HomeMy WebLinkAboutConstruction Schedule Home Grown Lacrosse-Terminal Road-North Andover MA 11-Mar-24 Project schedule-Preliminary Item Dates Description Building/Interior Work Site survey control March 4-8 Hancock Associates-completed 3/8 Foundation shop drawings March 5-28 Concrete mix,reinforcing steel,anchor rods Pre-construction site meeting March 12-13 Town planner,GC,site contractor,owner,engineer-3/12 Erosion protection March 11-22 Farmer site contractor Temporary gravel entrance&temp.parking March 18-28 Farmer site contractor Erosion control inspection March 25-28 Jean Enright,town planner Locate electric line&site prep March 18-28 Farmer site contractor Temporary power March 18-April 15 Electrician Strip loam&stockpile,subgrade March 26-29 Start sitework Layout foundation March 29-April 1 Hancock Associates Foundation/site contractor meeting March 29-April 1 Phases-foundation/site contractor meeting to plan out Found.shop drawings-conc.mix/rebar/bolts March 29-April 1 Submit to McBrie Dig frost walls April 1-5 Prep office area foundation first Sleeves under footing for water and sewer April 1-5 4"sewer service,4"water service,1"water service Pin foundation corners Hancock Associates Excavation inspection April 4-5 Footing&Foundation April 5-26 Confirm time. 3,000 psi. Sleeves for electrical needed?. Rebar inspection-footings&walls April 5-26 McBrie inspection Concrete testing&wall rebar inspection April 5-26 UTS. One set of tests/day or 150 cy and inspect wall rebar Pin footings April 5-26 Hancock Associates. Pin footings for wall location Foundation inspection April 25-26 As-built survey-foundation&utilities April 25-May 1 Hancock Associates Other sitework(included below in Exterior) March 26-April 26 Water,sewer,electric Backfill foundation and subgracle April 26-May 3 In phases. Determine curing time required before backfill. Underground plumbing/electrical April 26-May 3 Inside building Underground inspections-plumbing/elec. May 3-6 Prep for concrete floors May 6-8 Concrete floor mix shop drawing May 6-8 McBrie to review mix Concrete floor rebar inspection May 6-8 McBrie rebar inspection. UTS concrete testing optional Concrete floors May 8-10 4,000 psi Prep for turf May 6-10 Light gage metal engineering May 10-July 29 Submit shop drawings to McBrie Legacy-June 1-August 2(9 weeks) Legacy-shell June 1-28 Legacy-insulation July 1-12 Legacy-Interior liners July 15-26 Legacy-details July 29-Aug 2 Engineer inspection Windows and exterior doors-install July 29-Aug 2 Garage door-install July 29-Aug 2 Office frame,deck,stairs July 29-Aug 9 Confirm time. Engineer inspection Deck and stair railings Aug 9-22 HVAC,plumbing,electrical rough-in Aug 9-22 Fire sprinkler and alarm rough-in Aug 9-22 Start in fieldhouse Rough inspections Aug 23-26 Insulation Aug 26-30 Insulation inspection Aug 29-30 Sheet rock office/bathrooms&install doors Sept 3-10 Paint office/bathrooms Sept 10-20 Finish trim office/bathrooms Sept 18-20 Vinyl base Finishes-HVAC,electrical,plumbing Sept 20-30 Finishes-fire sprinkler,alarm Sept 20-30 Fieldhouse can start earlier Seal concrete floors and final clean Sept 27-30