HomeMy WebLinkAboutConstruction Schedule Heimlich Landscaping & Construction Corp. North Andover High School Athletic Field Improvements North Andover, MA ** weather permitting ** Activities Dates Notes Erosion controls/Temp fencing Site prep & demolition Push up topsoil on baseball field July 1, 2025 Reclaim existing tennis courts Begin sub grading Begin install drainage Begin installing concrete turf curb Install binder pavement on tennis courts August 1, 2025 Install Musco light bases Install fence posts on tennis courts Install backstop at baseball field Complete turf curb Complete drainage Se tember 1 2025 Finish pave tennis courts p ' Complete fencing & net sleeves at tennis courts Begin installing fabric & base stone Sealcoat tennis courts Install Musco lights Install fencing at baseball field October 1, 2025 Install top finish stone on baseball field Begin installing turf Complete turf install Complete fencing Paving around baseball field November 1, 2025 Loam & seed Complete all site furnishings Complete all miscellaneous items December 1, 2025