Loading...
HomeMy WebLinkAbout2017-01-17 Decision SPR I Town of North Andover Office of the Planning Department Community Development and Services Division 120 Main Street North Andover,Massachusetts 01845 1, 2011 JAN ( $ P 4 NOTICE OF DECISION SITE PLAN REVIEW SPECIAL PERMIT Pursuant to Chapter 40A,Section 17 of the Massachusetts General Laws, appeals from the decision niust be filed Date; January 17,2017 in the office of the Town Cleric Public Hearings: December 6, 2016, January within(20)days after the 3,2017,January 17,2017 date of filing this notice in Date of Decisions January 17,2017 the office of the Town Cleric. Petition of: Chestnut Green Condominiian Association c/o Property Management of Andover P,O. Box 488 Andover,MA 0 18 10 Premises Affected: 555-575 Turnpike Street North Andover,MA 01845 Assessor's Map 25 Lot 11, 69,71 The above application for a Site Plan Review Special Permit is in accordance with the requirements of the North Andover Zoning Bylaw, Section 8.1, 8.3 and 10.3, and Massachusetts General Law Chapter 40A, Section 9. This application is to allow for construction of nine (9) parking spaces and associated stormwater management in the Business 4(B-4)Zone. After a public hearing held on the above dates,and upon a motion by David Kellogg,seconded by Lynne Rudnield, the Planning Board APPROVES the Site Plan Review Special Permit as amended and with conditions.A vote of 5-0 was made in FAVOR of the application. law On beha of the N01111 dover Planning Board John Simons,Chair Lynne Rudnicki David Kellogg Lora McSherry Peter Boynton I € E i The Planning Board herein APPROVE,S the Site Plan Review Special Permit for the construction of'nine (i (9)parking spaces and associated storznwater management in the Business 4(B-4)Zone.This Special Permit was requested by Chestnut Green Condominium Association. The application was filed with the Planning Board on November 7,2016, The public hearing on the above referenced application was opened on December 6,2016, and closed by the North Andover Planning Board on January 17,2017, The Applicant submitted a complete application,which was noticed and reviewed in accordance with Section 8.1, 8.3, 10.3 and 10.31 of the Town of North Andover Zoning Bylaw and MGL c.40A, Sec, 9. The Planning Board voted unanimously(by a vote of 5-0)to grant the Site Plan review,Special Permit. A special permit issued by the planning board,as special permit granting authority, requires a vote of at least four members of a live-member board. The Planning Board makes the following findings as required by the North Andover Zolzitig Bylaws Sections 8.1, 8.3, 10.3 and 10.31: PINDIENGS OF PACT 1) The specific Site is an appropriate location for such a use, structure,or condition. 2) The use as developed will not adversely affect the neighborhood. 3) There will be,no nuisance or serious hazard to vehicles or pedestrians. 4) Adequate and appropriate facilities will be provided for the proper operation of the proposed use. 1 5) The Planning Board makes a specific finding that the use is in harmony with the general purpose and intent of the North Andover Zoning Bylaw. 6) The proposed prof cot is a result of discussions with the Planning Board,Torun Departments, � Applicant and outside consultant with respect to parking, site design,grading,and stozmwater management. 7) The site drainage system and stornwater management design are designed in accordance with the Town Bylaw requirements and Best Management Practices,and the most recent version of the MA DEP Stormwater Handbook, and has been reviewed by the outside consulting engineer,Eggleston Environmental. (See email from L.Bggleston dated November 22,2016.) 8) There is approximately 84,122 square feet of gross floor area in the three buildings,the required parking spaces per the North Andover Zoning Bylaw are 378 parking spaces, There are currently 259 parking spaces at the Site.The Site is a znix of medical and other office use,the medical use exceeds all other Uses at the Site, 9) The proposed nine(9)parking spaces will be dedicated as employee parking only. 10) The Hire Department has reviewed the Plan and has stated that although the proposed parking spaces are within the roadway casement the roadway as constructed currently does not provide the fire apparatus with sufficient turning radius. They presently need to back the apparatus up from that point on Hillside Road to either the entrance/exit of the Chestnut Green Complex or to Bucklln Road off of Hillside Road.Therefore,the additional proposed parking spaces will not impede Tire response to this complex. (See memo from Lt.Robert Bonenfant dated November 29,2016.) Site Plan Review Special Permit 555-575 Turnpike street—Chestnut Green Condominium Page 2 of 7 January 17,2017 11)The Department of Public Works has reviewed the projeet and finds that all of the proposed parking spaces are located within roadway easement area but off of the existing edge of the pavement. Since the proposed spaces are located completely off of the existing edge of pavement,the DPW does not have any concerns with the proposed parking layout, (See memo from John Borgesi,Town Engineer, dated November 30,2016) 12)There is no deeded casement to the Town of North Andover for access to the existing roadway easement area, as identified on the submitted"Site Development Plan of Land"dated April 20,2015. The DPW recommends that a deeded easement to the Town of North Andover,for the area identified as "Roadway Easement"be developed to clarify the roadway easement access rights for all patties and the deeded easement be recorded at the Northern Essex Registry of Deeds. (See memo from John Borgesi,Town Engineer,dated November 30,2016.) WAIWI RS 13) 8.3,5 (e)(i):North Arrow/Location Map: A north arrow and a-location map showing surrounding roadways and land use adjacent to the site.Location map should show at least one intersection of two existing Town roadways.This requirement is waived as the project site is bounded by three streets. 14) 8.3.5 (c)(iv):Name/Description of Project:The name of development and the names,addresses and telephone numbers of the project tenants,land uses,development pleases, or other pertinent information necessary to evaluate the proposed development plan.This requirement is waived because the tenants and telephone numbers is extensive as they are condominium units. The Condominium Association is listed and the information of the development and proposed construction is in the projectnarxative, resent d proposed to o ra h of the site utilizin two foot contour 15) $.3.5 (e)(v):Topography:Thep an p p p g p y , g intervals.Existing topography fifty feet beyond the perimeter of the parcel as it appears on the most current Town of North Andover topographic mapping shall also be shown.This requirement is i waived as the plan shows the proposed and existing topography in the proposed construction site only. 16) 83 S(e){vi): Zoning Information; All applicable Zoning Bylaw information shall be provided regarding the site's development. This information shall be placed in a table and list all the parking, setbacks,percent of lot coverage,floor-area-ratio,number of dwelling units, total amount of square feet, size of signs, and any tither applicable zoning information necessary for proper review of the site plan by the Town Planner and Planning Board.This requirement is waived as there are no new buildings proposed and only an additional trine parking spaces are involved in the application. 1.7) 8.3,5(e)(viii): Stormwater Management Plan: All applications for Site Plan Review shall include the submittal of a Stormwater Management Plan prepared in accordance with the latest version of the Massachusetts Stormwater Handbook and additional criteria established herein and demonstrating full compliance with the Massachusetts Stormwater Standards and the North Andover Stormwater Management and Erosion Control Regulations promulgated under Chapter 160 of the Town Bylaws. This requirement is waived as the stormwater calculations and design are provided for the nine parking spaces,using porous pavement with no increase in rate of runoff or volume of runoff. 18) $.3.5(e)(ix):Building Location: Identification of all existing and proposed structure(s) located on the site.The number of stories,overall height in feet and gross floor area in square feet of all structure shall be indicated, This requirement is waived as there are no proposed buildings for construction. Site Plan Review Special Permit 555-575 Turnpiko Strect--Chestnut Green Condominium Page 3 of 7 January 17,2017 I i 19) 8.3 6(e)(x):Building 1116vation:A drawing of the exterior of the building,as viewed from the front (street view)must be submitted.The Planning Board may request rear views if relevant to the Board's review.This requirement is waived as there is no building proposed to be built. t i 20) $.3.5(e){xiii}: Location of Walls/Signs: Identification of the location,height and materials to be used for all retaining walls and signs located on the site.This requirement is waived as no signs are proposed or will be impacted by the proposed nine parking spaces.The proposed retaining wall is shown on the plans. 21) 8.3.5(e)(xvi):Landscaping Plan:Identification of the location and landscape schedule of all perimeter I and interior landscaping,including but not limited to proposed paving materials for walkways, fences, ' stonewalls and all planting materials to be placed on the site.In addition,all existing trees over 12 inches DBH,to be saved or removed shall be shown on the site plan.Ally landscaping required by the Town Bylaws shall be indicated on the site plan in tabular form showing the amount required and the amount provided.This requirement is waived as landscaping is provided only in the area of the nine parking spaces and not the entire site as a whole. 22) 8.15(e)(xvii): Refuse Areas: Identification of the location of each outdoor refuse storage area, I including the method of storage and screening.All refuse areas must be fully enclosed.This � requirement is waived.since no new buildings are proposed and the proposed parking spaces do not impact any of the refOsefdtimpster areas. j 23) 8.3.5(e)(xviii): Lighting Facilities:Identification of the proposed illumination,indicating the direction and the degree of illumination offered by the proposed lighting facilities,including an example of the light fixture to be used.This requirement is waived since no impact to the existing lighting is j proposed. 24) 8.3.5(e)(xx): Traffic Impact Study: Identification of existing traffic levels,along with the expected traffic impacts to occur based upon the proposed project.Projects which access state highways, a i traffic impact study shall be filed with MEPA concurrently with the Planning Board review.This requirement is waived as the proposal is to add nine parking spaces to alleviate overcrowding in the existing developed parking lot. i 25) 8.3.5(e)(xxii)Utilities: All utilities,including water line locations,sewer Iine locations and profiles, and storm drainage systems.This requirement is waived as construction is limited to 24"below the street elevation and no utilities otherwise are servicing the building in this project area. 26) 8.3.5(e)(xxiii):Fiscal Impact:Projections of costs rising from increased demand for public services and infrastructurc;provisions of benefits from increased tax revenues,employment and infrastructure improvements;and impacts on adjacent property values.The requirement is waived as nine parking spaces will not impact tax revenues. ' 27) $ 3.5{e}(xxtv): Community Impact:Analysis of the proi cots impact on the surrounding neighborhood � in terms of architectural consistency, pedestrian movement and overall character;impacts on nearby historic structures or site; and an evaluation of the proposed projects consistency and compatibility with existing local and regional plans.This requirement is waived as the project will not impact the neighborhood or architectural consistency of the area since no buildings are proposed. Site Plan Review Special Permit 555-575 Turnpike Street—Chestnut areen Condominium Page 4 of 7 January 17,2017 E I Finally, the Planning Board finds that this Project generally complies with the Town of North Andover Zoning Bylaw requirements as listed in Sections 8.1, 8.3, 10.3 and 10.31, but requires conditions in order to be fully in compliance. The Planning Board hereby grants an approval to the Applicant provided the following conditions are met'. PRRMIT AEIC+INUI;ONS 28)The "Locus" refers to the approximately 4.8 acre parcel at 555-575 Turnpike Street, referenced on Assessor's Map 25,Parcel 11, 69, 7L 29)The"Plans"refer to the plans entitled"Site Development Plan of hand in North Andover,MA prepared for Property Management of Andover",prepared by Merrimack Engineering Services,dated April 20, 2016. 30) The "Project" refers to the construction of nine (9) parking spaces and associated stormwater management in the Business 4 (B-4)Zone. 31) The "Applicant" refers to Chestnut Green Condominium Association, the applicant for the Site Plan Review Special Permit, 32)The "Project Owner" refers to the person or entity bolding the fee interest to tine title to the Locus, which can include but is not limited to the Applicant,developer,and/or owner. SPECIAL CONDITIONS Upon reaching the above findings,the Planning Board approves this Site Plan Review Special Pernlit with the following conditions; E 33)Tile parking spaces shall be assigned for employees only and signage shall be erected to indicate that these spaces are reserved for employees only,The intent of the assigned parking spaces is to minimize constant turnover in these spaces, and the Site area in particular,for the benefit of the neighborhood. 34)The Applicant shall convey an easement in the parking area,to be reviewed by Town Counsel, and that the easement must be accepted by the Board of Selectmen and recorded with the Registry of Deeds.The Applicant shall provide the Planning Department with two copies of the recorded documents. 35) The use of coal tar-based pavement sealants is prohibited. 36)No mature trees shall be removed. 37) Snow stockpiling for the Site shall not occur at the end of Ili]]side.Road or hi the area around the mature trees to the left of the new parking spaces.A"No Snow Stockpiling"sign shall be placed in the area of the trees. 38) Trees shall be protected from road salt,sodium chloride, or other de-icing Chemicals. 39)All appropriate measures should be taken to protect the trees on the Site and the owner shall maintain the trees in perpetuity, 40) The Applicant will provide landscaping between the retaining wall and the sidewalk and the sidewalk and the building in offorts to preserve green space. Site Plan Review Special Permit 555 575`l'umlAo Street—Chestnut Crreea Condoininiurn Page 5 of 7 January 17,2017 I 41) The Applicant shall monitor the pavement to ensure water drainage, debris accumulation,and surface deterioration.A vacuum sweeper shall be used annually to remove sediment and organic debris on the pavement surface.An Operations and Maintenance Plan with these conditions shall be established and submitted to the Planning Department. PRIOR TO A BUIELDING PERMIT OR SITE WORK/CONSTRUCTION 42)The Basement, Plans and this Notice of Decision must be recorded at the Essex North Registry of Deeds. Two (2) copies of the signed and recorded Plans and Notice of Decision must be delivered to the Planning Department. 43)A Performance Guarantee bond in the amount of five thousand($5,000)shall be posted for the purposes of ensuring that the site is constructed in accordance with the approved plaits and that a-filial as-built plan is provided. 44)A construction schedule shall be submitted to the Planning Department for the purposes of tracking major milestones and general construction. 45)A pre-construction meeting must be held with the Applicant,contractors,Mining Department, and i any other applicable representatives to discuss scheduling of inspections,points of contact,and major milestones.At this same meeting,the activities for Special Conditions 45 and 46 below may also be conducted. iI 46) Yellow"Caution"tape must be placed along the limit of clearing and grading as shown ott the Plan. I The Planning Department must be contacted prior to any initial cutting and/or clearing on-site. Existing trees that will remain in the landscaped area are to be marked. 47) All applicable erosion control measures must be in place, reviewed,and approved by the Planning Department. DURING CONSTRUCTION 48)Any stockpiling of materials must be maintained using all relevant Best Management Practices (BMPs)including covering of loose stockpiles and/or implementing dust mitigation measures. 49)It shall be,the responsibility of the Applicant to ensure that no erosion from the site of construction shall occur which will cause the deposition of soil or sediment upon adjacent properties or public 3 ways,except as normally ancillary to off-site sewer or other off site construction. Off-site erosion will be a basis for the Planning Board to snake a finding that the project is not in compliance with the Special Permit, and the Board shall give the developer written notice of any such finding and provide three(3)days to implement corrective actions. i 50)hi an effort to reduce noise lovels,the developer shall peep in optimum working order,through regular maintenance, any and all equipment that shall emanate sounds from the construction site. 51)Hours of construction are limited from 7:00am to 5:00prn Monday through Friday,and from 8:00am to 5:00pm on Saturdays, PRIOR TO THE RELEASE OF, SECURITY AND/Olt ESCROWED FUNDS 52) The.Applicant must submit a letter from the architect and/or engineer of the project stating that the site layout complies with the approved Plans. i Site Plan Review Special Permit 555-575 Turnpike Street-_Chestnut Green Condominium Page,6 of January 17,2017 I 53)All slopes must be stabilized with regard to crosion and safety. 54)The Planning Board reserves the right to review the site after construction is complete and require additional site screening as it deems necessary and reasonable, 55)All stornrwater structures shall be cleaned in accordance with the approved Storrawater Operation& Maintenance Plan, 56)A final set of as-built plans showing final topography, location of utilities,stir►otures,curb cuts, parking spaces, drainage facilities, and easements must be submitted to the Planning Department for on-site verification. Plans shall show all relevant site elcnnents including, but not limited to, stormwater infrastructure,Iandscaping, building footprints, impervious and pervious surface area, sewer and water connections,and other pertinent site features. One full size paper copy and one electronic copy(TIFF format)shall be submitted to the Planning Depar-ftnent, 57)The Planning Board must, by a majority vote,make a finding that the site is in conformance with the approved Plans. GENET RA-L CONDITIONS 58)The contractor shall contact Dig Safe at least 72 hours prior to coinnrencing any excavation. 59) Gas,telephone,cable,and electric utilities shall be installed underground as specified by the respective utility company, 60)The provisions of this conditional approval shall apply to and be binding upon the Applicant,its employees,and all successors and assigns in interest or control. 61) Any action by a Town Board, Cornrnission,or Department which requires a change in the plan or design of this proposal as presented to the Planning Board may require the Applicant to return to the Planning Board to modify this Site Plan Review Special Permit,as deemed necessary by the Planning Director. 62)Pursuant to the North Andover Zoning Bylaw Section 10.31.3 this Site Plan Review Special Permit shall be deemed to have lapsed after January 3, 2019 (two years from the date the permit is granted), exclusive of the time required to pursue or await determination of any appeals,unless substantial use or construction has commenced within said two-year period or for good cause as determined by the Plaiming Board. 63) The following shall be deemed part of this decision: PLANS: Site Development Plan of Land in North Andover,MA prepared for Property Management of Andover PLAN SIMETS: I PREPARED FOR: Property Management of Andover P.O.Box 488 Andover,MA 01810 PREPARED BY: Merrimack Engineering Services 66 Parr Street Andover,MA 01810 DATE: April20, 2015 Site Plan Review Special Permit 555-575 Turnpike Street--Chasfnut Green Condominium Page 7 of 7 January 17,2017