Notice Of Decision
Any appeal shall be filed
Within (20) days after the
Date of filing this Notice 7 CD
In the Office of the Town,, �'a�-a
Clerk " cra
ern—?yam
�
Date: April 9, 2001 10 70 un CD
Date of Hearing: February f�04-�`��
'
February 20, 2001, &April %,,�001
w
Petition of: Stephen and Cheryl Juba, 555 Salem Street, North Andover, MA 01845
Premises Affected: Wallace Street, North Andover, MA
Referring to the above petition for a Definitive Subdivision. The application was
determined to be complete and was noticed and reviewed in accordance with the
procedures for review and approval in accordance with the Rules and Regulations
Governing the Subdivision of Land and M.G.L. c. 41 (the "Subdivision Control Law").
So as to allow: for a one (1) lot subdivision with one new home known as Wallace Street
Definitive Plan.
After a public hearing given on the above date, the Planning Board voted to APPROVE,
the Definitive Subdivision, based upon the following conditiops:
Signed:
Alison Lescarbeau, Chairman
Cc: Applicant John Simons, Vice Chairman
Engineer Alberto Angles, Clerk
Abutters Richard Rowen
DPW Richard Nardella
Building Department
Conservation Department
Health Department
ZBA
BOARD OF APPEALS 688-9541 BUILDING 688-9545 CONSBRVATION 688.9534 BEr\I T11688-950 PLANNIlNG 688.9535
Wallace Street Definitive Subdivision
Conditional Approval
The Planning Board herein APPROVES the Definitive Subdivision for a one (1) lot
subdivision with one new home known as Wallace Street Definitive Plan. Stephen and
Cheryl Juba, 555 Salem Street, North Andover, MA 01845, submitted this application on
January 5, 2001. The area affected is on Wallace Street and is located in the R-3 Zoning
District
The Planning Board makes the following findings as required by Section 5.6 of the Town
of North Andover Rules and Regulations Governing the Subdivision of Land:
A. The Definitive Plan, dated January 3, 2000, revised March 20, 2001, is
complete and technically adequate.
B. The Definitive Plan has due regard for the provision of adequate access to all
of the lots in a subdivision by ways that will be safe and convenient for travel.
C. The Definitive Plan has been prepared to lessen congestion in such ways and
in the adjacent public ways.
D. The Definitive PIan reduces danger to life and limb in the operation of motor
vehicles. The new roadway will provide better traveling for the operation of
motor vehicles versus the current paper street .
E. The Definitive Plan secures safety in the case of fire, flood, panic and other
emergencies. The new roadway will provide better access for emergency
situations.
F. The Definitive Plan complies with the Town of North Andover Zoning By-
law. The lot in this subdivision is subject to Section 7.8, Exceptions of the
Town of North Andover Zoning Bylaw, as determined by the Building
Commissioner, Robert Nicetta, subject to the Planning Board granting access
by virtue of this subdivision approval (see attached letter dated February 2,
2001),
G. The Definitive Plan secures adequate provisions for water, sewerage,
drainage, underground utility services, fire, police and other similar municipal
equipment, and street lighting and other requirements where necessary in a
subdivision. The.Definitive Plan has been reviewed by the Department of
Public Works, and the Fire Department and has been found to be acceptable,
H. The Definitive Plan coordinates the ways in neighboring subdivisions. The
new roadway will enable future lots on the connecting paper streets to tie into
the roadway.
1. The Definitive Plan conforms with the design and construction standards
described in these Rules and Regulations and in the attached Appendices with
the exceptions of waivers granted in Condition 17.
J. The Definitive Plan conforms with all applicable zoning requirements, The
lot in this subdivision is subject to Section 7.8, Exceptions of the Town of
North Andover Zoning Bylaw, as determined by the Building Commissioner,
Robert Nicetta, subject to the Planning Board granting access by virtue of this
subdivision approval (see attached letter dated February 2, 2001),
Finally, the Planning Board finds that the Definitive Subdivision complies with Town
Bylaw requirements so long as the following conditions are complied with:
1) Environmental Monitor: The applicant shall designate an independent
environmental monitor who shall be chosen in consultant with the Planning Department.
The Environmental Monitor must be available upon four (4) hours' notice to inspect the
site with the Planning Board designated official. The Environmental Monitor shall
make weekly inspections of the project and file monthly reports to the Planning Board
throughout the duration of the project. The rr-ionthly reports shall detail area of non-
compliance, if any and actions taken to resolve these issues,
2) Prior to endorsement of the plans by the Planning Board the applicant shall adhere
to the following:
a) A Site Opening Bond in the amount of ten thousand ($10,000) dollars to be held
by the Town of North Andover. The Site Opening Bond shall be in the form of a
check made out to the Town of North Andover that will be placed into an interest
bearing escrow account:. A covenant (FORM 1) securing all lots within the
subdivision for the construction of ways and municipal services must be submitted
to the Planning Board. Said lots may be released from the covenant upon posting of
security as required in Condition 5(e).
b) The applicant must submit to the Town Planner a FORM M for all utilities and
easements placed on the subdivision.
c) All subdivision application fees must be paid in full and verified by the Town
Planner,
d) The applicant must meet with the Town Planner in order to ensure that the plans
conform to the Board's decision. A full set of final plans reflecting the changes
outlined in Jim Rand's (DPW) memorandum dated 3/20/01 must be submitted
to the Town Planner for review prior to endorsement by the Planning Board,.
The final plans ,,rust also reflect that the road be built a maximum of 50'; that
the grading for the proposed house cannot be within the right-of-way; and the
reconstructed driveway for the abutting property blend in with the line of the
existing driveway. These plans must be submitted within ninety (90) days of
filing the decision with the Town Clerk.
e) The Subdivision Decision for this project must appear on the.mylars.
A Development Schedule must be submitted for signature by the Planning
Board, which conforms to Section 8.7 of the North Andover Zoning Bylaw. The
schedule must shove building permit eligibility by quarter for all lots.
g) All documents shall be prepared at the expense of the applicant, as required by the
Planning Board Rules and Regulations Governing the Subdivision of Land.
3) Prior to ANY WORK on site:
a) Yellow "Caution" tape must be placed along the limit of clearing and
grading as shown on the plan. The Planning Staff must be contacted prior to
any cutting and or clearing on site.
b) All erosion control measures as shown on the plan and outlined in the
erosion control plan must be in place and reviewed by the Town Planner.
E
4) Throughout and During Construction:
a) Dust mitigation and roadway cleaning must be performed weekly, or as deemed
necessary by the Town Planner, throughout the construction process.
b) Street sweeping must be performed, at least once per month, throughout the
construction process, or more frequently as directed by the Town Planner.
c) Hours of operation during construction are limited from 7 a.m. to 5 p.m., Monday
through Friday and 8 a.m. —5 p.m. on Saturdays.
S) Prior to any lots being released from the statutory covenants:
a) Three (3) complete copies of the endorsed and recorded subdivision plans and one
(1) certified copy of the following documents: recorded subdivision approval,
recorded Covenant (FORM 1), recorded Growth Management Development
Schedule, and recorded FORM M must be submitted to the Town Planner as proof
of recording.
b) The applicant must submit a lot release FORM J to the Planning Board for
signature.
c) A Performance Guarantee in an amount to be determined by the Planning Board,
shall be posted to ensure completion of the work in accordance with the Plans
approved as part of this conditional approval. The bond must be in the form
acceptable to the North Andover Planning Board. Items covered by the Bond may
include, but shall not be limited to:
i) as-built drawings;
ii) sewers and utilities
iii) roadway construction and maintenance
iv) lot and site erosion control
v) site screening and street trees
vi)drainage facilities
vii)site restoration
viii)final site cleanup
6) Prior to Building Permit Issuance for an individual lot, the following information is
required by the Planning Department:
a) The applicant must submit a certified copy of the recorded FORM J referred to in
Condition 5(b) above.
F
b) A plot plan for the lot in question must be submitted, which includes all of the
following;
i) location of the structure,
ii) location of the driveways,
iii) location of the septic systems if applicable,
iv) location of all water and sewer lines,
v) location of wetlands and any site improvements required under a NACC order of
condition,
vi) any grading called for on the lot,
vii)all required zoning setbacks,
viii)Location of any drainage, utility and other easements.
c) All appropriate erosion control measures for the lot shall be in place. The Planning
Board or Staff shall make final determination of appropriate measures.
d) Lot numbers, visible from the roadways must be posted on all lots.
e) An as-built plan must be submitted to the Division of Public Works for review and
approval prior to acceptance of the sewer appurtenances for use.
f) The sewer ejector plans and specifications shall be reviewed by the Board of
Health.
g) The roadway must be constructed to at least binder coat of pavement to properly
access the lot in question. Prior to construction of the binder coat, the applicant shall
ensure that all required inspection and testing of water, sewer, and drainage facilities
has been completed. The applicant must submit to the Town Planner and the
Department of Public Works an interim as-built, certified by a professional engineer,
verifying that all utilities have been installed in accordance with the plans and profile
i
A sheet. The interim as-built plan shall be prepared in accordance with the definition
listed in Section 1.3.3 of the Town of North Andover Subdivision Regulations and
Section 5.14 of the Town of North Andover Subdivision Regulations.
i
h) Two driveway permits for the new lot and abutting lot be secured and all fees paid
for from the Department of Public Works, along with necessary sewer connection,
water connection, and sewer mitigation permits.
i) The applicant shall adhere to the following requirements of the North
Andover Fire Department and the North Andover Building Department:
1) All structures must contain a residential fire sprinkler system. The
plans and hydraulic calculations for each residential system shall be
submitted for review and approval by the North Andover Fire
Department. Plans and hydraulic calculations for each residential
system must also be supplied to the Building Department,
7) Prior to a Certificate of Occupancy being requested for an individual lot, the
following shall be required:
a) All necessary permits and approvals for the lot in question shall be obtained from the
North Andover Board of Health, and Conservation Commission.
b) The residential fire sprinkler system must be installed in accordance with
referenced standard NFPA 13D and in accordance with 780 CMR,
Chapter 9 of the Massachusetts State Building Code. Certification that the
system has been installed properly in accordance with the above referenced
regulations must be provided from both the North Andover Fire Department
and the North Andover Building Department to the applicant. The
applicant must then provide this certification to the North Andover
Planning Department.
b) Permanent house numbers midst be posted on dwellings and be visible from the road.
c) There shall be no driveways placed where stone bound monuments and/or catch
basins are to be set. It shall be the developer's responsibility to assure the propel`
placement of the driveways regardless of whether individual lots are sold. The
Planning Board requires any driveway to be moved at the owner's expense if such
driveway is at a catch basin or stone bound position.
d) If a sidewalk is to be constructed in front of the lot, then such sidewalk must be
graded and staked at a minimum.
e) The driveway for the abutting property must be completely constructed and
approved, through virtue of an inspection, by the Town Planner.
4�
8) Prior to the final release of security retained for the site by the Town, the following
shall be completed by the applicant:
a) An as-built plan and profile of the site shall be submitted to the DPW and Planning
Department for review and approval, in accordance with Section 5.14 of the Town
of North Andover Subdivision Rules and Regulations.
b) The applicant shall petition Town Meeting for public acceptance of the street in
accordance with Section 5.11 of the Town of North Andover Subdivision Rules and
Regulations. Prior to submitting a warrant for such petition the applicant shall
review the subdivision and all remaining work with the Town Planner and
Department of Public Works, The Planning Board shall hold a portion of the
subdivision bond for continued maintenance and operations until such time as Town
Meeting has accepted (or rejected in favor of private ownership) the roadways. It
shall be the developer's responsibility to insure that all proper easements have been
recorded at the Registry of Deeds.
9) The Applicant shall ensure that all Planning, Conservation Conunission, Board of
Health and Division of Public Works requirements are satisfied and that construction
was in strict compliance with all approved plans and conditions.
10)The applicant shall adhere to the following requirements of the Fire Department:
a) Open burning is allowed by permit only after consultation with the Fire Department.
b) Underground.fuel storage will be allowed in conformance with the Town Bylaws
and State Statute and only with the review and approval of the Fire Department and
Conservation Conunission.
11)There shall be no burying or dumping of construction material on site.
12)The location of any stump dumps on site must be pre-approved by the Planning Board.
13)The contractor shall contact Dig Safe at least 72 hours prior to commencing any
excavation.
14)Gas, Telephone, Cable, and Electric utilities shall be installed as specified by the
respective utility companies.
15)Any action by a Town Board, Commission, or Department which requires changes in
the roadway alignment, placement of any easements or utilities, drainage facilities,
grading or no cut lines, may be subject to modification by the Planning Board.
V
rA
16)The utilities must be installed and the streets or ways constructed to binder coat two
years from this approval. If the utilities are not installed, the streets or ways are not
constructed to binder coat and the Planning Board has not granted an extension by the
above referenced date, this definitive subdivision approval will be deemed to have
lapsed.
17) The following waiver's from the Rules and Regulations Governing the Subdivision
of Land, North Andover, Massachusetts, revised February 1989, have been GRANTED by
the Planning Board. These waivers have been granted because although technically the
submission of this proposal constitutes a subdivision, the proposed roadway construction
only involves 50' in length of roadway so as to gain the required frontage for the proposed
home. It does not involve the construction of a roadway that would be serving numerous
homes. Frirtherm'Dre, although waivers have been granted, the proposed roadway secures
adequate provisions for water, sewerage drainage, and required municipal services to
service the new home.
a) Waiver from Section 5.2.5.4, Street Plan and Profile has been granted.
b) Waiver from Section 5.2.6.c Soil Borings, has been granted.
c) Waiver from Section 5,2.6.d, closure calculations, has been granted.
d) Waiver from Section 5.3, Stormwater Management report, has been granted.
e) Waiver from Section 5.4, Environmental and Community Impact Statement, has
been granted,
f) Waiver from Section 6.8.1, pavement width, centerline grade, vertical curve,
turnaround, has been granted,
g) Waiver from Section 6.9, curbing, has been granted,
h) Waiver from Section 6.11, sidewalks, has been granted.
i) Waiver from Section 6.14, storm drainage, has been granted.
j) Waiver from Section 6.18, trees and other plantings, has been granted.
k) Waiver from Appendix I A.5, gravel sub-base, has been granted.
1) Waiver from Appendix I A.7, pavement, has been granted,
m) Waiver from Appendix IV, has been granted.
n) Waiver from Appendix V, Stormwater Management Regulations, has been.granted.
IS)This Definitive Subdivision Plan approval is based upon the following information
which is incorporated into this decision by reference:
Plan titled: Definitive Plan, "Wallace Street"
Located in
North Andover,Massachusetts
Dated: 1/3/2000 revised 3/20/01
Applicant: Stephen M. Juba III and Cheryl Juba
555 Salem Street
North Andover, MA 01845
Civil Engincer:Christiansen& Sergi
160 Summer Street
Haverhill,MA 01830
Sheets: 1 of 1
Scale: 1"=20'