HomeMy WebLinkAbout2023-04-26 Middle School Building Committee Minutes Middle School Building Committee
Meeting Minutes
April 26, 2023
Present: Laurie Burzlaff,Jennifer Cronan arrived 4:18 pm,Stephen Foster,Jorge Goncalves,Joseph Hicks,Janice
Phillips
Owners Project Manager, Derek Osterman of Colliers,Architect Adolfo Cuevas of Mount Vernon Group and Mount
Vernon Group Project Manager, Bill Peters and Mount Vernon Group Principal
Jim Emmanuel—landscape architect
Meeting was called to order by Committee Chair Laurie Burzlaff at 4:03 p.m.
No public comment
Approval of Minutes
Approval of minutes of March 14,2023 meeting
April 5t"2023 meeting
Motion made by joe hicks second by steve foster 5-0 vote
Landscape plan
Plan 1
Jim Emmanuel presented 2 different landscaping plans
One with a full court basketball court—near the enclosure
Very shoe horned in
Problems with possibly being close to freezer—freezer may be able to be moved
Plan 2
Half Court
Away from building
More planting
Still have 4 square area
Mr. Goncalves asked about a more straight path increasing the amount of asphalt
This area has more asphalt than current
Motion made by Joe Hicks to accept site plan option 2
Second—Steve Foster
5-0 in favor of option 2
Utility Incentives
Al MOU in process with National Grid that it is ok to study it
Different than what was originally discussed
3 pathways for heating
We may or may not qualify for rebates that is over and above this process
Bid specifications
Bill Peters and Al Cuevas went over plan revisions
Fire separation doors
Univent,carpeting,flooring through whole building
There is work in each part of the building
Carpeting in auditorium,curtain, handicapped lift for stage, lighting
Total classroom addition on second floor
Need ceiling space for duct work—drop 6 inches
Phasing option 1—
Kids on one side,construction on other side of wing
Will need to be this way in symmes
Plan 2—construction in whole wing,students put in different wing
Joe hicks made motion to approve phasing option 2 as presented in diagram
Second by Steve Foster
6-0 vote
Bid Timeline
Currently in prequalification
Qualifications were due on 4/26 am
9 subs per
10 GCs
Elevators will have to go out to bid again
Dates are outlined in the bid materials
Will set date as close to 7/1 as possible
We need to be open to different phasing if there are better choices when the time comes
Town Meetine
3 slides dedicated to this in CIP at Town Meeting
Bill Peters suggested a 3D image of what building will look like
Colored landscape plan
First and second floor plan—will shrink to one slide and color them
Invoices
Mt.Vernon Group
OPM—Colliers
Online hosting site—bid docs online
Motion by Joe Hicks for invoices
Jen Cronan 2"d
6-0 vote
Adjourment
Motion to adjourn made by Janice
Second Steve Foster
6-0 Vote
MEETING MATERIALS:
Landscape plan
Bid materials