STORMWATER POLLUTION PREVENTION PLAN AND CONSTRUCTION SEQENCING PLAN
Project: 1210 Osgood Street North Andover
Client: Princeton Properties, Inc. NRP Group, Inc.
Operator: NRP Group, Inc.
SWPP Coordinator: Brenden Gilmore NRP Group, Inc. Cell Phone 978-735-2490
Plan Ref.: Erosion and Sediment Control Plan 4/20/18 Prepared by Hancock
Associates.
Date: 05-02-18
During the initial stages of site work, permanent stormwater measures as designed and detailed within
the approved site plans and final project permitting are not applicable. This SWPPP is intended to cover
the initial retaining wall, site preparation and stabilization construction operations required to reach
reasonably level and stable construction grades close to finish grades.This SWPPP has been developed
in coordination with the General Contractor, NRP Group, Inc. insuring all facets of site and building
construction are considered.This plan has been developed to insure the initial stages of site clearing and
earth movement are done in a manner that will protect the surrounding resource areas. We feel once
the walls are build and final grades achieved, potential for sedimentation will be dramatically
decreased and more standard measures can be implemented.The SWPPP coordinator will have day to
day responsibility for implementation of the plan, have daily interaction with the sub-contractors and
have the power to dictate certain and necessary measures to insure protection of the resource areas.
This document should be considered part of the approval of the North Andover Conservation
Commission, any change will require input and approval of the Conservation Agent and/or full
commission.
Best management practices (BMP)for erosion and sedimentation control are silt fence, hay bales,filter
fences, hydro seeding, and phased development. Many stormwater BMP technologies (e.g., infiltration
technologies) are not designed to handle the high concentrations of sediments typically found in
construction runoff and must be protected from construction-related sediment loadings. Construction
BMP's must be maintained.The fact that the project design utilizes modular retaining walls is being
used as an integral part of the control of erosion and sedimentation toward the surrounding environs.
In developing the construction sequencing for the proposed project, certain measures will be
implemented to minimize impacts which erosion and sedimentation could have on surrounding areas.
This section addresses items that involve proper construction techniques, close surveillance of
workmanship, and immediate response to emergency situations.The developer must be prepared to
provide whatever reasonable measures are necessary to protect the environment during construction
and to stabilize all disturbed areas as soon as construction ends.
The purpose of this document is describe the anticipated temporary and permanent soil erosion and
sediment controls and construction sequencing that will be used during the initial "Pad Ready" project
construction activities. Temporary control measures will be all those devices and practices design to
reduce, mitigate or eliminate soil erosion and sediment control during active construction activities, prior
to final project stabilization and site occupancy. Permanent control measures will be all those devices
and practices designed to reduce, mitigate or eliminate soil erosion and sediment control when
construction is completed, the site is occupied and all designed/approved stormwater infrastructure is in
place and functionally operable.
The main function and purpose of temporary erosion control practices is to prevent soil from uncontrolled
migration into existing natural resources, including streams, brooks, ponds and wetlands. As such, the
project anticipates implementing the above mentioned BMP's in the following sequence/purpose:
Sequence Purpose BMP
Passive cleaning of construction equipment Stabilized Construction Entrance(s)
1 entering and exiting the site
Perimeter surface containment and filtration Perimeter silt fence,staked hay bales and
2 devices crushed stone check dams
3 Localized point source filtration device Catch Basin silt sacks
Structural element—see approved plans Large segmental block retaining wall
4 Intended to provide a definitive separation from
both construction activities and final land use(s)
from existing natural resources
Redirect,channelize and control surface Diversion swales and interior sedimentation
5 stormwater energy/volume within disturbed and basins with pond skimmers,as appropriate
active construction zones
6 Centralize,manage and minimize potential point Stockpile stabilization and perimeter
source soil migration or erosion stockpile controls
7 Temporary surface stabilization Hydro-seeding,mulch and crushed stone
In addition to the above tangible temporary erosion control practices,there are additional good
housekeeping practices that can be performed on a regular basis in order to minimize, reduce or
eliminate soil erosion during active construction practices. These practical and common sense practices
area as follows:
A. Collect, store and monitor all onsite waste materials in a closed device, such a dumpster, barrel
or waste receptacle commensurate with waste materials composition.
B. Remove all stored waste from site on a routine basis,so as not to allow materials to accumulate
and potentially spill beyond reasonable containment or confinement devices.
C. Provide and maintain onsite sanitary waste units, having a regularly scheduled cleaning and
disposal program.
D. Provide and maintain an onsite spill prevention plan as well as spill clean-up kit.
E. Provide regularly scheduled training and information sessions for all persons onsite, including
visitors of long durations.
F. Provide and monitor centralized personal vehicle, as well as construction equipment storage
areas, including a first alert program notifying the SWPPP monitor of any known leaks, spillage
or apparent visual defects requiring repairs.
G. Do not permit any vehicle maintenance or repairs onsite
H. Do not permit any bulk fuel or petroleum storage onsite
I. Limit all chemical storage onsite to typical household volumes as usual and customary for
normal cleaning activities.
J. Implement a weekly street sweeping program of all hard surfaces within the construction
activities zone of influence,which may or may not entail offsite activities.
K. Implement a trucking inspection station that observes and monitors heavy trucking activities to
insure trucks entering or exiting the site are utilizing their load tarps/coverings and are
sufficiently clean so as not to transport unnecessary materials or debris on or off the active
construction site.
Pre-Construction Sequencing
1. Survey and flag wetlands buffer areas
2. Install wetlands signage and markings
3. Install erosion control measures per requirements- straw waddle, erosion control fence, etc
4. Schedule site inspections with Conservation Commission agent for pre-construction walk-thru
5. If necessary, make modifications outlined during pre-construction walk-thru prior to actual
construction start.
Construction Sequencing
Phase 1
Phase 1 of the construction sequencing is the area tributary to the "1" series wetlands flags at the
southeast corner of the site and partial tributary to the "2 series wetlands flags related to the retaining
wall (only) at the northwest of the property identified behind building D .This area will be worked prior
to any other work performed on site outside of mobilization and the setting of construction trailers.
1. Clear and grub vegetation only; (1) nthe area of the erosion control line, (2) proposed
temporary sediment basin 1-1, (3) sediment basin 1-2, (4) proposed retaining wall R-5, R-
4, and R-2. Note- Erosion control will be install at perimeter of subject property prior to
items 2-4 being cleared and grubbed.
2. Install construction entrance per plan.
3. Construct sediment basin 1-1, relocated sediment basin 1-2 and diversion swale
4. Begin wall installation for poured-in place wall R-4/R-5
5. Begin and install coursing at retaining wall R-2.Wall construction will run continuously
through phase 1.
6. Place wall R-4/R-5
7. Proceed with clearing and grubbing of remaining area within Phase 1.
8. Backfill retaining wall R-4/R-5
9. Stabilize all areas down gradient of the wall and loam and seed embankment.
10. Maintain and modify as necessary the diversion swales and sediment basins as fill and wall
operations proceed.
Phase 2
Phase 2 includes the area in tributary to the "2" and "3" series wetlands.
1. Clear and grub vegetation in the area of the proposed erosion control line, retaining wall R-1
and all areas identified in the ESC plan as Phase 2.
2. Start construct sediment basin 2-11 2-2 and diversion
3. Begin wall installation for two to three courses and construct sediment basins and diversion
swales behind walls as shown on detail in referenced plan.
4. Begin fill operation and advance walls higher.
5. Stabilize all areas down gradient of the wall with loam and seed.
6. Maintain and modify as necessary the diversion swales and sediment basins as fill and wall
operations proceed.
Phase 3
Phase 3 includes the area in tributary to the "3" series wetlands.
1. Clear and grub vegetation in area Phase 3 as identified in the ESC plan.
2. Begin fill operation and advance walls higher.
3. Construct sediment basin 2-3 and diversion
4. Maintain and modify as necessary the diversion swales and sediment basins as fill operations
proceed.
Phase 4
Phase 4 includes the balance of the site as this area is defined to the retaining wall and frontage of Osgood
Street.
1. Clear and grub of phase 4 will take place during phase 2.
2. Begin wall installation for two to three courses
3. Begin fill operation and advance walls higher.
4. Maintain and modify as necessary the diversion swales and sediment basins as fill and wall
operations proceed
Inspection
s
The SWPPP Coordinator shall be primarily responsible to insure stormwater inspections are scheduled,
performed and recorded. Stormwater observations or inspections may be performed by trained personal
only, usually assigned members of the SWPPP team or their assigned agent(s). All stormwater BMP's shall
be inspected or observed on a regularly scheduled basis, in accordance with the specific practice or after
every major storm event defined as one inch in a twenty—four hour period.
In general, the purpose of stormwater BMP inspections/observations is to verify the normal operations
of installed erosion control measures in accordance with approved plans/permits. All measures should
be found to be in good functional condition.
The following inspection schedule shall be used as a guide only, as additional observations may be
required depending on construction schedule, adverse weather and actual site conditions:
BMP Observation Schedule
Stabilized Construction entrance/entrance geometry,stone size,depth and
Daily
Entrance(s) cleanliness
Perimeter silt fence,staked hay
bales and crushed stone check Installation&condition,silt deposit or erosion Daily
dams
Catch Basin silt sacks Installation&condition,silt or debris deposits Bi-Weekly
Large block retaining wall Installation&condition,stability Daily
Stability,turbidity,inlet/outlet controls,silt or debris
Diversion swales and interior deposits.Sediment ponds should be drained if more than
sedimentation basins with pond half full in advance of a pending storm event. Draining Weekly
skimmers,as appropriate shall be done in a controlled manner to insure turbid
water is not discharged to the surrounding environment.
Stockpile stabilization and
Stability, perimeter controls, riels,soil migration,siltation Daily
perimeter stockpile controls
Hydro-seeding,mulch and Vegetative growth,stability,riels, material migration,
crushed stone siltation Bi-Weekly
In the event installed BMPs are compromised, damaged, missing or otherwise not functioning properly,
the observation representative shall immediate complete a Correction Action Log (see appendix) in
addition to the Observation Log, as well as verbally notify the appropriate construction representative
responsible for stormwater measures corrective actions.
Additionally, it will be encouraged to augment all SWPPP inspections/observations with photographs,
videos or plan mark-ups, as applicable. Proper, sufficient and adequate stormwater
observations/inspections logs records are critical to the resulting maintenance activities.
All inspection/observation reports/logs are to be kept on site, as required by the construction
manager/superintendent, typically within the project office(s). Duplicate copies shall be distributed to
the Owner, Operator and applicable agencies, as specified in the project approvals.
Landscaping
Maintenance
The SWPPP Coordinator shall be primarily responsible to insure stormwater maintenance activities are
identified and recorded with the project specific Observation or Correction Action Log(s), as applicable.
Additionally, the SWPPP Coordinator or his/her assigned agent(s) shall immediately verbally notify the
appropriate construction representative responsible for stormwater measure maintenance, as well as
follow up with written notification. BMP maintenance notification shall be specific to the applicable
stormwater measure.
Stormwater BMP maintenance shall be performed by the site contractor who installed the practice or
assigned agent(s) by the construction manager/superintendent. All Stormwater BMP maintenance shall
be performed in accordance with the approved plans/permits and manufacturer specification,whichever
is more stringent.Similar to stormwater observations, maintenance activities, including BMP replacement
or augmentation shall be performed by trained professionals.
The following maintenance schedule shall be used as a guide only, as additional maintenance may be
required depending on construction schedule, adverse weather and actual site conditions:
BMP Maintenance Schedule
Regrade—backdragorsimilar(trafficdependent) Daily
Stabilized Construction Refresh stone material(traffic dependent) Weekly
Entrance(s) Replace(traffic dependent) Monthly
Perimeter silt fence,staked hay
bales and crushed stone check Remove silt deposit, Fill erosion/riels,adjust placement Bi-Weekly
Remove& replace blinded or damaged practice (as needed)
dams
Remove silt or debris deposits Bi-Weekly
Catch Basin silt sacks Remove& replace blinded or damaged practice (as needed)
Large block retaining wall Installation&condition,stability Daily
Diversion swales and interior Remove silt or debris deposits Weekly
sedimentation basins with pond Clean&clear inlet/outlet devices (as needed)
skimmers,as appropriate Fill, re-grade,stabilize & re-establish practice
Stockpile stabilization and
perimeter stockpile controls Supplement and replace as necessary to contain sediment. Weekly
Hydro-seeding,mulch and Any areas that are completed and can be stabilized should
As needed
crushed stone be immediately treated.
If necessary,the SWPPP Coordinator shall be primarily responsible to maintain the integrity of the project
SWPPP, including all edits, revisions and alterations.
Landscaping
Landscaping shall occur as soon as practical to provide permanent stabilization of disturbed
surfaces.
2. If the season or adverse weather conditions do not allow the establishment of vegetation,
temporary mulching with straw, wood chips weighted with snow fence or branches, or other methods
shall be provided.
3. A minimum of 4 inches of topsoil shall be placed and its surface smoothed to the specified
grades.
4. The use of herbicides is strongly discouraged.
5. Hydro seeding is encouraged for steep slopes. Application rates on slopes greater than 3:1 shall
have a minimum seeding rate of 5-Ibs/1000 SF. A latex or fiber tackifier shall be used on these slopes at
a minimum rate of 50 lbs. of tackifier per 500 gallons of water used.
Training
The SWPPP Coordinator shall be primarily responsible to create, implement and manage the SWPPP
training program. The SWPPP training program will be developed to educate and inform individuals
about the project specific SWPPP. This education program will include project awareness of project
permit approvals, contracts, SWPPP applicability, purpose, responsibility, implementation and
maintenance.
There shall be two (2) levels of SWPPP training. The first and less invasive will be SWPPP awareness
training, applicable to all full time persons actively working within the project limits, including
management and ownership. The second level will be more in depth and focus on the purpose, use,
implementation and maintenance of the project specific SWPPP. All individuals who receive second level
training are required to sign the certification form, indicating they are certified by the SWPPP Coordinator
and are eligible to perform SWPPP team duties, as assigned by the SWPPP Coordinator.
SWPPP Training Certification
"I certify under penalty of law, that I have been trained and have reviewed this APEX Center SWPPP
document and all attachments, including appendices. I understand and acknowledge personal
responsibility to implement, monitor, observe and maintain the project specific intended purpose of this
SWPPP document and its supplemental information, including approved plans and permits. I accept
potential future SWPPP duties and responsibilities, as assigned by the SWPPP Coordinator, if called upon
to do so in accordance with the standard forms and documents provided herein. I am aware that there
are significant penalties for submitting false information, including the possibility of fine and
imprisonment for knowing SWPPP violations."
Name: Date:
Title:
Signature:
Corporate Certification (NRP Group, Inc.—Owner/Operator)
"I certify under penalty of law, that this SWPPP document and all attachments were prepared under my
direction or supervision,in accordance with a system designed to assure that qualified personnel properly
gathered and evaluated the information submitted herein. Based on my inquiry of the person or persons
who manages the system, or those persons directly responsible for gathering the information, the
information submitted is, to the best of my knowledge and belief, true, accurate, and complete. I am
aware that there are significant penalties for submitting false information, including the possibility of fine
and imprisonment for knowing violations."
Name: Date:
Title:
Signature:
APPPENDIX
The purpose of this section is to provide supplemental information.
• Construction General Permit
• Inspection Log, Corrective Action Log, Annual BMP Maintenance Log
• SWPPP Plan