851 Johnson Street approval
1 message
Daniel Ottenheimer<dano@millriverconsulting.com> Tue, Nov 30, 2021 at 11:39 AM
To: 'Brian Lag rasse (blagrasse@north and overma.gov)" <b lag rasse@northandoverma.gov>, Stephen Casey
<scasey@northandoverma.gov>, "Toni Wolfenden (twolfenden@northandoverma.gov)" <twolfenden@northandoverma.gov>
Brian, Steve, Toni -
Attached please find the approval letter which we suggest issuing for the property at 851 Johnson Street. The project is a
proposed expansion of the dwelling to add additional rooms (or bedrooms)and thus needs to meet the criteria for new
construction under Title 5.
There are a number of approval conditions which are provided here that should be put in place both because this is new
construction and also because they are proposing the use of the Enviro-septic Wastewater Treatment system.
Any questions please do let me know.
Dan
Daniel Ottenheimer, PE
President
Al
V�M�
ILL RIVER CONSULTING
Cacative Solutions liar land Developrnrnt
6 Sargent Street
Gloucester, MA 01930-2719
Phone: 978-282-0014 ext.802
www.miliriverconsulting.com
851 Johnson Street - Plan Approval 11-30-21.docx
77K
Presbynvi* ronmental , Inc .
Trai* ni* ng
This certifies that
Mark Finn
Has completed the Presby Environmental, Inc.
Enviro-Septic' Certification Course
Massachusetts Design & Installation Webinar Class
o
Other state or municipal licenses may be required.
July 17, 2008 DavM W. Yw,13N
Date of training David W. Presby
President and CEO
Certificate No: 6985MAES Presby Environmental, Inc.
7/26/22,4:52 PM Town of North Andover Mail-851 Johnson Street construction inspection
NORTH ANDOVER
Massachusetts Toni Wolfenden <twolfenden@northandoverma.gov>
851 Johnson Street construction inspection
1 message
Daniel Ottenheimer<dano@millriverconsulting.com> Tue, Jul 26, 2022 at 2:59 PM
To: "Brian Lagrasse (blagrasse@north andoverma.gov)"<baagrasse@northandoverma.gov>, Stephen Casey
<scasey@northandoverma.gov>, "Toni Wolfenden (twolfenden@northandoverma.gov)" <twolfenden@northandoverma.gov>
A Few items remain outstanding on this:
• Engineer is reported to have set a new benchmark, need a note from them saying that is what they did.
• The vent pipe has weep holes in it. Need something showing this is allowed by Enviro-septic.
• The house vent has to be determined by the installer if it is acceptable to be considered as a high vent for use with
the Enviro-septic system.
My report of today's inspection is attached. All of this was discussed with the septic system installer.
Please let me know if you have any questions or if I can help with the above.
Dan
Daniel Ottenheimer, PE
President
t MILL RIVER CONSULTING
Orative Solutions for iattd Ik%A0jyment
6 Sargent Street
Gloucester, MA 01930-2719
Phone: 978-282-0014 ext.802
https://mail.google.com/mail/u/0/?ik=aOc6f4e4cf&view=pt&search=all&permthid=thread-f%3Al 739442851184256843&simpl=msg-f%3A173944285118... 1/2
7/26/22,4:52 PM Town of North Andover Mail-851 Johnson Street construction inspection
www.miliriverconsulting.com
Construction Notes -851 Johnson St.docx
64K
https://mail.google.com/mai I/u/0/?ik=aOc6f4e4cf&view=pt&search=all&permthid=thread-f%3Al 739442851184256843&simpl=msg-f%3A173944285118... 212
The
Morin-Cameron
ALAW
3 �
November 18, 2021 To HE OF SORIH R
p,�THDEPA WENT
Mr. Stephen Casey Jr.
Health Inspector
120 Main Street
North Andover, MA 01845
Re: Subsurface Sewage Disposal System Plan — 851 Johnson Street (Map 107A, Lot 62)
Dear Mr. Casey:
We are in receipt of your review of the septic design for the above referenced property dated
October 28, 2021. Please find enclosed the following:
• 3 sets of the revised Sanitary Disposal System design
On behalf of Derek Delaney, The Morin-Cameron Group, Inc. has prepared the following
responses to your comments. For your convenience the response comments are numbered in the
same order and correlate to the numbered comments in your letter:
1. The plan states "Note: All Pipe To Be 4" P.V.C. (SCH. 40) Unless Noted" on the system
profile (see Sheet 2 of 2).
2. The proposed addition will be constructed on a slab foundation, therefore a foundation
drain is not required or proposed.
3. The estimated seasonal high water table (ESHWT)was calculated using a gradient between
Test Pit 21-1 and Test Pit 21-2. Cross section A-A' has been added to sheet 2 of 2 to
illustrate a minimum 4' separation between the bottom of the soil absorption system and
the ESHWT. A column showing the ESHWT calculated based on the gradient was also
added to the "Presby Data" table on sheet 2 of 2. The table has been revised to maintain
a 4' or greater separation from the bottom of the system to ESHWT. A gradient between
test pits 21-1 and 21-4 was also analyzed but was less conservative than the assumed
gradient between 21-1 and 21-2. As a conservative approach the gradient between 21-1
and 21-2 was used for the design.
4. A swale along the property line has been added and noted on the plan view (see Sheet 1
of 2).
CIVIL ENGINEERS • LAND SURVEYORS • ENVIRONMENTAL CONSULTANTS • LAND USE PLANNERS
66 Elm Street, Danvers, MA 01923 978.777.8586
Providing Professional Services Since 1978
www.morincameron.com
Mr. Stephen Casey Jr. November 18, 2021 Page 2
5. The area for conventional primary and conventional reserve leaching facilities have been
bolded on the plan view. The field dimensions have been added in the callouts (see sheet
1 of 2).
6. A note was added to the plan view to call for the roof stack to be utilized as the high vent
and note #21 was added to the general notes (see sheet 1 of 2).
7. General Note#5 was revised to include "(SEE SLOPING VENT DETAIL)" and a sloping vent
detail has been added to sheet 1 of 2.
A. The plan clearly shows the location of the proposed conventional primary and reserve
leach beds. We do not believe a "prof plan" is needed or required.
In addition to the revisions described above, a three-foot sand bed extension has been added to
the PRESBY field and associated reserve system. This extension is required because the slope of
the PRESBY field is greater than 10%.The calculations and plan details have been revised to reflect
the sand bed extension which has been designed in accordance with the PRESBY design manual.
We trust these responses satisfy your questions and concerns. If you have any additional
questions, please do not hesitate to contact our office.
Sincerely,
THE MORIN-CAMERON GROUP, INC.
John Morin, PE
President
JMM/kmm
Attachments
cc: Derek Delaney
X:\Delaney,Derek\4085\Docs\Board of Health\Response comments.dou