Notice Of Decision
Any appeal shall be filed
Within (20) days after the
Date of fling this Notice ;
In the Office of the Town
Clerk
L
Date: April 3, 2002 j>
Date of Hearing: March 26,2002 !j
Petition of: Falcon Air Inc., P.O. Box 995 492 Sutton St. North Andover, MA 01845 '
Premises Affected: 492 Sutton Street
Referring to the above petition for a special permit from the requirements of the North
Andover Zoning Bylaw Section 8.3 and 10.3.
So as to allow: the construction of a metal hangar building of 5,920 sq. ft. within the I-2
Zoning District
After a public hearing given on the above date, the PIanning Board voted to APPROVE,
the Special Permit for Site Plan Review, based upon the following conditions:
Signed:
J n Si us, Chairman
Cc: Applicant A erto Angles, Vice Chairman
Engineer Richard Nardella, Clerk
Abutters Felipe Schwarz
DPW George White
Building Department
Conservation Department
Health Department
ZBA
BOARD OF APPEALS 688-9541 BLULDING 688-9545 CONSERNFAT10N 688-9530 Mil L.TH 688-9540 PLANNING 688-9535
Site Plan Review - Special Permit
492 Sutton Street-Falcon Air
The Planning Board herein approves the Special Permit/Site Plan Review for the construction of a
metal building of 5,920 square foot within the Industrial-2 Zoning District: This Special Permit
was requested by Falcon Air, Inc P.O. Box 995 492 Sutton Street North Andover, MA 01845.
This application was filed with the Planning Board on February 7, 2002. The applicant
submitted a complete application which was noticed and reviewed in accordance with Sections
8.3, 10.3, and 10.31 of the Town of North Andover Zoning Bylaw and MGL c.40A, sec. 9.
The Planning Board makes the following findings as required by the North Andover Zoning
Bylaws Section 8.3 and 10.3:
FINDINGS OF FACT:
1. The use as developed will not adversely affect the neighborhood, as the hangar will not be
visible from adjacent streets or residents. The closest property line is approximately 400'
from the hangar where the adjacent use is commercial. The nearest residence is
approximately 1300' from the hangar.
2. The hangar will not generate any new vehicular or pedestrian traffic.
3. The existing conditions of the site are currently paved, as such no increase in runoff rates or
volume will occur.
4. The applicant has met the requirements of the Town for Site Plan Review as stated in Section
8.3 of the Zoning Bylaw.
Finally the Planning Board finds that this project generally complies with the Town of North
Andover Zoning Bylaw requirements as listed in Section 8.35 but requires conditions in order to
be fully in compliance. The Planning Board hereby grants an approval to the applicant provided
the following conditions are met:
SPECIAL CONDITIONS:
1. Prior to the endorsement of the plans by the Planning Board, the applicant must
comply with the following conditions:
a) A bond in the amount of one thousand ($1,000) dollars in the form of a check
must be posted for the purpose of insuring that a final as-built plan showing the
location of all on-site utilities, structures, curb cuts, parking spaces, topography,
and drainage facilities is submitted. The bond is also in place to insure that the
site is constructed in accordance with the approved plan. The form of security
must be acceptable to the Planning Board.
b) The applicant must receive approval from the Zoning Board of Appeals for the
allowed use of a hangar within the I-2 District and for setback requirements. The
applicant must provide to the Planning Department copy of all approvals.
2. Prior to the start of construction:
a) During construction, the site must be kept clean and swept regularly.
1
b) A construction schedule shall be submitted to the Planning Staff for the purpose
of tracking the construction and informing the public of anticipated activities on
the site.
3. Prior to Building Permit Issuance:
a) The Planning Board must endorse the final site plan mylars and three (3) copies of
the signed plans must be delivered to the Planning Department.
b) One certified copy of the recorded decision must be submitted to the Planning
Department.
4. Prior to issuance of the Certificate of Occupancy:
a) The applicant must submit a letter from the architect and engineer of the project
stating that the building, signs, landscaping, lighting and site layout substantially
comply with the plans referenced at the end of this decision as endorsed by the
Planning Board.
b) The aircraft hangar must comply with applicable state fire and building codes.
5. Prior to the final release of security:
a) The Planning Staff shall review the site. Any screening as may be reasonably
required by the Planning Staff will be added at the applicant's expense.
b) A final as-built plan showing final topography, the location of all on- site
utilities, structures, curb cuts, parking spaces and drainage facilities must be
submitted to and reviewed by the Planning Staff and the Division of Public
Works.
6. Any stockpiling of materials (dirt, wood, construction material, etc.) must be shown on a
plan and reviewed and approved by the Planning Staff. Any approved piles must remain
covered at all times to minimize any dust problems that may occur with adjacent
properties. Any stockpiles to remain for longer than one week must be fenced off and
covered.
7. The hours for construction shall be limited to between 7:00 a.m. and 5:00 p.m. Monday
through Friday and between 8:00 a.m. and 5:00 p.m. on Saturday.
8. The contractor shall contact Dig Safe at least 72 hours prior to commencing any
excavation,
9. Gas,Telephone,Cable and Electric utilities shall be installed underground as specified by
the respective utility companies.
10. No open burning shall be done except as is permitted during burning season under the
Fire Department regulations.
11. No underground fuel storage shall be installed except as may be allowed by Town
Regulations.
2
12. The provisions of this conditional approval shall apply to and be binding upon the
applicant, its employees and all successors and assigns in interest or control.
13. Any action by a Town Board, Commission, or Department, which requires changes in the
plan or design of the building, as presented to the Planning Board, may be subject to
modification by the Planning Board.
14. Any revisions shall be submitted to the Town Planner for review. If these revisions are
deemed substantial, the applicant must submit revised plans to the Planning Board for
approval.
15. This Special Permit approval shall be deemed to have lapsed April 3, 2004 (two years
from the date permit granted) unless substantial use or construction has commenced.
Substantial use or construction will be determined by a majority vote of the Planning
Board.
16. The following information shall be deemed part of the decision:
Plan Titled: Site Plan Falcon Air,Inc
Located at Lawrence Municipal Airport
North Andover,Mass.
Prepared For: Falcon Air,Inc
Prepared By: Andover consultants, inc.
I East River Place
Methuen,MA 01844
Scale: 1"=20'
Date: February 5, 2002
cc: Applicant
Engineer
File
3