HomeMy WebLinkAbout2026/03/03 - Response to 1st Stormwater Peer Review - 200 Bridle Path /,Iandover 1 East River Place
consultants Methuen,Massachusetts 01844
inc. Tel.(978)687-3828
www.andoverconsultants.com
March 3, 2026
Ms. Jean Enright, Planning Director
North Andover Planning Department
120 Main Street
North Andover, MA 01845
RE: 200 Bridle Path
North Andover,Mass
Response to Peer Review Memorandum#1
Dear Ms. Enright and Members of the Board:
We are in receipt of a review letter for the above referenced project dated February 27, 2026 prepared by the Board's Peer
Reviewer, Horsley Witten Group (HW). We have reproduced HW's comments below in italics with our response noted
below in bold.
Comment I —The Applicant has included erosion controls on the site plan including a 9-inch straw wattle on the north
and east side of the project area and a stockpile location on the west side of the house. HW recommends that the
Applicant provides a limit of work line on the site plan confirming the total area of disturbance. and includes erosion
controls around the stockpile.
Response—The site plan has been revised to include a clearly delineated limit of work line, as recommended. The
total area of disturbance within the limit of work is approximately 15,880 square feet. In addition, erosion control
measures have been added around the stockpile location to further minimize potential sediment impacts during
construction.
Comment 2—The Applicant has proposed a temporary construction access around the north side of the house. HW
recommends that the Applicant provide a detail of the construction access. If feasible, HW recommends that the Applicant
evaluate whether the construction access can be around the south side of the house furtherfrom the BVW. Note 4 on the
Site Plan indicates that the existing driveway will be used as the construction entrance. The plan view and the note are
not consistent. HW suggests that the Applicant considers construction matting or other measures to minimize the tracking
of sediment onto the driveway and offsite per§250-25.E. (13) of the North Andover Code.
Response— stabilized construction entrance detail has been added to the site plan as recommended, and the plan
notes have been revised to clarify that the existing driveway will be used for construction access. The feasibility of
relocating the temporary construction access to the south side of the house was evaluated; however, nearly the
entire site lies within the 100-foot buffer zone, and the limited area between the existing dwelling,previously
disturbed areas, and the bordering vegetated wetland constrains access options. Given that the majority of
construction activities will occur on the northerly side of the site,the proposed access location represents the least
environmentally impactful option.
Comment 3— The Applicant has noted that the project includes proposed work consisting of two small additions to an
existing single-family residence and is therefore exempt from the Massachusetts Stormwater Management Standards
pursuant to 310 CMR 10.05(6)(1). The Applicant has not provided stormwater calculations for the proposed work.
However, the Applicant has provided a stormwater trench adjacent to the proposed expanded driveway. HW recommends
that the Applicant provides runoff calculations for the existing and proposed conditions to ensure that the stone trench is
properly sized for the increased impervious area and that the proposed improvements do not create adverse conditions to
downstream neighbors.
Page 1 of 3
Civil Engineers•Land Surveyors•Land Planners
P:\25\25-05\Docs\letters\2026-03-03_response to peer review comments.docx
and over
consultants
inc.
Response—As noted in the comment,the proposed improvements are exempt from the Massachusetts Stormwater
Management Standards pursuant to 310 CMR 10.05(6)(1) and are not subject to State or local stormwater
requirements.Nevertheless, a crushed stone infiltration trench has been incorporated into the site plan as a best
management practice to offset a de minimis increase of approximately 340 square feet of impervious area. This
increase consists of a minor driveway expansion (142 square feet) and a rear addition (198 square feet); the front
addition is proposed over an existing paved driveway and therefore does not result in a net increase in impervious
cover.
The proposed crushed stone trench provides approximately 77.6 cubic feet of storage,which is sufficient to
accommodate approximately 2.7 inches of runoff from the additional impervious area.As designed,the trench will
mitigate any potential increase in runoff and will not create adverse drainage conditions for downstream
properties.
Comment 4—HW recommends that the Applicant clarify the total increased impervious area. HW could not confirm the
impervious area to be removed and the total proposed impervious area to be constructed. HW recommends that the
Applicant provides a stormwater calculation comparing the existing and proposed impervious areas and the runoff for
each. HW further notes that a roof drain is indicated on the Site Plan discharging towards wetland flag SA. HW
recommends that the Applicant clarify if this roof drain will remain after construction and if it is causing any erosion to
the adjacent BVW.
Response—The total increase in impervious area associated with the proposed project has been clarified on the
revised site plan. The project results in a de minimis net increase of approximately 340 square feet of impervious
area, consisting of a 142-square-foot driveway expansion and a 198-square-foot rear addition. The proposed front
addition is located entirely over an existing paved driveway and therefore does not increase impervious cover.No
existing impervious surfaces are proposed to be removed.
Although the project is exempt from State and local stormwater management standards, a comparison of existing
and proposed impervious areas and associated runoff has been provided to demonstrate that post-construction
conditions will not result in adverse impacts. The proposed crushed stone infiltration trench provides
approximately 77.6 cubic feet of storage,which is sufficient to accommodate approximately 2.7 inches of runoff
generated by the net increase in impervious area.
With respect to the roof drain shown on the site plan,the roof drain is proposed to remain following construction
and discharges to a previously disturbed area. Based on site observations,the discharge has not resulted in erosion
or adverse impacts to the adjacent bordering vegetated wetland.No changes to the roof drain discharge location
are proposed,and existing conditions will be maintained.
Comment S—The Applicant has noted the existing soil conditions as Hydrologic Soil Group (HSQ)B/D per the Natural
Resources Conservation Service (NRCS). HW recommends that the Applicant provides the sizing calculations for the
stormwater trench for this soil type. A soil test pit within the footprint of the trench would be appropriate to confirm the
infiltration rate. The Board may consider requiring a test pit conducted prior to construction with documentation
provided to the Board as a special condition.
Response—As noted previously,the proposed project is exempt from the Massachusetts Stormwater Management
Standards; however,the crushed stone infiltration trench has been included as a conservative best management
practice to mitigate the de minimis increase in impervious area. The trench has been sized based on available
NRCS soil mapping indicating Hydrologic Soil Group B/D, using storage volume rather than infiltration rate as
the controlling design criterion.As designed,the trench provides approximately 77.6 cubic feet of storage,which is
sufficient to accommodate approximately 2.7 inches of runoff from the net increase in impervious area,
independent of infiltration performance.
Page 2 of 3
P:\25\25-05\Docs\letters\2026-03-03_response to peer review comments.docx
and over
consultants
inc.
No soil test pit is proposed at this time, as the trench is not required for regulatory compliance and is intended
primarily as runoff storage and attenuation. If infiltration rates are lower than anticipated due to localized soil
conditions,the trench will continue to function as a subsurface storage feature and will not adversely affect
adjacent resource areas.The Applicant understands that the Board may, at its discretion,require confirmation of
subsurface conditions prior to construction and would comply with any such condition if imposed.
Comment 6—The Applicant has provided Erosion and Sedimentation Control elements on the Site. It does not appear
there are any notes for stabilization on the plans or in the supplementary information. HW recommends that the Applicant
revise the plans as needed to clarify how the site will be stabilized. HW further recommends that the Applicant indicates
how the landscaping will be restored at the end of construction.
Response—The plans have been revised to include general erosion and sedimentation control notes addressing site
stabilization as recommended. These notes specify that all disturbed areas will be stabilized upon completion of
construction activities with loam and seed.Any temporary erosion control measures will remain in place until
stabilization is achieved and will be removed upon approval by the Planning Board and Conservation Commission.
Comment 7—HW notes the Applicant has proposed a stone trench along the driveway. The Applicant does not mention
how this will be maintained or how this affects the proposed runoff. HW recommends that the Applicant provides
information in the supplementary package explaining how the trench should be maintained after construction and at
what frequency for the benefit of the homeowner.
Response—The crushed stone trench is designed as a passive stormwater best management practice requiring
minimal maintenance.Maintenance guidance for the homeowner has been added to the revised site plan as part of
the detail and includes periodic inspection of the trench and contributing drainage areas,particularly following
major storm events.Maintenance activities consist of removing accumulated sediment and debris (e.g.,leaves,
litter)from the trench surface,ensuring runoff can enter the trench unimpeded, and repairing or replacing stone
as needed. Inspections are recommended at least annually and after significant rainfall events, as part of routine
residential landscaping maintenance.When properly maintained,the trench will continue to provide runoff
storage and attenuation for the minor increase in impervious area without adversely affecting site drainage or
adjacent resource areas.
If you have any questions concerning these latest revisions, or require anything further, please feel free to contact me at
your convenience.
Sincerely,
Andover Consultants Inc.
0
Dennis A. Griecci,P.E., LEED AP
Enclosures
Page 3 of 3
P:\25\25-05\Docs\letters\2026-03-03_response to peer review comments.docx