HomeMy WebLinkAboutCorrespondence - 858 GREAT POND ROAD 5/12/2011 Sullivan Engineering Group, LLC
Civil Engineers&Land Development Consultants
May 12, 2011
Town of North Andover Conservation Commission
c/o Jennifer Hughes
1600 Osgood Street
North Andover, MA 01845
Re: 858 Great Pond Road, North Andover
Construction Update
Ms.Hughes;
On behalf of the owner,David&Gay Tracy, I am submitting this letter to inform you that the Tracy's intend
to demolish the existing dwelling structure entirely, and then rebuild their new house utilizing the existing
foundation. During the public hearing process for the Notice of Intent,the intention was to gut the existing
dwelling and construct a second story. After the Order of Conditions was issued,the various builders bidding
on the project ALL felt that the existing structure should be razed.
Please note that this modification does not affect ANY of the design features on the approved Site Plan. The
construction access points are the same, the erosion control location is the same, and there is no change to the
approved building footprint. The site grading and drainage mitigation for this project remain the same. The
only excavation activity will be for the foundation for the approved addition off of the rear of the house and
for the construction of the third garage bay(approved).
If you should have any questions or require additional information please feel free to contact me.
Very Truly Yours,
Jack Sullivan, P.E.
Cc: David&Gay Tracy, Owners
22 Mount Vernon Road — Boxford,Massachusetts 01921 — (978)352-7871-Phone — 978352-7871 -Fax
Annecrest Building Corporation
P. O.Bog 290
Boxford,MA 01921
Date: May 23, 2011
To:North Andover Conservation Commission
Re: Orders of Condition DEP File No. 242-1509
For David and Gay Tracy
858 Great Pond Road
North Andover, MA 01845
In accordance with the above Order of Conditions please be advised of the following:
The On-site Construction Supervisor and Contractor: Bill Constantine
Annecrest Building Corporation
81 Herrick Road
Boxford,MA 01921
Tel# 978-887-4991
The Erosion Control Monitor: Jack Sullivan,P.E.
Sullivan Engineering Group,LLC
22 Mount Vernon Road
Boxford,MA 01929
Tel# 978-352-7871
The following are dates for the sequence of construction:
June 1, 2011---------------- -Demolition of main house down to first floor deck
June 8, 2011---------------- -Excavation work for new partial foundations
June 13, 2011----------------Foundation installations
June 21,2011----------------Foundation backfilling
Sept 8,2011------------------Roof drains and drywell tank installations
Oct 4,2011-------------------Re-vegetation and final stabilization
Oct 28,2011------------------Final paving
LR� f Vim"446'24
Bill Constantine,President