HomeMy WebLinkAboutConstruction Schedule Home Grown Lacrosse-Terminal Road-North Andover MA 11-Mar-24
Project schedule-Preliminary
Item Dates Description
Building/Interior Work
Site survey control March 4-8 Hancock Associates-completed 3/8
Foundation shop drawings March 5-28 Concrete mix,reinforcing steel,anchor rods
Pre-construction site meeting March 12-13 Town planner,GC,site contractor,owner,engineer-3/12
Erosion protection March 11-22 Farmer site contractor
Temporary gravel entrance&temp.parking March 18-28 Farmer site contractor
Erosion control inspection March 25-28 Jean Enright,town planner
Locate electric line&site prep March 18-28 Farmer site contractor
Temporary power March 18-April 15 Electrician
Strip loam&stockpile,subgrade March 26-29 Start sitework
Layout foundation March 29-April 1 Hancock Associates
Foundation/site contractor meeting March 29-April 1 Phases-foundation/site contractor meeting to plan out
Found.shop drawings-conc.mix/rebar/bolts March 29-April 1 Submit to McBrie
Dig frost walls April 1-5 Prep office area foundation first
Sleeves under footing for water and sewer April 1-5 4"sewer service,4"water service,1"water service
Pin foundation corners Hancock Associates
Excavation inspection April 4-5
Footing&Foundation April 5-26 Confirm time. 3,000 psi. Sleeves for electrical needed?.
Rebar inspection-footings&walls April 5-26 McBrie inspection
Concrete testing&wall rebar inspection April 5-26 UTS. One set of tests/day or 150 cy and inspect wall rebar
Pin footings April 5-26 Hancock Associates. Pin footings for wall location
Foundation inspection April 25-26
As-built survey-foundation&utilities April 25-May 1 Hancock Associates
Other sitework(included below in Exterior) March 26-April 26 Water,sewer,electric
Backfill foundation and subgracle April 26-May 3 In phases. Determine curing time required before backfill.
Underground plumbing/electrical April 26-May 3 Inside building
Underground inspections-plumbing/elec. May 3-6
Prep for concrete floors May 6-8
Concrete floor mix shop drawing May 6-8 McBrie to review mix
Concrete floor rebar inspection May 6-8 McBrie rebar inspection. UTS concrete testing optional
Concrete floors May 8-10 4,000 psi
Prep for turf May 6-10
Light gage metal engineering May 10-July 29 Submit shop drawings to McBrie
Legacy-June 1-August 2(9 weeks)
Legacy-shell June 1-28
Legacy-insulation July 1-12
Legacy-Interior liners July 15-26
Legacy-details July 29-Aug 2 Engineer inspection
Windows and exterior doors-install July 29-Aug 2
Garage door-install July 29-Aug 2
Office frame,deck,stairs July 29-Aug 9 Confirm time. Engineer inspection
Deck and stair railings Aug 9-22
HVAC,plumbing,electrical rough-in Aug 9-22
Fire sprinkler and alarm rough-in Aug 9-22 Start in fieldhouse
Rough inspections Aug 23-26
Insulation Aug 26-30
Insulation inspection Aug 29-30
Sheet rock office/bathrooms&install doors Sept 3-10
Paint office/bathrooms Sept 10-20
Finish trim office/bathrooms Sept 18-20 Vinyl base
Finishes-HVAC,electrical,plumbing Sept 20-30
Finishes-fire sprinkler,alarm Sept 20-30 Fieldhouse can start earlier
Seal concrete floors and final clean Sept 27-30