HomeMy WebLinkAboutCertificate of Compliance - 1030 JOHNSON STREET 4/11/2003 Town of North Andover
Office of the Health Department
Community Development and Services Division � 4
27 Charles Street
North Andover,Massachusetts 01845
acffus
Sandra Starr Telephone(978) 688-9540
Public Health Director Fax(978)688-9542
TOWN OF NORTH ANDOVER
BOARD OF HEALTH
CERTIFICATE OF COMPLIANCE
DATE OF COMPLIANCE
04/11/03
This is to certify that
the individual subsurface disposal system
constructed O or repaired (X)
by
Peter Breen
at
1030 Johnson Street
has been installed in accordance with the provisions of Title V of the State Sanitary Code and with the
North Andover Board of Health regulations.
The Issuance of this certificate shall not be construed as a guarantee that the system will function
satisfactorily.
IL
Brian J.d-aGrasse
Health Inspector
BOARD OF APPEALS 688-9541 BUILDING 688-9545 CONSERVATION 688 __ __. a n vivuvv o88-9535
'lTOW� Or' ,10RXH ANDOVER SE�V:kCrZ DISPOSAI. S)..!'- E\,r
I-STALLA•rioN CE• RTIEI( :ATION
"The uncersisaed hereI,v cerifv that the Sewage Disposal Syste-a i ! Cor.su,ictcd;
repaired!: y
bY_ T �..
located at 1030). sb H i\V SO
was installed in 66nfermance with the North Andover Board of Hc:ith a-fproved plan
System Design Pe,,rat'= dated. :with an approved design
low of nallens per day The materi als;use,4 were in conformar.:e xIrh those
specined on the approved plan; the systenn was instated in accordarce ,,,ith the provisions
of 31 10 CMR 1 5.000, Title 5 and local regular ors, and the final Qradir. agrees
substantially with the approved plan. :ail work- is accurateiv represented ;)c the ?.s-built
which has been submitted to the Board e:Health.
Bed inspection •crate: ff Z_(-e
Engineer R::iresefn-,a ive-
Final inspection date:
Engsee: Representat:e
4
Lnstalier: — of �qs _ �ic.m: Date: ---
y HARD
Lesion EnQineer,;r' Cw�iiP Date --
U
TANGA
Fs
S90VAL <
i
" 1
1
INSPECTION CHECKLIST FOR SEPTIC SYSTEMS J
Yes NO [ itls
A. Bottom of Bed C
1. Excavation to proper depth
2. With trenches,sides of excavation are beneath B horizon
3. Edge of excavation specified distance from foundation,etc.
Comments:
B. Retaining Wall
1. Wall height and width as specified
2. Waterproofed
3. Wall minimum 10'to leaching facility
4. Wall meets specifications of plan
Comments:
C. Building Sewer
1. Pipe diameter minimum 4"
2. Schedule 40 pipe
3. Watertight joints
4. Inlet to tank cemented
5. Slope minimum 0.01 or 1/8"per foot minimum
6. Pipe properly set on compact firm base -
7. Pipe laid on continuous grade in straight line
8. Cleanouts precede all change in alignment and grade
9. Manholes at any 90°change
10. 10' minimum offset to water line
Comments:
D. Septic Tank
I. Level
2. 1,500 gal minimum
3. Gas baffle present on outlet
4. Manhole to grade
5. Manholes over center and each tee
6. 3-20"manholes
7. Inlet tee minimum 12"under invert
8. Outlet tee minimum 14"under invert
9. Outlet line cemented
10. Air space 3"above tees
11. 2"-3"drop from inlet to outlet
12. Pipe set
13. Compact base with 6"of 3/4"crushed stone under tank
14. Tank is watertight
Comments:
I
I
i
Yes NO
E. Pump Chamber
I. If separate from tank,compact base with 6"of/4"stone underneath
2. Minimum 2"pipe to d-box if gravity system
3. 20"access manhole
4. Tank level
5. Watertight
6. Tank size agrees with plan specification
7. Manhole to grade
8. Check valve and bleeder hole present
9. Alarm in building on separate circuit
10. Alarm functions
11. Manual operating switch
12. Pump delivers liquid to d-box
Comments:
F. Distribution Box
1. D-box level
2. Minimum 0.IT'(2")drop from inlet to outlet
3. Minimum 6"sump
4. Outlet pipes show equal distribution
5. Compact base with 6"of stone beneath box
6. Box is watertight
7. All lines cemented with hydraulic cement
8. Schedule 40 pipe -
Comments:
G. Soil Absorption system
1. All stone double-washed-3/4"- 1 V2"
-pea stone
Bucket test done?
2. Minimum 2"of pea stone above distribution lines
3. Minimum 6"stone beneath pipe
4. Distribution lines capped or connected together
5. Grading meets 3:1 slope
6. Minimum of 9"of fill graded over system
7. Toe of slope stops minimum 5' from edge of property; if not,then swale.
Comments:
H. Leach Trenches
1. Minimum 2 trenches
2. Length of trenches agree with plan. (Max. length 100')
3. Width of trenches agree with plan-Minimum 2';maximum-41.
4. Vent present if X50 feet or specified
5. Distance between trenches minimum 4' and maximum of 6'
6. Minimum distance between trenches 10'
7. Pipe slope minimum 0.005 or 6"per 100'
8. Depth of trenches below outlet invert minimum of 6". -
Yes NO
9. Pipes set on stable base.
Comments:
i
I. Leach Field
1. Maximum length of field 100'
2. Pipe slope minimum 0.005 or 6"per 100'
3. Separation between pipe 6'maximum
4. Pipes connected at end
5. Separation between adjacent fields 10'minimum
6. Pipes set on stable base
7. Maximum 4'separation from edge of field to first line
8. Minimum two distribution lines
9. Maximum perc rate 20 mpi
Comments:
I Leaching Pits
1. Minimum inlet pipe 4"
2. Pits of concrete
3. Sidewall between 12"and 48"wide
4. Access manholes on each pit
5. Pipes cemented with hydraulic cement
Comments:
K. Final Grade
1. Slope over soil absorption system minimum 0.02
2. All system components covered by at least 9"soil
3. Cover soil free of stones larger than 6"
4. Grading slopes away from dwelling
5. No areas over system that may pond —