HomeMy WebLinkAboutConstruction Schedule Heimlich Landscaping & Construction Corp.
North Andover High School Athletic Field Improvements
North Andover, MA
** weather permitting **
Activities Dates Notes
Erosion controls/Temp fencing
Site prep & demolition
Push up topsoil on baseball field July 1, 2025
Reclaim existing tennis courts
Begin sub grading
Begin install drainage
Begin installing concrete turf curb
Install binder pavement on tennis courts August 1, 2025
Install Musco light bases
Install fence posts on tennis courts
Install backstop at baseball field
Complete turf curb
Complete drainage Se tember 1 2025
Finish pave tennis courts p '
Complete fencing & net sleeves at tennis courts
Begin installing fabric & base stone
Sealcoat tennis courts
Install Musco lights
Install fencing at baseball field October 1, 2025
Install top finish stone on baseball field
Begin installing turf
Complete turf install
Complete fencing
Paving around baseball field November 1, 2025
Loam & seed
Complete all site furnishings
Complete all miscellaneous items December 1, 2025