December 6, 2021
Ms. Jean Enright, Planning Director
Planning Department
Town of North Andover
120 Main Street
North Andover, Massachusetts 01845
Ref: Stormwater Peer Review
Modifications to 505 Sutton Street
North Andover, Massachusetts
Dear Ms. Enright and Board Members:
The Horsley Witten Group, Inc. (HW) is pleased to provide the North Andover Planning Board
with this letter report summarizing our peer review of the modifications to the Stormwater
Management Report and Site Plans for the proposed development at 505 Sutton Street, North
Andover, MA. The plans were prepared for Sutton Street redevelopment, LLC (Applicant) by
The Morin-Cameron Group, Inc. HW understands that the Applicant is proposing to construct
three multifamily residential buildings and associated surface and underground parking,
landscaping improvements, a stormwater management system and new utility infrastructure on
a 5.10-acre parcel. The south and eastern portions of the site are currently undeveloped. There
are no wetlands on-site, however at the south side of the site there is a buffer zone that is
associated with an isolated wetland that is located off-site. j
The following documents and plans associated with the modified stormwater system and
prepared by The Morin-Cameron Group, Inc were received electronically by HW:
• Letter to North Andover Planning Department, regarding Summary of Site Plan Updates,
dated November 10, 2021 (5 pages).
• Stormwater Management Summary, 505 Sutton Street— Multi-Family Site Development,
dated November 10, 2021 (2 pages).
• HydroCAD Model —505 Sutton Proposed Conditions Hydrologic Analysis Final, Printed
10/12/2021 (72 pages).
• Proposed Watershed Plan at 505 Sutton Street, North Andover, Massachusetts (1 Sheet).
• Redlined Permit Plans, Dated May 16, 2019, revised through January 31, 2020 (13 sheets),
• Multifamily Site Development Plans, 505 Sutton Street, North Andover, Massachusetts,
prepared by The Morin-Cameron Group, Inc., dated May 28, 2021, revised October 27,
2021, which include:
o Cover Sheet C.1
o Existing Conditions Plan C.2
o Demolition Plan C.3.A
Erosion & Sediment Control Plan C.3.B
(r+)Hors IeyWittenCroup Horsley Witten Group, Inc.
Town of North Andover
December 6, 2021
Page 2 of 2
o Site Layout Plan CA
o Overall Grading Plan C.5.A
o Grading & Drainage Plan C.5.13
o Utility Plan C.6
o Construction Details I C.8
o Construction Details 11 C.9
o Construction Details III C.10
o Construction Details IV CA I
o Construction Details V C.12
o Construction Details V1 C.13
Modified Stormwater Design Peer Review
The Applicant has made several changes to the site plans for various reasons detailed in its
Summary of Site Plan Updates letter. HW has reviewed the changes to the stormwater design
and has the following comments:
1. The Applicant has illustrated the perimeter drains that are capturing and directing the
roof runoff to the subsurface Retain It systems. The roof drain piping is located around
each building, HW recommends that clean outs are proposed at the northeast corner of
Building 1, the southeast corner of Building 2, and the southwest corner of Building 3.
2. The Applicant has eliminated the originally proposed CDS units and replaced catch
basin 2 and 3 with Stormceptor 450i units. HW recommends that the CDS units be
returned to the design and that the Applicant eliminate the catch basin to catch basin
configuration where feasible.
Conclusions
With the minor adjustments suggested, HW agrees that the proposed stormwater design is
equivalent to the approved design. Please contact Janet Bernardo at 508-833-6600 or at
jbernardo@horsleywitten.com if you have any questions regarding these comments.
Sincerely,
HORSLEY WITTEN GROUP, INC.
Janet Carter Bernardo, P.E.
Associate Principal
K:1Projects12013U8065 N Andover On-Cal M806511 505 Sutton S4-cet\Reports1211205 I'eerReview nwdirccalions 505 Sutton Yreet,docx
The M6rin-Cameron
. .............
I H
r
December 14, 2021
Ms, Jean Enright, Planning Director
Planning Department
Town of North Andover
120 Main Street
North Andover, MA 01845
RE: Response to Peer Review„Comments
Modifications to 505 Sutton Street
North Andover, Massachusetts
Dear Ms. Enright:
On behalf of Sutton Street Redevelopment, LLC (Owner), The Morin-Cameron Group, Inc. (MCG)
prepared this response letter to the peer review comments provided by the Horsley Witten Group,
Inc. (HW) in their letter dated December 6, 2021.The original HW comments are included below,
with the MCG responses following each comment.
Modified Stormwater Design Peer Review:
3
1. HW Comment: The Applicant has illustrated the perimeter drains that are capturing and
directing the roof runoff to the subsurface Retain It systems The roof drain piping is
located around each building. HW recommends that clean outs are proposed at the
northeast corner of Building 1, the southeast corner of Building 2, and the southwest corner
of Building 3.
MCG Response:The clean-outs described above will be added to the roof drain pipe
network in the locations suggested.
2. HW Comment: The Applicant has eliminated the originally proposed CDS units and
replaced catch basin 2 and 3 with Stormceptor450i units. HW recommends that the CDS
units be returned to the design and that the Applicant eliminate the catch basin to catch
basin configuration where feasible.
MCG Response: Following a detailed review and discussion of this particular closed
drainage system, the use of 5tormceptor 450i units was recommended by Contech
Engineered Solutions (Contech),who recently added Stormceptor to its product offerings (it
was previously owned by a separate company). The drain pipe network in the vicinity of C8-
2 & C13-3 does not allow for separate treatment structures, because of the tight angles,
shallow cover depths and various underground utility services in those locations.
Considering these project constraints, MCG used its best engineering judgement and
CIVIL ENGINEERS • LAND SURVEYORS • ENVIRONMENTAL CONSULTANTS • LAND USE PLANNERS
25 Kenoza Avenue, Haverhill, MA 01830 978.373.0310
Providing Professional Services Since 1978
505 Sutton Street December 14, 2021
Response to Comments
simplified the design by specifying treatment structures with a combination of piped and
grated inlets, in the interest of improving both constructabiEity and long-term maintenance.
Based on the physical characteristics of Contech's treatment structures (e.g. Stormceptor,
CDS, Cascade), the TSS removal capacities are not dependent on whether runoff is
conveyed via pipe flow or a grated inlet, or a combination of the two, For the CDS units that
were originally proposed, It is necessary to use a deflector pan with grated inlets in order to
induce the desired vortex flow pattern, These deflector pans are not ideal in a shallow cover
Installation such as that required for CB-2, because they need to be attached to the
underside of the grates and can Interfere with the CDS internals. In this case, the
Stormceptor Is the ideal choice because if offers similar treatment capacities without the
need for a deflector pan.
MCG understands that MassDEP doesn't have a current approval process for these
proprietary stormwater units, which can be a challenge for design engineers. However,
Stormceptors have been used throughout the country for decades, and have a proven track
record of success. We verified with Contech that the historical testing performed on these
structures does not differentiate between piped inlets or grated inlets when rating the
performance. Provided they are installed per the design plans and corresponding
construction detail, all runoff entering them will be treated equally. As such, MCG remains
confident that the Stormceptor is the most appropriate choice for this application.
Finally, it is worth noting that both CB-2 and CB-3 convey runoff to subsurface infiltration
systems which are rated to provide at least 80% TSS removal on their own, when preceded
by adequate pretreatment measures.And there is also a high-capacity CDS unit specified
for installation at the very end of this project's closed drainage system, which will provide
additional treatment for any runoff that Is discharged from the infiltration system outlet
control devices.
In conclusion, MCG is confident that the final stormwater management system design is in
full compliance with the Massachusetts Stormwater Handbook in addition to all local
project approvals.
We trust that this supplemental information sufficiently addresses the Horsley-Witten Group
comments from their peer review of the modified stormwater design. Please contact the undersigned
at (978) 373- 310 should you have any questions or requests for additional information.
Sincerely,
THE MO -CAMERON GROUP, INC.
ott . ameron, P.E. Michael C. Laham, P.E.
Vice- resident Project Manager
Cc: Sutton Street Redevelopment, LLC
Horsley-Witten Group, Inc.
Page 2 of 2
12116121,8:04 AM Town of North Andover Mail-505 Sutton Street
N0 H.ANROVER
PAassaclfusGtts Jean Enright<jenright@northandoverma.gov>
T77
505 Sutton Street
2 messages
Jean Enright <jonright@northandoverma.gov> Wed, Dec 15, 2021 at 2:37 PM
To: Janet Bernardo <jernardo@horsleywitten.com>
Cc: Amy Maxner<amaxner@northandoverma.gov>, Michael Laham <Mike@morincameron.com>
Hi Janet,
I have attached Michael Laham's response to your Dec. 6 peer review letter. Please let us know your thoughts. Thank
you
Sincerely,
Jean Enright
Planning Director
Town of North Andover
120 Main Street
North Andover, MA 01845
Phone 978.688.9533
Fax 978.688,9542
Email: jenright@northandoverma,gov
Web: www.NorthAndoverMA.gov
L,p. cid:image001.jpg@010EOF52.F68A5980
211214 Resp Ltr to HW,pdf
976K
Janet Bernardo <jernardo@horsleywitten.com> Wed, Dec 15, 2021 at 3:49 PM
To: Jean Enright<jenright@northandoverma.gov>
Cc: Amy Maxner<amaxner@northandoverma.gov>, Michael Laham <Mike@morincameron.com>
Hi Jean,
The response from Michael Laham is acceptable to HW. We have no further recommendations.
Thanks, Janot
Janet Carter Bernardo, P.E.
'rsley Witten Group
857-263-8193
nmlinal llu/0/?Ik=7c2eff6265&view=pt&search=all&permthid=th read-a%3Ar8275896189030228798&sim pl=msg-a%3Ar-691969526... 112
12/16121,8:04 AM Town of North Andover Mail-505 Sutton Street
From: Jean Enright<jenright@ north andoverma,gov>
Sent: Wednesday, December 15, 2021 2:37 PM
To: Janet Bernardo <jernardo@horsleywitten,com>
Cc: Amy Maxner<amaxner@northandoverma.gov>; Michael Laham <Mi.ke c@morincameron.com>
Subject: 505 Sutton Street
Hi Janet,
have attached Michael Laham's response to your Dec. 6 peer review letter. Please let us know your thoughts. Thank
you
Sincerely,
Jean Enright
Planning Director
Town of North Andover
120 Main Street
North Andover, MA 01845
Phone 978.688.9533
Fax 978,688.9542
Email: jenright@northandoverma,gov
Web: www.NorthAndoverMA.gov
All email messages and attached content sent from and to this email account are public records unless qualified as an
exemption under the Massachusetts Public Records Law.
Visit us online at www.northwidoverrna.gov,
https:#mail.googio.com/maillu/0/?ik=7c2eff6265&view=pt&search=all&permthid=thread-a°/a3Ar8275896180030228798&simpl=msg-a%3Ar'