HomeMy WebLinkAbout06/14/2018 - A&M 1st Response - - 1429 OSGOOD STREET ' � V
H,��.
, �� ..�•,�mow,
"�° � 1 wig
100 Commerce Way
P.O.Box 2118
Woburn,MA 01888-0118
June 14, 2018 Tel:(781)935-6889
Fax:(781)935-2896
Horsley Witten Group, Inc. Re: A&M Project#: 2351-02
Janet Carter Bernardo, P.E. Site Plan and Drainage Report Review
Senior Project Manager
294 Washington Street
Suite 801
Boston, MA 02108
Dear Ms. Carter Bernardo,
This letter provides responses to the Horsley Witten Group, Inc. review letter dated May 2, 2018 for
the proposed development at 1429 Osgood Street,North Andover. The original comment is listed
with A&M's response in bold italics. The numbering is consistent with your letter.
1. Standard 1 states that no new stormwater conveyances may cause erosion in wetlands of the
Commonwealth.
a. The existing site currently sheet flows in three directions:
• West from the Project site into an existing catch basin that appears to be associated with
the drainage system in Osgood Street, also known as Rte 125, a Massachusetts State
Highway;
• Northwest towards an existing low point at the property boundary; and
• Southwest towards the unnamed stream and BVW delineated at the edge of the existing
parking lot.
The Applicant is intending to maintain these three discharge points and has proposed best
management practices (BMPs)to provide additional treatment. To verify that the proposed
grass swale located along the southwest property line will not cause erosion at the existing
headwall HW recommends that the Applicant provide the velocity calculations for the grass
swale.
Response: The Drainage Report will be updated to include velocity calculations for the
narrowest section of the grassed swale.
2. Standard 2 requires that post-development runoff does not exceed pre-development runoff off-site,
for a redevelopment project per MassDEP this standard must be met to the maximum extent
practicable.
The Applicant has reduced impervious cover to all three discharge points and the HydroCAD
modeling calculations provided indicate that the post-development peak discharge rates do not
exceed the pre-development discharge rates. The proposed HydroCAD model does not include
the proposed BMPs, including the rain gardens and grass swales proposed for water quality
treatment. This is a reasonable methodology to verify compliance with Standard 2. HW has the
following comments regarding the HydroCAD model:
a. The Existing and Proposed Watershed Plans indicate that the existing building has specific
breaks in the roof runoff. HW recommends that the Applicant provide a narrative explaining
how the roof divide was determined.
Response:ABM walked the entire interior of the building to note roof drain locations as
well as roof drain building exit locations. Most of the roof drain lines were visible. All
building drain exit locations are above grade on the exterior of the building. ABM verified
the information gathered on the inside of the building with the visible drain exits on the
civil & structural engineers • land surveyors • environmental consultants • landscape architects
exterior of the building. A&M then compared the roof drain locations with aerial images to
determine which parts of the roof drain to which drain exit locations. The majority of the
roof drains to the south, but a portion of the building drains to the north.
c. Furthermore, in accordance with Section 7.2 B.b) of the Stormwater Regulations the
Applicant should provide the analyses for the 1/2 inch storm. HW recommends that the
Applicant provide these additional calculations.
Response: The Drainage Report will be updated to include the %"Storm.
4. Standard 4 requires that the stormwater system be designed to remove 80% Total Suspended
Solids (TSS) and to treat 0.5-inch of volume from the impervious area for water quality.
b. In accordance with Section 7.2 D. b) and c)of the Stormwater Regulations the Applicant
should provide the water quality volume for the 1/2 inch storm, however it appears that the
Applicant has not provided sizing calculations for the rain gardens or provided the 1/2 inch
storm analysis. HW recommends that the Applicant provided the sizing calculations for the
rain gardens in accordance with Volume 2, Chapter 2,page 26 of the MSH.
Response: The Drainage Report will be updated to include sizing calculations for the rain
gardens. These calculations show that the proposed rain gardens do not meet the sizing
criteria of 5% to 7% of the area draining to it, as provided on the referenced page 26 of the
Stormwater Handbook. However, as described in Volume 2, Chapter 3,Page 6 of the
Stormwater Handbook, the rain gardens have been sized to be as large as possible and
remove TSS to the maximum extent practicable and are an improvement to the existing
condition.
c. HW recommends that the Applicant provide a detail for the pea stone diaphragm.
Response:A detail for the Pea Stone Diaphragm has been added to the detail sheets (Detail
8 on sheet C-502).
5. Standard 5 is related to projects with a Land Use of Higher Potential Pollutant Loads
(LUHPPL).
a. The Applicant has noted that the proposed land use is not considered a LUHPPL; however the
Layout&Materials Plan indicates that open storage bins are proposed. HW recommends that
the Applicant clarify the proposed use of the property as well as document what material will
be placed in the storage bins.
Response: The property will be a mixed-use development consisting of office space,
warehouse and contactor's yard. A portion of the site will be used for parking. The
remaining area within the fenced off area will be used for exterior material storage for a
contractor's yard, ranging from gravel to crushed stone, to granite block, to precast
concrete curbing to loam. The intent of the storage bins is they are constructed of large
freestanding walls and contain the material stored in them (crushed stone,gravel, loam,
etc.).
8. Standard 8 requires a plan to control construction related impacts including erosion, sedimentation
or other pollutant sources.
b. In accordance with Section 8.0 of the Stormwater Regulations, if a SWPPP is required per the
NPDES General Permit the Applicant is required to submit a complete copy of the SWPPP as
part of its application for a Land Disturbance Permit. HW recommends that the Applicant
provided the SWPPP to the Town for review and verify that the Erosion and Sediment Control
Criteria listed under Section 8.2 of the Stormwater Regulations is clearly referenced.
Response:A copy of a SWPPP will be prepared for review.
c. HW recommends that the size of the Fiber Roll be added to Detail 7 on Sheet C-501.
Furthermore HW recommends that the size of the siltation fence be added to the detail.
civil & structural engineers • land surveyors • environmental consultants • landscape architects
Response: The size of the fiber roll and the siltation fence have been added to Detail 7 on
sheet C-501.
9. Standard 9 requires a Long Term Operation and Maintenance (O &M)Plan to be provided.
a. The Applicant has included an O&M Plan in accordance with Standard 9. HW recommends
that the Applicant provide additional information related to the maintenance of the grass swale
and pea stone diaphragm. Furthermore the Applicant may choose to separate the narrative for
the bioretention area and the grass channel so that the plants in the rain gardens are not
mowed.
Response: The Drainage Report will be updated to include the maintenance of the grass
swale and pea stone diaphragm.
13. Miscellaneous Comments:
a. The proposed plan set including the Layout&Materials Plan, the Grading&Drainage Plan,
and the Utilities Plan illustrate subsurface trenches in the area of the existing catch basin and
Bioretention Area#2. It is not clear what these trenches are. HW recommends that the
Applicant clarify the purpose of these trenches.
Response: The trenches shown were the reserve area for the septic system. This system has
since been revised and the reserve trenches are now shown between the primary trenches.
b. As noted previously Osgood Street is a state highway and the Applicant is discharging
stormwater into the state drainage system. HW recommends that the Applicant document to
the Planning Board that permission to continue to discharge into the Massachusetts
Department of Transportation(MassDOT) drainage network will be received prior to
construction. The Applicant is reducing the flow to this catch basin as well as providing water
quality as will be required by MassDOT.
Response:Allen &Major has reached out to MassDOT to inquire what will be needed to
obtain permission to continue to discharge. Any permits necessary will be obtained.
We look forward to reviewing these comments and responses at the next Conservation Commission
and Planning Board meeting. Please feel free to contact me at my direct line of(781) 305-9434 with
any questions.
ALLENp, M JOR ASSOCIATES,INC.
Wayne KeelLer, .E.,PTOE, LEED AP
Senior Project Manager
June 14, 2018
Date
civil & structural engineers • land surveyors • environmental consultants • landscape architects