building demolition has been initiated with wall sheathing removal and crane-assisted roof structural removal. 3. Nuisance Conditions —No nuisance conditions noted, ash loadout containment functioning as designed and no material track-out from ash house facility. No fugitive emissions observed. 4. Areas of Non-Compliance — No areas of non-compliance noted, ash house air scrubber in operation and no fugitive emissions were observed. 5. Corrective Actions—No corrective actions required. 6. Dust Nitration —Ash conveyance and truck loadout was in operation, scrubber in service. New partition wall installed and sealed for demo phasing work. Ash loadout area confined. As noted in photos, plastic sheeting is skirting the demolition zone to capture any ash and debris resulting from building demolition activity. 7. Material Stockpiling — As previously noted, two covered material stockpiles currently on site: 1) crushed stone at clarifier pad; 2) sand at clarifier pad. WNA updated Town Planner with a site plan to ID this temporary location on August llch 8. Erosion Control — No additional erosion control measures required with this work-in- progress outside of covered material stockpiles. 9. Scrubber In/Out of Service—Ash loadout in progress and scrubber operational. 10. Next Major Activity—Continue with initial demolition phase of main ash house building. Address: 303 Wyman Street,Suite 295 1 Waltham,MA 02451 1 Phone:781-890-2220 1 Fax:781-890-9451 1 Website:www.techenv.com Wheelabrator North Andover—Site Inspection Photos 08/17/2017 r � y s � r I t r, �z s j ram' r Site Inspection Photos (cont.) s � �.,r"' �. r'_ r �,r? ��r�_✓r �"-�"`r�. '�`�' �, "�'�Y r r- �� ..�.,. .�r .„.r='" . r r 'r u t i r Site Inspection Photos (cont.) i I �t i tee= Y i I P " rvMs ..6 4 P' p 2 Y � a $o �^a r r- �t x r�. G ,b�o .,'_„ -• K w r F ram' 1 �G Site Inspection Photos (cont.) r_ " r " w µ 3 " re' j y i � r E u " E .. E r f � i " Site Inspection Photos (cont.) U� R N v a f 8/11/2017 Town of North Andover Mail-Weekly Inspection Report-Wheelabrator Ash House Project Rebecca Oldham <roldham@northandoverma.gov> Weekly Inspection Report - Wheelabrator Ash House Project 1 message Tim Jones <tjones@techenv.com> Fri, Aug 11, 2017 at 11:53 AM To: Rebecca Oldham <roldham@northandoverma.gov>, Brian LaGrasse <blagrasse@northandoverma.gov> Good Moring Rebecca and Brian, Please see the attached weekly inspection and updated site plan that Matt Hughes forwarded this AM. Project is going according to expectations. Two items we addressed yesterday: 1) requiring cover of idle/temp stockpiles (ID'd on site plan update); and 2) keeping the ash loadout bay doors closed at all times during ash loading activities. In sum, no fugitive emissions/nuisance conditions noted and the facility was immediately responsive to my observations/corrective action requests. Please let me know if you have any questions. Have a great weekend, Tim Tim Jones, PMP Associate TECH ENVIRONMENTAL Focused Knowledge. Real Solutions 303 Wyman Street, Suite 295 Waltham, MA 02451 (0) 781.890.2220 X32 (C) 802,279.9418 Fax: 781.890.9451 tjones@TechEnv.com www,TechEnv.com https://mail.goog le.com/mail/u/0/?ui=2&ik=ab4f3cb798&jsver=Tz53q 167 F 1 w.en.&view=pt&search=inbox&type=15dd 1 f3d 1 ce0848e&th=l 5dd20051 b9c... 1/2 8/11/2017 Town of North Andover Mail-Weekly Inspection Report-Wheelabrator Ash House Project 2 attachments WNA_Sitelnspection_08112017.pdf 4350K Ash House Project Excavated Soils Staging Location.pdf 2366K https:Hmail.google.com/mail/u/0/?ui=2&ik=ab4f3cb798&jsver=Tz53gl67F1w.en.&view=pt&search=inbox&type=15ddlf3dl ceO848e&th=15dd20051 b9c... 2/2 FOCUSEO KNOWLEDGE. REAL SOLUTIONS. SITE INSPECTION MEMORANDUM To: Town of North Andover—Planning&Health Departments From: Tim Jones Date: August 11, 2017 Subject: Weekly Site Inspection Report—Wheelabrator Ash House Reconstruction Ref 1949 Tech Environmental, Inc. (Tech) is providing this weekly site inspection report for the Wheelabrator North Andover Ash House Replacement project. The observations below and attached photos represent the activities observed during the inspection on august 10,2017. General Project Progress Developments: Met with Wheelabrator team to conduct weekly inspection of Ash House project. This week's inspection was self-guided following check-in with Gary Collette, Plant Manager, and Kevin Beauregard, Plant EH&S Manager. Work in progress noted during the inspection: 1) regular truck loadout of ash was ongoing during the inspection; 2) initial ash house roof demo has begun at the west-side concrete wall and adjoining metals building; 3) binder asphalt coat has been applied to clarifier pad; 4) new scrubber pad footing/walls complete, final pad work in progress, security/construction zone chain link fence has been installed. 1. Construction Phase—Phase I 2. Construction Schedule — New scrubber pad forming, beginning of existing ash house building demolition has been initiated along west side of ash building, east side of adjoining metals building. 3. Nuisance Conditions —No nuisance conditions noted, ash loadout containment functioning as designed and no material track-out from ash house facility. No fugitive emissions observed. 4. Areas of Non-Compliance — 1) identified two uncovered material stockpiles, sand and aggregates, that are temporarily staged/not in active use adjacent to clarifier pad to complete scrubber pad work; 2) ash truck loading in progress with rollup doors open at front of truck loading bay—scrubber in operation and no fugitive emissions were observed. 5. Corrective Actions — Consulted with site managers: 1) temporary sand and aggregates stockpiles to be covered to prevent exposure while not in active use; 2) ash house doors were immediately closed per site operating protocol for ash handling/truck loading. b. Dust Mitil4ation —Ash conveyance and truck loadout was in operation, scrubber in service. New partition wall installed and sealed for demo phasing work. Ash loadout area confined. 7. Material Stockpiling — As previously noted, two material stockpiles currently on site: 1) crushed stone at clarifier pad; 2) sand at clarifier pad. WNA updated Town Planner with a site plan to ID this temporary location on August I1th 8. Erosion Control — No additional erosion control measures required with this work-in- progress outside of covering material stockpiles. 9. Scrubber In/Out of Service—Ash loadout in progress and scrubber operational. 10. Next Major Activity—Continue with initial demolition phase of main ash house. Address: 303 Wyman Street,Suite 295 1 Waltham,MA 02451 1 Phone:781-890-2220 1 Fax:781-890-9451 1 Website:www.techenv.com Wheelabrator North Andover— Site Inspection Photos 08/10/2017 ME ------------ a it � V Site Inspection Photos (cost.) lll�MAN, ji S - G w � w� y�Ji Jw �y r i y- Site Inspection Photos (cont.) t . �4 r ,a. s �✓ F x 1 { d �s £ r, i Site Inspection Photos (cont.) 9 3., i. 1 j + d& k $11'v P r� Vg I I( d i r Site Inspection Photos (cost,) IN r I �I a. 3 r r f I, � 1 Site Inspection Photos (cont.) nuel 2 w 1 s, r r 3 Corrective Action Photo from WNA on 8/11/17 n a" TeCH FOCUSEO KNOWLEOGE. REAL SOLUTIONS. SITE INSPECTION MEMORANDUM To: Town of North Andover—Planning& Health Departments From: Tim Jones Date: August 4, 2017 Subject: Weekly Site Inspection Report—Wheelabrator Ash House Reconstruction Ref 1949 Tech Environmental, Inc. (Tech) is providing this weekly site inspection report for the Wheelabrator North Andover Ash House Replacement project. The observations below and attached photos represent the activities observed during the inspection on August 3, 2017.. General Project Progress Developments: Met with Wheelabrator team to conduct weekly inspection of Ash House project. This week's inspection was completed with Kevin Beauregard, Plant EH&S Manager. Work in progress noted during the inspection: 1) regular truck loadout of ash was ongoing during the inspection; 2) completion of existing ash house wipe down and partition wall installation; 3) completion of form work inside clarifier footprint(scrubber fan/motor pad) and final backfill/compaction in prep for binder pavement; 4) ash loadout facility completely enclosed/functional in preparation of building demo start. 1. Construction Phase—Phase I 2. Construction Schedule—Bulk ash removal/building cleaning, partition wall install, clarifier backfill, scrubber pad forming, metals building support strucutures. 3. Nuisance Conditions —No nuisance conditions noted, ash loadout containment functioning as designed and no material track-out from ash house facility. 4. Areas of Non-Compliance — No areas of non-compliance noted, construction activities match project schedule and containment areas functional. 5. Corrective Actions—No corrective actions required. 6. Dust Mitigation — No dust generating activities in progress during inspection, ash conveyance and truck loadout was in operation, scrubber in service. New partition wall has been installed and sealed to prepare for initial demo work. Ash loadout area confined. 7. Material Stockpiling — Two material stockpiles currently on site: 1) crushed stone at clarifier pad; 2) sand at clarifier pad. Materials for clarifier and concrete form work. 8. Erosion Control—No erosion control measures required with this work-in-progress. 9. Scrubber In/Out of Service—Ash loadout in progress and scrubber operational. 10. Next Major Activity—Begin I"phase of existing building demolition the week of August 7, 2017. Address: 303 Wyman Street,Suite 295 1 Waltham, MA 02451 1 Phone:781-890-2220 1 Fax:781-890-9451 1 Website:www.techenv.com Wheelabrator North Andover—Site Inspection Photos 08/03/2017 v r r >E Iry r�r a �I Site Inspection Photos (cont.) y ems, r 3 rcr l y w r;v "rl i � i Site Inspection Photos (cont.) go �. � e [[ x r e j r� i w r a; r � w � e �M a w l f rti Site Inspection Photos (cont.) 6 �d Iffi NOW,; Y }' �w �r utii � r g w " . Site Inspection Photos (cont.) - E 7j s � L 1 r I i iui �I L. w 1 s 3 Pl.v ?k 4 Site Inspection Photos (cont.) ram. �r 1 ' r rx' is I l t Iu� r t f, d I I I�IVII r{ i t, ^Jk. t r^ i �M TeCH FOCUSEO KNOWLEDGE, REAL SOLUTIONS. SITE INSPECTION MEMORANDUM To: Town of North Andover—Planning& Health Departments From: Tim Jones Date: July 28, 2017 Subject: Weekly Site Inspection Report—Wheelabrator Ash House Reconstruction Ref 1949 Tech Environmental, Inc. (Tech) is providing this weekly site inspection report for the Wheelabrator North Andover Ash House Replacement project. The observations below and attached photos represent the activities observed during the inspection on July 26, 2017. General Project Progress Developments: Met with Wheelabrator team to conduct weekly inspection of Ash House project. No physical inspection was conducted on July 19 but a general progress report and photos were forwarded to the Planning and Health Departments as an update. This week's inspection was completed with Gary Collette, Plant Manager. Tech also consulted with Richard Falk, Manager of Air Quality, to review the specifics of the Ash House Dust Collection Scrubber and its typical operation. Work in progress noted during the inspection: 1) regular truck loadout of ash was ongoing during the inspection; 2) continuance of existing ash house wipe down in prep for partition wall install and demo; 3) form work inside clarifier footprint,preparing for ultimate backfill. 1. Construction Phase—Phase I 2. Construction Schedule—Bulk ash removal and cleaning of metal support framework. 3. Nuisance Conditions—No nuisance conditions noted, ash loadout containment functioning. 4. Areas of Non-Compliance — No areas of non-compliance noted, construction activities match project schedule. 5. Corrective Actions—No corrective actions required. 6. Dust Mitigation — No dust generating activities in progress during inspection, ash conveyance and truck loadout was in operation, scrubber in service. New containment structure for ash truck loadout (building bump-out at ash bay roll-up door) has been constructed and sealed to initiate modified ash loadout use. 7. Material StockpilinLy — One material stockpile currently on site: 1) crushed stone at clarifier pad. Metals support building support structures inspected and backfilled. 8. Erosion Control—No erosion control measures required with this work-in-progress. 9. Scrubber In/Out of Service—Ash loadout in progress and scrubber operational. Tech has reviewed Wheelabrator's `Municipal Waste Combustor Emission Control Plan' (Oct. '98), and confirmed the ash house scrubber operation is discretionary/operated as needed to control fugitive dust emissions. The combination of the enclosed storage building and wet conveyed ash should adequately control fugitive emissions. It can be necessary during truck loading and other ash handling, Tech will monitor activity-based fugitive emissions. 10. Next Major Activity — Preparation/start of ash house partition wall to begin week of July 31, 2017. Address: 303 Wyman Street,Suite 295 1 Waltham,MA 02451 1 Phone:781-890-2220 1 Fax:781-890-9451 1 Website:www.techenv.com heelabrator North Andover—Site Inspection Photos 07/26/2107 § '!q a � i 1i�4 t �E} � s� 16 1 S��� '^"-�j�~�.,-'-"'� c����c�;,�^�.w,��r ,-r �✓�, f{{fff yy �jfrfr t� [� I Hill 771 S. ......................... ------------------------------------------------- r v �^ �A r s 3 x r � .. f r r i # Ai r ,fit Site Inspection Photos (cont.) o _ s 3 =»x z �w t L � v n: Y? dl 6 N �r Site Inspection Photos (cost.) ------------------ er,F4 eaa /'- a o fF fU s t e r r r n . w o-_4 i v a s t S+ 2 F' M. s a 2.,Y.s�..,..,m......,.>.........<..:..,,...n...Y.,�,:.._...ev..e. e�:�.,....e..�.:..,....... ......n,�.m...,�....,......,aa..m..,.....,iv�:,.�a..._.... .._,..__„�.._w..�. _.t....a...,,,.4.,a..�..e.,.<.....a.� .....,e.....,.d.,r,....m.....,,"««.ia.,:..,r....,.....«.:..a�,s.. ..�,^�i..--.:...r.,�,...�a�".fa�.-,r.,...--.,:.. ,,....v»......„...,« Site Inspection Photos (cont.) .0 Ai a� �r������ �„.� �---�".--ram"�� :.r �'�✓� -�r��. I � a a � , r 7/21/2017 Town of North Andover Mail-Wheelabrator Ash House Progress Report-Week of July 17 NoRTfi ANDOVER Massachusetts Rebecca Oldham <roldham@northandoverma.gov> heelabrator Ash House Progress Report - Week of July 17 Tim Jones <tjones@techenv.com> Fri, Jul 21, 2017 at 8:08 AM To: Rebecca Oldham <roldham@northandoverma.gov>, Brian LaGrasse <blagrasse@northandoverma.gov> Good Morning, The following is a brief progress report with photo documentation of construction/operation activities over the past week. As we confirmed this week, routine site inspections will resume the week of 7/24. • The ash stacker retro-fit was completed on 7/11 and the facility has since transitioned to a 24-hr. ash load-out operation, with ash being transported away from the facility daily from approximately 5AM through 3PM. • As far as schedule is concerned, the fan foundation activities were pulled forward to facilitate the ability to backfill the clarifier, both tasks anticipated being complete by 7/31. • The removal of bulk ash from within the ash bldg. is on schedule and the manual cleaning process of removing ash from the metal support members has begun. • The west exterior wall gutter system has been fastened in preparation for the commencement of interior water wash activities. • The metals roof structure support foundations have been poured and backfilled with preparations for the concrete slab pour in progress with an anticipated completion by 7/21. Please let me know if you have any questions. Based on the construction/operational task completion and photo array, no nuisance/environmental conditions noted to address and the activity base is in-step with the published project schedule. Thank you and have a great day, Tim Tim Jones, PMP Associate https://mail.google.com/mail/u/0/?ui=2&ik=ab4f3eb798&jsver=-6exfAFCXgM.en.&view=pt&msg=15d65Oc35f39291 a&search=inbox&siml=15d65Oc35f3... 1/2 7/21/2017 Town of North Andover Mail-Wheelabrator Ash House Progress Report-Week of July 17 TECH ENVIRONMENTAL Focused Knowledge. Real Solutions 303 Wyman Street, Suite 295 Waltham, MA 02451 (0) 781.890.2220 X32 (C) 802.279.9418 Fax: 781,890.9451 tjones@TechEnv.com www.TechEnv.com Wheelabrator_NA_AshHouseReconstruct_Progress_07212017.pdf 351 K https://mai1.google.com/mail/u/0/?ui=2&ik=ab4f3cb798&jsver=-6exfAFCXgM.en.&view=pt&msg=15d65Oc35f39291 a&search=inbox&siml=l 5d65Oc35f3... 2/2 Wheelabrator-North Andover Ash House Progress—Week of 7/17/17 � 4 ✓ r � €4, v � v of � ✓ �... U. y i w Wheelabrator-North Andover Ash House Progress—Week of 7/17/17 (cont.) �s. ram -_ w f� r f _.,,.......-._m.,. 777 r i� !Im r � III , � v -�.- �.,„�"" � Wheel abrator-North Andover Ash House Progress—Week of 7/17/17 (cont.) w. N. �f a 4 1�� s t 7 ems. �r r � FOCUSED KNOWLEDGE. DEAL SOLUTIONS, SITE INSPECTION MEMORANDUM To: Town of North Andover—Planning& Health Departments From: Tim Jones Date: July 14, 2017 Subject: Weekly Site Inspection Report—Wheelabrator Ash House Reconstruction Ref 1949 Tech Environmental, Inc. (Tech) is providing this weekly site inspection report for the Wheelabrator North Andover Ash House Replacement project. The observations below and attached photos represent the activities observed during the inspection on July 12, 2017. General Project Progress Developments: Met with Wheelabrator team to kickoff weekly inspections, review schedule and establish expectations for routine inspection and reporting activities. Pre- inspection meeting attendees included Tim Jones (Tech), Gary Collette, Matt Hughes, Kevin Beauregard and Richard Falk (Wheelabrator). Site inspection team included Tim Jones, Gary Collette and Matt Hughes. Work in progress on this project since start of permit approval of June 29: 1) scrubber duct work reconfiguration; 2) ash conveyor shortening; 3) ash house wipe down; 4) prep of crane pad inside clarifier footprint; 5) construction of modified ash truck loadout building extension/containment; 6) installation of support footings under adjoining metals building(footings and support forms). 1. Construction Phase—Phase I 2. Construction Schedule—Primary Task ID No. 3: Ash Conveyor Shortening. 3. Nuisance Conditions—No nuisance conditions noted. 4. Areas of Non-Compliance — No areas of non-compliance noted, construction activities match project schedule. 5. Corrective Actions—No corrective actions required. 6. Dust Mitil4ation — No dust generating activities in progress during inspection, ash conveyance and truck loadout was idle. New containment structure for ash truck loadout (building bump-out at ash bay roll-up door) has been constructed and sealed to initiate modified ash loadout use. 7. Material Stockpiling — Two material stockpiles currently on site: 1) crushed stone at clarifier pad; 2) excavated soil from support footings under metals building (stockpiled inside building). S. Erosion Control—No erosion control measures required with this work-in-progress. 9. Scrubber In/Out of Service — Ash conveyance not in progress during inspection to accommodate conveyor shortening/retrofit for `live loading' of ash during construction phase. Scrubber to be in service once ash handling resumes. 10. Next Major Activity — Preparation/start of ash house partition wall to begin week of July 17, 2017. Address: 303 Wyman Street,Suite 295 1 Waltham,MA 02451 1 Phone:781-890-2220 1 Fax:781-890-9451 1 Website:www.techenv.com Wheelabrator North Andover—Site Inspection Photos 07/12/2107 �o K a` w a Q " Site Inspection Photos (cont.) a. "1 _ w i �. I Site Inspection Photos (cost.) 0 k 3 a i 3 _r f� a r t r �� Site Inspection Photos (cont.) E, I i f I i l a r r ka n F.• ✓ ��. 3s.;, i �tiwl�"t3'q. wit# r T l � w Gary Collette From: Donald Belanger <dbelanger@northandoverma.gov> Sent: Wednesday, May 10, 2017 4:50 PM To: Gary Collette Cc: Thomas Penna Subject: Re: North Andover 36" Clarifier Pool-Wall Removal Gary that is correct, for safety I would highly recommend removing the 3'high wall and associated attachment. Per our conversation it is my opinion you do not need a permit to remove the wall, the sooner the better. Also the void/area where the water is pooling should be leveled so as not to create any pooling of rain water. Let me know when the job is complete and I will swing by. Thank You Donald Belanger On Wed, May 10, 2017 at 3:50 PM, Gary Collette <c-Tcollette(d,,,wtiener=4v.com>wrote: Inspector Belanger, This email is to confirm our conversation yesterday regarding our intent to remove a section of clarifier pool- wall as depicted in the attached drawing. As discussed, the clarifier pool was once used to settle ash out of our wastewater, but became obsolete circa 2010 when we installed a filter press process. The pool now just collects rain water which is periodically pumped back into the facility. Assuming your continued opinion that a Permit is not required for such work, we intend to remove the 36" vertical wall section and promptly backtill the pool to grade-level without disturbance to adjacent soils or cover. Respectfully, Wheelabrator TECH NO LOG IES Gary Collette Plant Manager, Appreciatively, Gary Collette, Plant Manager, Wheelabrator North Andover Sent from my BlackBerry 10 smartphone on the Verizon Wireless 4G LTE network. CONFIDENTIALITY NOTICE: This message originates from Wheelabrator Technologies Inc. This message and any attachments are solely for the use of the intended recipients. They may contain privileged and/or confidential information or other information protected from disclosure. If you are not an intended recipient, you are hereby notified that you received this email in error and that any review, dissemination, distribution or copying of this email and any attachment is strictly prohibited. If you have received this email in error, please contact the sender and delete the message and any attachment from your system. Public Records Law -.northa Public Records Law www,northandovermamov. 2 I j , � s i ( F tw ul 4 P r f, I t w [ t i 2 p F nt a t i t { a� F nG i p Y 1 ' t cc } � ,pp tI l Y r _ t G ( {7 1 1 wan f L BRATC 2 1 }I�lfll rJL7S UK ,. 4 PN( _If—Tj'�{f�K H_5'FtC ICtt �'TMT av:a SF_910N G�.4� 4 RU LCJM 1'_LAN VIEW Wheelabrator North Andover— Clarifier Preparation Work (7/12/17) ----------------------- 10 r m Wheelabrator North Andover—Clarifier Preparation Work (7/1 /17) r / if 3 5 i Y r/ r � 1 �v I II� •, Y t. � II e w � � 3 Y �r 3 , 4