HomeMy WebLinkAbout25 Cranberry Lane - NACC #309 Small Project - Permits #NACC #309 - 25 CRANBERRY LANE 7/26/2023 CONSERVATION DEPARTMENT
Community & Economic Development Division
John Hirschfeld
25 Cranberry Lane
North Andover, ILIA 01845 July 27, 2023
25 Cranberry Lane, North Andover
In-Kind .Deck Replacement
Conservation Conditions of Approval,NACC #309
Pursuant to section 4.4.2 of the North Andover Wetlands Protection Regulations,
Nick Boucher, on behalf of the homeowner, filed for a Small Project permit application for work
proposed at 25 Cranberry Lane,North Andover. The work involves: in the exact same footprint
replace the deck boards, railings, stair furring, and footing replacement is allowed if necessary. '1Thc
existing stairs are the closest to the wetland at 53 feet. A dumpster shall be stored on the paved
driveway.
During the July 26, 2023 public mcetuzg, the North Andover Conservation Con n.ission ACC
found this project to qualify as t Small Pro ec.t Permit and voted unanimously to approve this
project as proposed under (,rrte�a)y `73"Ia-,>?kl rep4(tce)Llerrt a�lcrry r�l����:xirting dcek� i�g�zrrlle,.rs of side
snb'ect to coin liaxxce with tle conditions listed lrelo�v. The project is approved only as it
relates to the Conservation Comnussion and any and all other approvals should be obtained by the;
applicant/homeowner.
All work shall conform to the following:
RECORD DOCUMENTS: Small Project Piling Including:
Application Checklist with supporting narrative and
attachments, received 07-19-23
Annotated Aerial Map
As-Built Plan
The following,conditions are hereby inandated:
CONDITIONS:
1. Prior to work commencing, the homeowner: shall have an 8" diameter straw wattle sock
installed between the deck and wetland (in the lawn area so as to allow enough room for the
contractor to maneuver within the work area but still fully envelope the work to properly
protect the wetland) and schedule an on--site pre-construction erecting with the contractor
and the Conservation Department to inspect installation and review the scope of work and
conditions of this approval.
25 Cranberry Lane—Small project permit Approval Category B
Page 1 of 2
2. If footings need to be replaced, the contractor sliall inform the Conservation Departinent as
to style of footings, rneans and methods of installation and ,in), excess soil shall be removed
from site and disposed of properly.
3. Post-construction inspection shall be scheduled with the Conservation Department to verify
cOrYiplialicc and approve removal of the inulch sock.
4. This permit shall expire otit-year.,from the date of issuance.
The applicant, homeowner and their contractors are advised that NO other work on the prope
rty
is allowed under this permit. The NACC has jurisdiction overall of the wetlands and associated
100-Foot buffer zones and 200 Riverfront urea to thc Shawsheen River on site and anv work
that involves ground disturbance or changing the current conditions in these areas will requirc
Vcr—lnftt Ln t.are not Limited to, house addifions,,.I?-Q-01-113.piti(.)S
decks, sheds, feric ge i
98 -installation tree or
vegetation cutting/ tuning. These activities shall be held to the current standards Linder the 11�Ixsv
and VXTPA.**
Should you have any question or comments.regarding the contents of this letter, please do not
hesitate to contact the undersigned at 978.688.9530. 'I'liank you for your anticipated cooperation
with this matter.
Respectfully,
N TH ANDOVER CONSERVATION DEPARTMENT
Ti-,
Amy R. M ner
lie
Conservation Adininistrator
25 Cranberry Lane-Stmall Project Permit Approval Category B
Page 2 of 2